2.8.1 Final Inspection

Construction Management Representative (CMR)

  • Coordinate with contractor, park, and Contracting Officer Representative (COR) to set final inspection date.
  • Draft and sign response letter to contractor providing final inspection date using template below.
  • Conduct final inspection and incorporate a final sequentially numbered, priced punch list into the draft Letter of Substantial Completion; and send electronic version to COR.
  • The NPS Accessibility Inspector will conduct a final accessibility inspection. The inspector will utilize the NPS Final Accessibility Inspection Report below. The contractor must correct any deficiencies identified in the inspection.
  • Before occupancy can occur on building projects the Regional Structural Fire Management Officer (RSFMO) has to have accepted the fire and life safety systems and issued a preliminary certificate of occupancy. Utilize forms below as required.

Guidelines:

Forms:

  • 2.8.1D AS-5 Above Ground Piping Acceptance Test
  • 2.8.1E BF-1 Backflow Prevention Assembly Test
  • 2.8.1F CO-1 Certification of Occupancy
  • 2.8.1G FA-2 Fire Alarm Record of Completion and Acceptance
  • 2.8.1H FSD-1 Fire Smoke Damper Acceptance
  • 2.8.1I AS-4 Underground Piping Acceptance Test
  • 2.8.1J NPS Final Accessibility Inspection Report