September 17, 2025 Update

September 17, 2025 Posted by: K. Karnes

Construction work is progressing, despite some delays due to high winds and waiting on material deliveries. The bridge is now welded to the bearings on each side. The receiving tower and the remaining launch truss have been removed and staged for demobilizing. The back, cheek, and wing walls have been set and are being welded at the east abutment.

Workers are now preparing to begin the final stages of thermosiphon installation and activation, along with backfill and grading at the east abutment. As is typical in late summer, the slide has seen some extreme movement recently, and the temporary access route across the slide that had been in place below the bridge is no longer passable.

Depending on the weather, construction season is expected to continue for another few weeks and will likely wrap up sometime in October. Check back for at least one more blog post at the end of the season.


Looking east at the full bridge from the west abutment.Photo courtesy of FHWA

Two works wearing safety vests and helmets kneel next to large metal beams.

Inspecting welds using magnetic particle testing.
Photo courtesy of proHNS


Sparks fly as a welder wearing a full face helmet kneels next to the back wall of the bridge abutment.

Rail welding the backwall of the abutment.
Photo courtesy of proHNS

Last updated: September 17, 2025

Park footer

Contact Info

Mailing Address:

PO Box 9
Denali Park, AK 99755

Phone:

907 683-9532
A ranger is available 9 am to 4 pm daily (except on major holidays). If you reach the voicemail, please leave a message and we'll call you back as soon as we finish with the previous caller.

Contact Us