Repairs To Alluvial Fan Ypsilon Lake And Lawn Lake Trails In Rocky Mountain National Park

Subscribe RSS Icon | What is RSS
Date: August 9, 2016
Contact: Kyle Patterson, (970) 586-1363

The Director of the Intermountain Region, National Park Service (NPS), signed a decision document earlier this summer that enabled Rocky Mountain National Park (RMNP) to conduct repairs to the Alluvial Fan, Ypsilon Lake, and Lawn Lake Trails that were damaged in the September 2013 flood. Repair work has already begun on some sections.  It will be a few years before the reroutes and repairs are completed on all three trails.

Following the September 2013 flood, RMNP prepared an Environmental Assessment (EA) to evaluate alternatives and the potential impacts associated with reestablishing five trails that were badly damaged during the flood: Twin Sisters, Aspen Brook, Alluvial Fan, Ypsilon Lake, and Lawn Lake. The purpose of the EA was to identify potential travel routes while protecting natural and cultural resources and preserving wilderness character. Park staff anticipate that a decision for the Aspen Brook and Twin Sisters trails will be made sometime in 2017. 

The NPS selected Alternative B, Establish and Maintain a Travel Route (the NPS preferred alternative) for the Alluvial Fan, Ypsilon Lake, and Lawn Lake trails because the alternative best met the purpose and need for the project as well as the project objectives. A description of the selected action for the three trails follows. 

Lawn Lake Trail – A new trail is being constructed around the four trail sections damaged or washed out, and limited improvements will be made to an existing informal trail. Trail tread will be about 3 feet wide, with trail clearing limits 6 feet wide by 10 feet high. Pedestrian and equestrian use will be allowed. 

Ypsilon Lake Trail –A new timber foot bridge has been constructed across the Roaring River. New trail approaches on either side of the river are being constructed, with a trail tread about 3 feet wide, and trail clearing limits approximately 6 feet wide by 10 feet high. Pedestrian and equestrian use will be allowed on the trail, but equestrian use will not be allowed on the bridge, instead a horse stream crossing will be established. 

Alluvial Fan Trail – A new accessible trail will be constructed between the existing east and west parking lots with a new bridge across the Roaring River. An accessible overlook trail to Horseshoe Falls will be constructed. A 150-foot portion of the accessible trail will extend into designated wilderness to reach the overlook. The trail tread will be about 5 to 6 feet wide, with trail clearing limits approximately 8 feet wide by 8 feet high. Only pedestrian and accessible use will be allowed. 

For more information about Rocky Mountain National Park, please visit www.nps.gov/romo or call the park's Information Office at (970) 586-1206. 



Last updated: August 9, 2016

Park footer

Contact Info

Mailing Address:

1000 US Hwy 36
Estes Park, CO 80517

Phone:

970 586-1206
The Information Office is open year-round: 8:00 a.m. - 4:00 p.m. daily in summer; 8:00 a.m. - 4:00 p.m. Mondays - Fridays and 8:00 a.m. - 12:00 p.m. Saturdays - Sundays in winter. Recorded Trail Ridge Road status: (970) 586-1222.

Contact Us