Replace Edwards Ferry, Dargan, & Fifteen Mile Creek Bridges

A concrete and wood vehicle bridge crosses the grassy canal prism
The existing bridge at Fifteen Mile Creek that is to be replaced as part of this project.

NPS | Joe Reed, Park Engineer

1) Edwards Ferry (mile 30.8)

  • Towpath - OPEN starting September 7, 2024

  • Boat Ramp, Parking Lot - OPEN starting September 7, 2024

2) Dargan Bend (mile 64.9)

  • Boat Ramp, Parking Lot, Towpath - OPEN

3) Fifteen Mile Creek (mile 140.8)

  • Boat Ramp, Parking Lot, Campground - OPEN

The park plans to replace three public vehicle bridges at Edwards Ferry, Dargan Bend, and Fifteen Mile Creek. Both the bridges at Dargan Bend and Fifteen Mile Creek show signs of deterioration and have reached the end of their service life. As a reminder, users should abide by any posted load restrictions when crossing any bridges in the park. At Edwards Ferry, the temporary bridge, previously installed as an interim repair measure, will be removed and replaced with a permanent structure during this project.

The project aims to increase visitor safety and provide a more sustainable method of accessing these recreational areas by removing the existing bridges and replacing them with new foundations and steel/wood superstructures. These new bridges are designed for modern vehicles loads that will better serve park operations, emergency responders, and park visitors. 

 
 

FREQUENTLY ASKED QUESTIONS (FAQs)

What is the need for the project?

The existing bridges at Dargan Bend and Fifteen Mile Creek are experiencing significant deterioration and have reached the end of their service life. The bridge at Edwards Ferry is a temporary bridge previously installed as an interim measure while awaiting a permanent structure. To prevent future concerns and to ensure the safety of visitors and NPS staff, it is critical that these structures are replaced.

What does the project include?

The project consists of work removing the existing vehicular bridges at Dargan Bend and Fifteen Mile Creek, as well as the temporary steel spanner bridge at Edwards Ferry. These bridges will be replaced with new multi-beam steel bridges with steel beams, timber decking, and wood railings that will convey pedestrian, vehicular, and recreational boater traffic.

Additionally, an existing culvert and retaining walls beneath the roadway at Edwards Ferry will be rehabilitated as part of this project. The existing stacked stone masonry wingwalls will be repaired or rebuilt so that their characteristic matches the original. The asphalt approaches to the bridges will also be repaved prior to completion of the project.

 
A newly reconstructed wooden bridge crossing a canal
The newly reconstructed bridge over the Canal in Little Orleans, MD, providing access to the Fifteen Mile Creek Campground, boat ramp, and recreation area.

NPS | C&O Canal Professional Services Division

 
A steel spanner bridge crosses the masonry walls of a lock with water in the canal
Temporary steel spanner bridge at Edwards Ferry that is to be replaced with a permanent bridge as part of this project.

NPS | Joe Reed, Park Engineer

Where will the project take place?

This project will take place at Edwards Ferry (mile 30.8), Dargan Bend (mile 64.9), and Fifteen Mile Creek (mile 140.8).

When will the project begin and end?

The project is anticipated to begin Summer 2023 and continue through Fall 2024, weather dependent.

During excavation early on in the construction phase at Edwards Ferry, historic bridge abutments were found below existing ground surface, which necessitated a redesign of the new bridge to minimize the impacts to those historic features.

How will this project impact park visitors?

Through traffic on the towpath will remain possible for pedestrians via local detour routes.

How will this project benefit park visitors?

Once the project is complete, the new bridges will improve visitor safety by providing an updated and more reliable method of accessing the park’s recreational areas for pedestrian, vehicular, and recreational boater traffic. The adjacent historic structures in the project areas will also be protected and preserved for the enjoyment of future generations.

How will this project impact natural and cultural resources?

Every project the NPS executes undergoes review by a multidisciplinary team to ensure compliance with Section 106 of the National Historic Preservation Act (NHPA), National Environmental Policy Act (NEPA), and other federal, state, and local laws.

What is the park doing to protect those resources during the project?

NPS resource protection experts, engineers, and the contractor’s team will be monitoring the bridge, stone, and towpath work in these recreation areas, along with contractor’s operations and visitor safety during the project with the goal of safely protecting the environment surrounding the project. Every project undertaken by the NPS is conducted in compliance with the National Environmental Protection Act (NEPA), the National Historic Preservation Act (NHPA), and other regulations.

How is the project funded?

The contract for the replacement of the Edwards Ferry, Dargan Bend, and Fifteen Mile Creek bridges was awarded in March 2023 for $3 million and was funded from the National Park Service’s Federal Lands Transportation Program.

Who can I contact if I have further questions regarding the project?

Additional questions are to be directed to the park headquarters at 301-739-4200.

 
A wooden vehicle bridge crosses over a dry canal prism
The newly installed bridge at Dargan Bend.

NPS | Joe Reed, Park Engineer

Last updated: September 6, 2024

Park footer

Contact Info

Mailing Address:

142 W. Potomac St.
Williamsport, MD 21795

Phone:

301-739-4200

Contact Us