June 3, 2025 Update

June 03, 2025 Posted by: K. Karnes

Despite some high winds over the weekend which suspended operations for a few hours, the contractor has completed erection of the next bay to the west (bay L3 to L2) and bolt torque verifications.

This week, they plan to complete the final two bays of the bridge (L2–L1 and L1–L0).

The partial bridge that has been constructed extends out over the landslide and a steep, rocky mountainside. A crane places a metal beam at the end of the bridge.Hanging the L2–L1 NS bottom chord.
Photo courtesy of FHWA