News Release Date: September 28, 2023
Contact:
Public Affairs Office, 360-565-3005
“We are working to maximize efficiency at every step to ensure Hurricane Ridge reopens as quickly as possible. During this closure, we will also install temporary facilities and prepare for winter operations. Barring unforeseen circumstances, we anticipate being able to enjoy winter on the Ridge with the community by early December” said Jeff Doryland, Olympic National Park's Acting Facility Manager.
The current construction schedule for Hurricane Ridge is:
- October 11-12: The temporary trailers for Hurricane Ridge winter operations will arrive.
- October 15: Good Man Sanitation Inc., under contract with the National Park Service, will remove the portable toilets that have served visitors throughout the summer season. A robust restroom trailer, capable of withstanding the Ridge’s harsh winter conditions, will serve winter visitors.
- October 31: The trenching in the Hurricane Ridge parking lot will be complete. As of September 28, electrical and fiber lines have been installed. Crews continue to work Monday through Thursday to install wastewater and freshwater lines, and re-pave areas.
- November: Crews will install and connect utilities to the restroom trailer and staff office trailer.
For more information and updates on the restoration projects at Hurricane Ridge, visit: Hurricane Ridge - Post-Fire - Olympic National Park (U.S. National Park Service) (nps.gov)