Herring River Tidal Restoration Project

Current View of Chequessett Neck Dike and Rendering of Final Bridge Design

A dike crosses over a river. A dike crosses over a river.

The image on the left shows the current dike as built in 1909 and the right image shows the rendering of the final project design of the bridge when the tide gates are fully open.
NPS Photo/Kristin Vinduska and NPS Graphic

 
 

Project Benefits

 

Project Area and Elements

A map showing the Herring River project area with labels of specific locations. A legend shows the extent of monthly mean spring tides, the outline of the full project area, and the Cape Cod National Seashore boundary. A map showing the Herring River project area with labels of specific locations. A legend shows the extent of monthly mean spring tides, the outline of the full project area, and the Cape Cod National Seashore boundary.

Two maps show the Herring River project area. The map on the left has labels for siginificant locations within the project area including Upper Bound Brook, Lower Bound Brook, Upper Herring River, Mid Herring Riiver, Duck Harbor, Lower Pole Dike Creek, Lower Herring River, Mill Creek, and Upper Pole Dike Creek. An area highlighted in blue shows the extent of the monthly mean spring tides. A red outline shows the full project area and a green outline shows the Cape Cod National Seashore (CCNS) boundary. The map on the right shows the same area with same blue highlighted area and outlines. This map describes the project elements including elevating low roads, enlarging Bound Brook Road culverts, building Pole Dike Creek Water Control Structure, removing High Toss Road, building the Mill Creek Water Control Structure, and building the Chequessett Bridge. 
NPS Maps

 

 

Project Elements

The Herring River Restoration Project (HRRP) includes many complex elements to achieve the goals of this project. This consists of public infrastructure construction projects, vegetation management, and restoration of natural salt marsh elevation and hydrology. Reintroduction of tidal flow is a phased process that will occur over several years. The primary reasons to implement the project in this manner are to avoid unexpected or sudden irreversible changes to the river and Wellfleet Harbor and to allow monitoring of the system so that unexpected and/or undesirable responses can be detected, and appropriate remedial actions taken. 

Computer simulations (i.e. modeling) of the current and future conditions of the river, form the basis of design requirements for the overall restoration program, including the need for infrastructure modifications and protection of existing infrastructure and structures from restored tidal flow. The hydrodynamic modeling is a computerized simulation of the flow direction, velocity, duration, and depth within the river driven by tides in Cape Cod Bay, wind, rain, and external conditions, and the configuration of water control structures (i.e. tide gates). The primary design objective is to facilitate natural tidal hydrology within the river while protecting roads and structures from regular and storm-driven tidal impacts.  

These summaries and more information, including detailed engineering plans, can found in the permit application narratives on the Friends of Herring River website: Friends of Herring River Restoration Project Updates.

 
Map of Herring River and Duck Harbor Vegetation Clearing for 2024, with cleared spaces indicated by red polygons on the map.
Vegetation clearing for Duck Harbor and the surrounding areas has been completed for 2024.

NPS

Project Updates

Mill Creek Water Control Structure
Construction on the Mill Creek water control structure has begun and is expected to be completed in early to mid 2025. Project-specific updates related to that work can be found here.

Vegetation Management
Vegetation clearing has been completed for the year at Duck Harbor and surrounding areas. There will be other areas selected to begin clearing next year.

 

Resources for More Information

 

Photo Galleries

 
 

Meetng Notice

Regulatory Oversight Group
Herring River Restoration Project (EEA Number 14272)
Wellfleet, MA


The Regulatory Oversight Group for the Herring River Restoration Project will meet virtually on Monday, January 6, 2025, at 2 pm via Zoom. Members of the public can participate in the meeting by using the following link:

Join Zoom Meeting
https://us06web.zoom.us/j/86401994349?pwd=vWkaoaCfpSBqncrUbJ15mdACOpNQbx.1
+1 312 626 6799
Meeting ID: 864 0199 4349
Passcode: 903940

The Regulatory Oversight Group (ROG) was established in accordance with the Certificate of the Secretary of Energy and Environmental Affairs on the Final Environmental Impact Report for the Herring River Restoration Project (EEA Number 14272). The Regulatory Oversight Group consists of representatives of local, county, state and federal agencies and the Mashpee Wampanoag Tribe. The Herring River Restoration Project is being undertaken by the Town of Wellfleet, MA and the National Park Service Cape Cod National Seashore. Phase 1 of the project is currently being implemented and upon completion will restore 570 acres of former tidal wetlands. The agenda for the January 6th meeting is below.

1. Welcome and Introductions
2. Phase 1 Restoration Project Updates – Carole Ridley, Project Coordinator
• Construction
• Marsh Management
• Permitting
• Fundraising
• ROG questions, discussion, guidance
3. Marsh Management Pilot Projects – Tim Smith, Restoration Ecologist, Cape Cod National Seashore
• Berm Removal Pilot Project
• Mill Creek Salt Marsh Restoration Pilot Project (with Kevin Kroeger, Supervisory Research Chemist, US Geological Survey)

Last updated: December 4, 2024

Park footer

Contact Info

Mailing Address:

99 Marconi Site Road
Wellfleet, MA 02667

Phone:

508-255-3421
To contact NPS Law Enforcement or report an incident, please call the 24-hour dispatch: 617-242-5659. In the event of an emergency, call 911.

Contact Us