July 13, 2026 Update

July 13, 2026 Posted by: K. Karnes

The busy summer season is rolling right along and construction is continuing as expected. The project remains on track to be completed this summer. Please note that the Polychrome area is still an active construction site and the bridge is not yet open to pedestrians or bicyclists—it is expected to open in late summer, but no date is set at this time.

In the past week, contractors completed the timber facing for the retaining wall on the east side of the bridge and painted the friction coating on the bridge deck. Rock scaling is scheduled to begin next week and will help reduce the rockfall risk on slopes above the road in the Polychrome area.

At the Bear Cave landslide, progress is underway on re-routing the road away from the slide. The cut for the new alignment is complete and the new road has been established.


A large wooden wall built into a steep rock slope, next to the east end of the bridge.The completed retaining wall on the east end of the bridge.
NPS Photo / J. Hubbard


The gravel road splits into two routes for a brief section, one route sinks lower and one is built higher into the hillside.The new road alignment at Bear Cave.
NPS Photo / J. Hubbard

Last updated: July 13, 2026

Park footer

Contact Info

Mailing Address:

PO Box 9
Denali Park, AK 99755

Phone:

907 683-9532
A ranger is available 9 am to 4 pm daily (except on major holidays). If you reach the voicemail, please leave a message and we'll call you back as soon as we finish with the previous caller.

Contact Us