Parkway projects in Roanoke, Virginia, scheduled to conclude during the 2022 visitor season

Subscribe RSS Icon | What is RSS
Date: April 5, 2022
Contact: BLRI Public Affairs

September 20, 2022 Update: 
The project completion date for the Roanoke slope repair project underway at milepost 127.9 has been extended into spring 2023 due to a culvert failure. Please visit the updated news release for more information and a detailed detour map.


August 01, 2022 Update:

The Roanoke River Bridge project (Milepost 114.7) is complete as of August 01, 2022 after a year of work and is now open to visitors for public use. As a reminder, MP 121-136 are still closed due to slope failure. Detour signage will be modified to display the current detour and will remain in place for the duration of the project. Roanoke Area Road Closure - Blue Ridge Parkway (U.S. National Park Service) (nps.gov)


June 9, 2022 Update:

REMINDER:  The Roanoke section of Parkway from U.S. 220 (milepost 121.4) to Adney Gap (milepost 135.9) which was previously open to cyclists and pedestrians is now fully closed to all visitors and recreation of any kind. Due to heavy equipment and contractors working in the area, a full closure is in place and enforceable under 36 CFR 1.5(f).    

Additionally, the Roanoke River Bridge at Milepost 114.7 is still anticipated to open by the end of June.


Original News Release:
Roanoke Area Road Closure - Blue Ridge Parkway (U.S. National Park Service) (nps.gov)
National Park Service officials today announced that multiple road projects on the Blue Ridge Parkway near Roanoke, Virginia, are scheduled to be complete in the coming months. Specifically, the rehabilitation of the Roanoke River Bridge, at Milepost 114.7, is expected to be finished in June; and repairs needed to stabilize slope failures near mileposts 119.7 and 127.9 are expected to conclude by the end of September.
While work is underway and until repairs are complete, current, signed detour routes will remain in place. The detour route around both projects extends from VA Route 24 at Washington Avenue (milepost 112.2) to Adney Gap at US 221 (milepost 136.0); and access to Explore Park remains available from the south via US 220 (milepost 121.4). Behind closed gates, the Parkway is closed to all uses including motorists, cyclists, and pedestrians. The public’s cooperation with these closures helps support an efficient work schedule and the safety of staff, visitors, and the contractor. 
The Roanoke River Bridge closed during the summer of 2021 for a long-scheduled, major rehabilitation project. The National Park Service and Federal Highway Administration identified this project as a priority in 2015, as part of the ongoing, multi-year road maintenance planning cycle for the Blue Ridge Parkway. This project included concrete repairs to bridge piers, reconstruction and drainage repairs to approach areas, removal of existing asphalt surface and waterproofing membrane, installation of new waterproofing membrane and asphalt surface, and repainting of the steel super structure of the bridge. 
A spring 2020 storm resulted in a full road failure roughly one hundred and fifty feet (150') in length at Milepost 127.9. Geotechnical and roadway experts have designed and planned a series of repairs for this emergency project, including installation of soil anchors and reconstruction of the fill slope, to stabilize the area and restore safe access.
At the time of the large slide, Parkway staff discovered another smaller slope failure at milepost 119.7. Repairs needed at this location will also take place this season and be managed using single-lane traffic controls. Park visitors in this section should anticipate delays up to 15 minutes, a shifted lane alignment, warning signs, new pavement markings and a regulatory speed reduction to 35 mph.