Past Construction Projects

3 bathroom structures in a parking lot.

NPS Photo

Rebuild Nauset Light Beach Bathhouse

Completed August 2022

Nauset Light Beach is one of the national seashore's busiest beaches. In summer, it is the first parking lot to fill, attracting over 1,000 beachgoers daily.

The need to replace the Nauset Light Beach facilities reached a critical point when accelerated erosion caused by winter storms endangered the bathhouse. The facilities were removed in response to an erosion rate of 12-15 feet per year over the past dozen years.

Construction of a new facility at the far end of the parking area was completed in August 2022. It includes a new septic system, restrooms, showers, and lifeguard support facilities.

 
Three images of Highland Light in progress, one before construction, the second wrapped in scaffolding, and the third wrapped in scaffolding and wrapping to protect the exterior.
Progress of Highland Light rehabilitation project.

NPS Photo

Rehabilitation of Highland Light

Completed in 2022

Highland (Cape Cod) Light is the oldest and tallest light on Cape Cod, standing at 66 feet. Originally built in 1797 and replaced in 1853, the current masonry structure was completed in 1857. The lighthouse was listed on the National Register of Historic Places in 1987 based on its architecture and engineering. The light can be seen from 40 miles at sea, and it continues to serve as a significant official aid to navigation.

This project will restore ventilation to the masonry tower to eliminate the build-up of moisture over many decades that has led to corrosion and the development of large cracks in the masonry. Tasks include elimination of the modern cement-like material between tower walls that inhibits air flow, removal of non-breathable exterior coating, repair or replacement of corroded metal components, new windows, masonry repairs, and application of a new exterior coating.

 
Image of stairs and ramp leading up to visitor center.
New ramp installed at Province Lands Visitor Center.

NPS Photo

Province Lands Visitor Center Preservation

Completed in 2022

A facelift is underway at Province Lands Visitor Center in 2021-2022. The building’s position on a high bluff overlooking the Atlantic Ocean, and impacts from wind, sand, and salt spray necessitated exterior repairs. Work includes a new roof; prepping and painting trim, wood fascia, and wood board & batten siding; stabilizing, repairing, and repointing loose block on the retaining wall to the basement; and removing, repairing, re-installing, and resealing portions of the exterior panels at the upper level observation deck. Interior painting and new carpeting throughout the building complete the rehabilitation.

A new ramp has made the building accessible. Previously, stairs were required to access the visitor center and observation deck, where there are commanding views of the Atlantic, the Gulf of Maine, dunes, and the chance to spot whales in spring and summer.


 
Construction materials sit outside bathroom building.
Construction at Coast Guard Beach bathroom.

NPS Photo

Restroom Renovations

Completed in 2021

2021 was the year of restroom renovations! The satellite bathroom at the Salt Pond Visitor Center, Coast Guard Beach restrooms, Marconi Beach restrooms, and Race Point Beach restrooms received numerous upgrades. Restroom upgrades varied by location, but included replacement of restroom fixtures, lighting, plumbing, and electrical components with safe, more efficient items, as well as repairs to deteriorated structural materials. Exterior upgrades were also included.

 
Maintenance staff rebuild sections of the swamp's boardwalk.
NPS maintenance crews work to rebuild sections of the Atlantic White Cedar Swamp boardwalk.

NPS Photo

Repairs to Atlantic White Cedar Swamp Trail

Completed 2020

The Atlantic White Cedar Swamp Trail meanders through one of the most unique and intriguing areas on Cape Cod. The swamp is an isolated remnant of an ecosystem created after the last ice age and now normally found in mid-Canada or further north.


A favorite visitor destination, this boardwalk trail through a white cedar swamp trail requires repair and replacement of wooden boardwalk sections that have become deteriorated. 800 lineal feet of trail will be repaired. As a Centennial Challenge project, this work will be accomplished through both federal funds and a 50% match from Friends of the Cape Cod National Seashore. Getting ahead of these repairs before the trail becomes unsafe will allow for continued visitor access in the future.

 
Visit our keyboard shortcuts docs for details
Duration:
43.8 seconds

Time lapse video of the Herring Cove parking lot realignment project completed in 2019. Video courtesy of Classic Site Solutions.

 

Realignment of Province Lands Road and Relocation of Herring Cove North Parking Lot

Completed August 2019

The goal of this project is to provide sustainable access to the beach by relocating key facilities inland from the eroding shoreline. NPS developed a long-term plan for management of the north public use area in a way that considers the potential for future erosion, sea level rise, coastal flooding during storm events, and long-term sustainability; that restores natural systems to the greatest extent possible; and that also retains the recreational experience to the greatest extent possible.

