News Release

NPS
Subscribe
![]() |
Contact: Brendan Wilson
VICKSBURG, Miss. – On March 3, 2025, the National Park Service (NPS) will begin repair work on Grant Circle and a section of Union Ave in the northern portion of the park. Following heavy rainfall in early 2020, these roads suffered catastrophic failures necessitating closure to ensure visitor safety. These roads have been closed since that time. Repairs are scheduled to be completed by November 2025. No additional road closures will be needed to complete these repairs. Construction areas will be closed to all vehicular and pedestrian traffic during the project.Work will include:Install new stormwater control infrastructure and management features
Slope and Soil Stabilization:
- Install reinforced soil slope walls and install gabion baskets
- Install Rammed Aggregate Piers
- Install Load Transfer Platform
- Turf replacement/establishment
- Roadway excavation and embankment construction
- Remove and replace pavement on roads and Thayer’s Approach Bridge
- Remove and replace curbs
- New pavement striping
For more information and updates on the project.
Last updated: February 27, 2025