July 3, 2025 Update

July 03, 2025 Posted by: K. Karnes
Last week, the contractor used a helicopter to move equipment and materials to the west side and began assembling the receiving tower at the west abutment.

Pre-assembly of the launch truss continued at the mile 44 staging area. They also began removing the crane, crane mats, and other equipment from the main truss of the bridge to make room for the launch truss.

Several trusses of the bridge extend out over the landslide above the viewer against a bright blue sky.A view of the bridge from below.
Photo courtesy of proHNS

A helicopter carries a large box attached to a long line below the helicopter.
Flying equipment over to the west side.
Photo courtesy of proHNS

Last updated: July 3, 2025

Park footer

Contact Info

Mailing Address:

PO Box 9
Denali Park, AK 99755

Phone:

907 683-9532
A ranger is available 9 am to 4 pm daily (except on major holidays). If you reach the voicemail, please leave a message and we'll call you back as soon as we finish with the previous caller.

Contact Us