Replacement of Culvert 82 Bridge

A body of water lays before masonry ruins left from a culvert and bridge that washed out.
The remnants of Culvert 82 over Little Catoctin Creek that will be spanned by a new bridge as part of this project.

NPS | Susannah Noppenberger, Park Engineer

The towpath at Culvert 82 (Mile 52.51) is OPEN.

The park plans to replace the bridge over the remnants of Culvert 82 (mile 51.51) at Little Catoctin Creek. The previous bridge was washed out during a flash flood event in May 2018 . A temporary low water crossing bridge was installed by the National Park Service (NPS) in 2019. This temporary bridge remained open as the detour route for the duration of this project. At the conclusion of the project, the temporary bridge will be removed.

The project's aim is to increase visitor safety and re-establish continuity of the towpath that was breached during a large magnitude flash flood in May 2018.

The project focused on the replacement of the previous bridge that spanned Culvert 82. No repairs to the historic culvert were done as part of this project.

 
 
A brown metal bridge spans the towpath trail across the remnants of a masonry culvert
The Culvert 82 Bridge - July 2024

NPS | C&O Canal Professional Services Division

 

CURRENT DETOURS AND CLOSURES

The towpath over Culvert 82 and Little Catoctin Creek (MM 52.51) is OPEN.

FREQUENTLY ASKED QUESTIONS (FAQs)

What is the need for the project?

The towpath at Culvert 82 over Little Catoctin Creek has been breached since May 2018 due to flash flooding. A temporary low water crossing bridge was installed by the National Park Service (NPS) in 2019. However, this bypass is frequently under water after heavy rains. This project is critical to ensure the safety of visitors and restore continued access to the towpath.

What does the project include?

The project consists of installing a new steel truss bridge with timber decking, placing two concrete abutments with micropiles, and replacing a drainage pipe. At the conclusion of the project, the temporary low water crossing bridge will be removed.

 
A low wooden bridge crosses the Little Catoctin Creek
Temporary low water crossing at Little Catoctin Creek that detours visitors around the project site. This bridge will be removed at the completion of the project.

NPS | Stephanie Spencer

Where will the project take place?

This project will take place at Culvert 82 (mile 52.51), approximately 2.5 miles downstream from the Brunswick Boat Ramp. Access for construction along the towpath will be from the NPS gate near Brunswick, MD – downstream to the work area.

When will the project begin and end?

The project began late Fall 2023 and continued through Summer 2024.

How will this project impact park visitors?

To facilitate the work, the towpath at Culvert 82 (mile 52.51) is OPEN.

How will this project benefit park visitors?

Once the project is complete, the new bridge will provide a safer method of crossing over Little Catoctin Creek.

How will this project impact natural and cultural resources?

Every project the NPS executes undergoes review by a multidisciplinary team to ensure compliance with Section 106 of the National Historic Preservation Act (NHPA), National Environmental Policy Act (NEPA), and other federal, state, and local laws.

What is the park doing to protect those resources during the project?

NPS resource protection experts, engineers, and the contractor’s team will be monitoring the bridge and towpath work in this area, along with contractor’s operations and visitor safety during the project with the goal of safely protecting the environment surrounding the project. Every project undertaken by the NPS is conducted in compliance with the National Environmental Protection Act (NEPA), the National Historic Preservation Act (NHPA), and other regulations.

How much does the project cost?

The contract for the replacement of the Culvert 82 Bridge was awarded in March 2023 for $1 million and was funded from the National Park Service’s Federal Lands Transportation Program.

Who can I contact if I have further questions regarding the project?

Additional questions are to be directed to the park headquarters at 301-739-4200.

 
A stream runs through the remnants of a washed out masonry culvert
Existing remnants of the failed Culvert 82 and breach in the towpath above Little Catoctin Creek.

NPS | Joe Reed, Park Engineer

Last updated: July 18, 2024

Park footer

Contact Info

Mailing Address:

142 W. Potomac St.
Williamsport, MD 21795

Phone:

301-739-4200

Contact Us