In March 1965 Superintendent Liles met with Regional Director Garrison,
staff members, and Casey to review the building's working drawings and
overall construction program. As on-site "architects' representative,"
Taliesin selected Charles Gordon Lee, a former apprentice who had established
private practice in Denver. [32] The bidding process for the construction of the Headquarters
began with notices advertising the "partly reinforced concrete and partly
structural steel frame" building, and a May 24 press release invited
potential contractors to obtain copies of plans, specifications and
a photograph showing "an artist's conception" of the building. [33]
Gordon Lee and WODC staff attended a June 17 "pre-bid conference" for
construction companies interested in the project. Five days later, Kunz
Construction Company of Arvada, Colorado, submitted the lowest bid of
$652,871.95. The ground-breaking ceremony took place on July 16, and
the Park Service issued a "start work order" the next week. [34] Shortly after, Liles transferred to a different park
and was replaced by Superintendent Fred J. Novak.

Figure 58. The concrete and stone
panels were cast on the site and lifted into place by crane, November
1965.
(Photo by Miller. Courtesy Rocky Mountain National Park archives.)
|
The Headquarters' unique materials and construction required all sorts
of special provisions, not to mention the use of building techniques
unfamiliar to most contractors. Monthly superintendent's reports and
Park Service snapshots (by WODC architect Jerry Riddell) capture the
drama of the construction process, as cranes lifted the heavy walls
into place. The concrete and stone walls were a puzzle of one hundred
and one pre-cast concrete panels in sixty-four different sizes, one
of which weighed 65,000 pounds. The challenge was to fit each panel
into its proper location. In April, "the contractor was advised to correct
the alignment of a concrete column consisting of panels PC/3-4-5," which
was "out of plumb by 4 1/2"." [35] Even such a slight maladjustment could result in a
serious structural problem and required immediate correction. Sections
were cast in wooden forms assembled on-site; large stones were placed
in the forms, concrete was poured around them, and then pebblesor
gravel aggregatewere sprinkled on the exposed wet mortar. This
method of creating a "naturalistic" wall originated during the construction
of Taliesin West in 1937-1939, when Wright was searching for a method
of building with regional stones that could not be cut easily like granite
or limestone. [36] "Face rocks" were selected
for flat surfaces, thickness, and color. These were set into wood frames
along with smaller stones, or "rubble," to hold them in place while
a mixture of concrete and sand was used to fill the crevices. [37]
By varying the size of the stones and laying them in rough horizontal
rows, Wright created the illusion of cut-stone masonry. At the Headquarters,
auditorium panels included electrical wires and other utilities imbedded
in concrete along with the stones. Once the concrete hardened, the panels
appeared to be composed of natural stone, but the seams between panels
were also a visible design element, creating both horizontal striations
resembling geologic strata and a sense of the building's structure.
According to former apprentice Bruce Brooks Pfeiffer, the horizontal
concrete lines also originated in the Arizona desert and were perfected
at Taliesin West. He recalls
. . . An outing the Fellowship made to northern Arizona
into one of the canyons which had once been under water, the deep,
horizontal grooves in the stone canyon walls caused by water erosion
greatly appealed to Mr. Wright. On his return to camp he instructed
the apprentices building the walls to insert triangular strips of
wood stretching in thin lines on the inside surface of the wooden
forms prior to placing stones and pouring concrete. When the forms
were removed the indentation of the horizontal strips left an impression
within the concrete surface of the wall, creating yet another element
with which the sun could make deep shadow lines across the mosaic
wall. [38]
At the Headquarters, the use of lichen-covered pink fieldstone from
the nearby town of Lyons heightened the ornamental effects. As Tom Casey
remembers, the stone had been left in an abandoned quarry established
by the government for use in Denver's first federal courthouse. The
architects were delighted to find leftover red sandstone the thickness
of stairs, now suitably weathered and broken into smaller chunks. They
had only to gather the stone and haul it to the site. [39]

Figure 59. The building's steel framework,
as seen under construction in January 1966.