To maintain long-term visitor access, a new parking lot of similar dimensions is being built 350 feet inland of the former parking lot, representing a retreat of man-made materials from the coastline and reestablishing a natural shoreline. This retreat is responsive to best available estimates of shoreline change. The new parking lot will be built at an elevation of 15-16 feet (two feet above the current FEMA base flood elevation), which accounts for expected sea level rise and continental subsidence as well as the level predicted for major hydrologic coastal flood event having a predicted 100-year occurrence.

 
Yellow barn building
Penniman barn adjacent to Penniman House.

NPS Photo

Rehabilitation of Captain Penniman Barn

Completed 2019

Significant structural work and repairs to the deteriorated 1882 Captain Penniman House Barn are required. In fall 2014, park maintenance staff discovered serious structural deterioration on the east side of the barn. The crew placed temporary shoring timbers to stabilize the east side pending permanent repairs, and the barn was closed to the public. In addition to the structural deterioration on the east side of the barn, its gutter and drainage systems have failed, causing accelerated moisture damage.


Work includes structural repairs to the east wall, including new sill plates and posts; replacement of rotted fascia, soffits and gutters; and repairs or replacement of trim, cupola, shed roof and posts, doors and windows, wall sheathing and clapboards. In addition, the barn will be prepped and painted, and the mansard roof will be prepped and stained.

The 1868 Penniman House and Barn are the centerpieces of the 100-acre Fort Hill Rural Historic District. Home to whaling captain Edward Penniman, the 2-1/2 story, 2,750 square foot house features intricate architectural details, an elaborate cupola, and bold colors in the Second Empire style. The house and barn sit prominently at the entrance to the historic district.

The house and barn were listed on the National Register of Historic Places in 1976. The seashore’s interpretive staff and volunteers conduct popular interpretive tours through the house twice to three times weekly from late spring through early fall. In 2014, nearly 1,100 people attended the tours. The Fort Hill area of Cape Cod National Seashore is a primary park resource and receives the highest annual visitation at the seashore with the exception of its beaches.

 
White building with green shutters and red roof.
Completed Coast Guard Station project.

NPS Photo

Exterior Rehab of Coast Guard Station

Completed 2019

The Nauset Coast Guard Station building overlooks the Atlantic Ocean at Coast Guard Beach in Eastham. It was constructed on an overlook of the Atlantic Ocean in 1936, to be used by the United States Life Saving Service in its early years. The historic building is now part of Cape Cod National Seashore, and has annual visitation of over 432,000 people. For the past 80 years it has been adaptively reused as an early park headquarters, then employee housing, next as a residential education facility, and finally, as a support facility for the Parks as Classrooms program. Its location adjacent to the beach and salt marsh makes it an ideal location for educational activities and discussions about beach processes, salt marsh resources, global climate change and sea level rise, erosion, and threatened and endangered species. Its historic nature supports lessons about storms, shipwrecks, life-saving, and maritime industries.


Over sixty years of use and constant exposure to wind, sand and salt spray has led to a need for major repair to the exterior. Rehabilitation is necessary to protect the integrity of this National Register-eligible building. This project will repair damage to the exterior of the Coast Guard building, re-glaze and repaint the windows, paint all exterior surfaces, remove and replace the siding on the building with cedar shakes and repair the fire escape. Also included is re-grading of the grounds adjacent to the building to correct drainage problems.

 
Head of the Meadow Bike Trail extension entrance at High Head.
Head of the Meadow Bike Trail extension entrance at High Head.

NPS Photo

Rehabilitation of the Head of the Meadow Bike Trail

Completed 2017

This project includes the rehabilitation of the 2 mile long Head of the Meadow bike trail in Truro, Massachusetts. A critical component is mitigation of disturbance to the sensitive natural resources in the wetlands of the Pilgrim Heights area and public safety of the visitor using this trail. The bike trail will be widened to meet current bike trail standards. A new hot asphalt overlay across the whole trail surface, new signs, and pavement markings will be installed. Beach grass and other native plantings and sand fence will be installed to stabilize sandy areas along the bike trail.


This project also includes extending the existing Head of the Meadow Bicycle Trail by creating an approximately mile long connection along Old King’s Highway, an ancient way on Cape Cod since the time Massachusetts was a colony, which leads to the ocean and surrounding attractions. The connection will greatly improve recreational bicycle trail use opportunities in the Town of Truro by making a major loop that would afford various destination possibilities.

This is a major park secondary route in the Outer Cape Bicycle/Pedestrian Master Plan, as well as an interim primary route while funds for the “spine” route, a Separated Multi-Use Path on Route 6, are being sought. It will connect the Truro Highlands to both the planned primary "spine" route and secondary route network.

Last updated: January 4, 2023

Park footer

Contact Info

Mailing Address:

99 Marconi Site Road
Wellfleet, MA 02667

Phone:

508-255-3421
To contact NPS Law Enforcement or report an incident, please call the 24-hour dispatch: 617-242-5659. In the event of an emergency, call 911.

Contact Us