2.4.1 Progress Meetings

Construction Management Representative (CMR)

  • Convene progress meetings on weekday and time agreed upon at pre-construction conference.
  • Conduct meeting using agenda (see Division 01 Specifications Section 013100) and ensure minutes are taken and routed promptly.

Template:

Sample:

Document Control:

  • Electronic copy of meeting minutes are routed to Park Superintendent, Project Manager (PM), Contracting Officer Representative (COR), CMR, Contract Specialist (CS).