(Photo by Lockwood. Courtesy Rocky Mountain National Park archives.)
|
The November 18, 1966, Estes Park Trail announced that the Headquarters
employed a "structural steel truss system" on the second floor. The
architects called this dynamic and complex pattern of triangles, formed
of hollow steel tubes and thin metal sheets, "architecturally exposed
bare structural steel." Sections of tubes were welded together to form
the triangular skeleton of the design and the Cor-ten steel welded to
either side. Steel-stamped spandrel panels were attached directly to
the exterior walls. A similar stamped sheet metal facia encircled the
edge of the roof. This complicated mixture of structure and surface
ornament proved to be one of the most problematic aspects of the design.
Taliesin had to special order the material as needed because the supplier,
U. S. Steel, did not warehouse the required type and only manufactured
it in one mill. The steel was blasted to a white hot state to achieve
the desired color effect, which required allowing the material to oxidize
(rust) for a period of one to two years. Cor-ten, high carbon steel,
was a new, self-sealing product that never required painting. [40]
The designers chose Cor-ten both for its low maintenance and for its
rich color, which worked with the desired earth tone palette and the
surrounding environment. The steel typically rusted to a warm purple
in the city, but at high altitudes without excessive pollutants, it
turned a deep brown. In its final aged state, the steel was said to
resemble tree bark. One of U. S. Steel's promotional ads includes a
photograph of the Headquarters next to a tree with the caption, "this
building is painting itself!" Despite pressure from the design office
in Washington, D.C., slow production of the steel resulted in construction
delays. [41]
The Headquarters was half complete by January 11, 1966, when union
officials from the Denver Building Trades visited the site to speak
with James O'Shea, acting project supervisor. A Mr. Nilander and his
partner asked questions about pay rates, overtime wages, subcontractors
and job classifications, promising to continue their interrogation the
next week. Although they did not return, a picket line of employees
from Sheet Metal Workers Local #9 formed near the site on January 17.
Park Service officials met with union representatives and learned that
the problem lay with the contractors handling the heating and air conditioning
systems. For some time, the union had been picketing all projects associated
with Croy Brothers Heating and Air Conditioning, Inc. The steel workers,
plumbers and electricians chose not to cross the line for a few days,
but arrangements were made with their respective unions to allow the
resumption of work. At the time, the incident caused little more than
an unanticipated delay, but in retrospect, it foreshadowed a history
of serious deficiencies in the building's air circulation systems. The
lack of a typical forced air cooling system was specified by Superintendent
Liles, who believed air conditioning an extravagance, particularly at
over 7,000 feet. [42]
Over the next few months, the contractors placed concrete floors with
terrazzo finish, installed window walls, completed electrical and plumbing
work, and built up the roof installation. The pink terrazzo was laid
with gold adonized aluminum seams, the colors carefully chosen to add
warmth to the interior. Window casings were of steel obtained locally.
In addition to the attention lavished on interior surfaces, the Taliesin
apprentices employed a Wrightian technique of dividing interior space
in their use of an elaborate partition system. The basic drawings of
the first and second floors included only the permanent walls around
utilities and bathrooms; the remainder of the building was left open
space. Additional drawings specifically devoted to the interior partition
system show the space divided into the chosen office arrangement. The
typical office partitions were gypsum board with a corrugated paper
core. Anodized aluminum studs stretched the height of the walls about
every four feet. The upper few feet of most partitions were glass, sometimes
filling a triangular space, with the gold aluminum continuing up to
the ceiling as a mullion. Doors were red oak veneer but solid wood to
the core. In some of the fancier offices, red oak wood panels covered
the gypsum board. Although the walls give the impression of permanency,
their potential for change adds to the flexibility of the plan, not
to mention the "breaking of the box." Whether or not park employees
were intended to move the walls frequently is unknown, but one current
ranger did successfully re-configure his office space at a recent date.
[43] Wright used the partition system in all
of his office buildings, and Casey recalled such flexibility in the
Sunday school at Wright's Greek Orthodox Church (1956) as well.
At the height of excitement over the Headquarters in the fall of 1966,
architect Victor Hornbein met with the superintendent to discuss preliminary
drawings for the new West Side Administration Building. Although superintendent's
reports indicate that Hornbein's plans were approved and even admired,
the extant facility (later named the Kawuneeche Visitor Center) appears
to have been designed by the Park Service's San Francisco Planning and
Service Center. It is unclear whether or not collaboration took place,
but Hornbein's name never appears on the final drawings. In any case,
the Park Service was intrigued by Hornbein's preliminary designs, and,
perhaps, by the Wrightian aspect of his work. A Denver native, Hornbein
was an advocate of Wright's principles and had written about his architecture.
His work in the Denver area includes two buildings that exemplify a
Wrightian range of designthe Frederick R. Ross Branch Library
(1951) and the Boettcher Conservatory at Denver Botanic Gardens (1964
). The library emphasizes horizontal lines in a colorful mixture of
brick and glass, while the conservatory is a bubble of seemingly woven
concrete that manages to appear appropriate in its garden setting. Having
made a reputation for himself with local buildings, and a recent splash
at the botanic garden, Hornbein was an exciting choice as architect
of the park's final Mission 66 structure. [44]
Although considering the design of a third new visitor center, the
superintendent was still occupied with a variety of issues at the Headquarters
as the building entered its final months of construction. Park staff
and members of Kunz Construction gathered in his office on May 3 to
discuss defective road paving and problems with "ceiling lighting, air
return, upper floor and fireplaces." [45] Taliesin did not take part in this meeting, perhaps
because it resulted in some minor change orders relating to lighting,
the buzzer system, relocation of the audiovisual control panel, and
information desk alterations. By August 1966, the estimated completion
date for the Headquarters was mid-September, but a "pre-final" inspection
near the end of the month revealed two hundred and twelve items requiring
attention. Nevertheless, the final inspection of the building took place
on October 21. Approval was contingent on smoothing the uneven terrazzo
floors in two rooms. Although "many deficiencies" remained, the Headquarters
was accepted in November contingent on their correction. Park Service
officials and staff began moving into the building at the end of the
month. Kunz Construction was still fulfilling its part of the contract
in early January, with minor repairs and alterations, which included
modifying the heating system. Final payment on the building had not
yet been made in April, as preparations were made for its dedication
on June 24, 1967.
As the Headquarters' dedication approached, Park Service planners were
busy with the design and construction of the West Side Administration
Building. An excellent example of Mission 66 style and planning, the
visitor center was organized according to a standardized visitor circulation
pattern. Upon approaching from the parking lot, visitors were immediately
confronted with the restrooms to the right and a path to the visitor
center to the left. A natural stream flowed under the bridge between
the restrooms and lobby. Inside, the lobby space featured a large information
desk surrounded by items for sale and small exhibits, a map, and relief
model. Exhibit and audio-visual rooms were envisioned as a future wing
of the building, to be entered from the right side of the lobby. [46]
In the interim, this space featured an outdoor patio and pool made by
the stream. The lobby was discreetly connected to a rectangular administration
wing hidden in the back along with employee parking. Although the visitor
center has little in common with the Headquarters, both buildings are
unabashedly modern and also manage to blend into their respective park
environments. The West Side Administration Building drawings included
a "design statement," declaring a desire to "reflect the vertical forms
as found in the adjacent lodgepole forest," and noted the choice of
"wood and stone materials throughout structure to relate to the natural
environmental phenomenon at the area." The building's simple vertical
wood framework is punctuated by floor-to-ceiling sections of glass.
The final work on the landscaping of the Headquarters began in the
spring and continued through the building's dedication. The park's new
resident landscape architect, James O'Shea, worked on the exterior lighting
in May and June to produce field layouts and inspections. The west entrance
road was staked and graded. O'Shea's other responsibilities included
examining the building and concrete curbs. In August, the park issued
a change order to insure exposed aggregate finish on the curb and gutters.
Work on the planting plan for the Headquarters, which involved mapping
the area and researching plant material, occupied O'Shea during the
spring of 1967. He may have filled the three roof planters installed
in the center of each side of the auditorium. [47]
Despite progress with the landscaping, a few technical problems remained
to be solved. The heating and air conditioning system installed by Croy
Brothers was operating so poorly that a mechanical design company was
recommended as a consultant for the firm.
CONTINUED