MANZANAR
Historic Resource Study/Special History Study
NPS Logo

CHAPTER EIGHT:
CONSTRUCTION AND DEVELOPMENT OF THE MANZANAR WAR RELOCATION CENTER — 1942-1945 (continued)

STATUS OF CONSTRUCTION AT MANZANAR WHEN THE WAR RELOCATION AUTHORITY ASSUMED ADMINISTRATION ON JUNE 1, 1942

When the War Relocation Authority assumed administration of Manzanar on June 1, 1942, George H. Dean, a Senior Information Specialist in the WRA's office in San Francisco, undertook assessment of conditions at the relocation center. After his inspection, he issued a lengthy report describing both the administrative operation and the physical conditions of the camp which then housed 9,671 evacuees. Among his observations on the physical conditions and status of construction at Manzanar were the following:

The War Relocation Authority, in acquiring the Manzanar project, took over a plant consisting of 724 wooden barracks buildings, a hospital group and a children's center. . . .

In many instances, especially on those days when heavy arrivals of evacuees occurred, assignments to the barracks have been made perhaps inevitably in an indiscriminate manner, resulting in serious overcrowding in some of the buildings. Many cases existed of eight and ten persons of various ages being housed in a single apartment, sometimes two and three separate family units. This has resulted in a health and sanitation problem, and in some scattered instances in an unsatisfactory moral situation.

Floors and walls of the barracks reflected considerable deterioration, large cracks developing from the drying out of the lumber under the heat and low humidity in this area. They were, and are, rough and difficult to keep clean, and on some days as high as nine complaints have been received at the engineering office on floors giving way. Linoleum and felt padding had been ordered for installation in all barracks and mess halls, and the installation in the messes had been completed on June 1. The remainder of the work of laying the linoleum in the barracks will be performed by Japanese labor, but this had to be postponed as white union labor would not work on the project simultaneously with Japanese labor.

Barracks were turned over to the evacuees without steps and it has been necessary to construct 2,232 sets of steps on which work was about 75 percent complete when lumber supplies were shut off. Considerable difficulty has developed from plumbing valves sticking. Because of the peculiar type of valve used, it is hard to replace them. On the whole, however, the amount of plumbing disorder is not abnormal for a community of this size.

Electrical installations and overloading of the lines because of the large usage of electrical devices, such as irons, heaters and radios, by the evacuees have created a serious fire hazard in all of the barracks. Wiring is openly strung in the buildings. The evacuees have more than five and a half miles of electrical cord connected to electrical accessories. Most of this cord is in good condition at the present time, but with continual overloading of the wires it will deteriorate abnormally quickly. Numerous daily blowing of fuses is evidence of the overloading. . . .

The water supply is not entirely completed. . . . Tests conducted in May revealed a rather high degree of pollution and a trace of E. coli. There has been a comparatively high incidence of dysentery within the project and studies were being made to determine whether this was attributable to pollution of the water supply. . . .

Dishwashing equipment was inadequate and unsanitary. Additional equipment had been ordered prior to June 1 and is in the process of installation. Dr. Harrison, chief of the 5th Public Health District, described the dishwashing situation as the most serious health menace in the project. The supply of hot water, both in the kitchens and wash rooms is adequate under normal usage but is insufficient to meet peak loads.

Sewage from the project is siphoned under the aqueduct east of the camp and spread out over the open land. A disposal plant was commenced by the army prior to June 1 and is under construction. Sectional drainage problems exist and water collects under some of the barracks. Garbage collection generally is handled satisfactorily. It is dumped in an open pit east of the project, burned and buried. No attempt is made to use the wet garbage but plans were being drawn for hog and chicken projects to utilize this waste. . . .

On June 1, no provision had been made for buildings to house the carpenter shop, repair shops, plumbing shops, equipment sheds, or a lumber yard. The shops are being temporarily housed in warehouse buildings. . . . No landscaping work had been done prior to June 1, except for a limited, voluntary improvised project in front of the guayule experiment and plant propagation stations. The absence of landscaping was due to the lack of both equipment and stock. In this respect, the project was substantially as it was when the land first was cleared of the native sagebrush growth. Neither had steps been taken looking towards dust palliation. The project possessed no sprinkler wagon and a limited amount of hosing was done by hand. With the destruction of the natural ground cover, the dust problem is acute on windy days. . . .

The men and women's lavatories were without partitions. . . .

In operation on June 1, were twenty mess halls, each accommodating approximately 500 persons. Sixteen additional block mess halls, completed insofar as physical construction is concerned, were inoperative because of the lack of plumbing facilities and mess equipment. The hospital, personnel and high school messes had not been built. . . .

The hospital facilities at Manzanar on June 1, consisted of a 10-bed improvised hospital in one of the barracks buildings, an isolation ward, an out-patients' clinic and a children's ward. . . .

. . . . Manzanar has a single 500-gallon fire engine borrowed from the United States Forest Service. The fire department crew consisted of a fire chief, three Caucasion [sic] captains and thirty Japanese firemen split among three eight hour shifts. The camp is without a fire alarm system or an inter-barracks telephone system over which the ocurrence [sic] of fires might be reported. There is not a telephone to the hospital. During the night, the camp is patrolled by one Japanese for each area of three blocks. For the patrolman to report a fire it would be necessary for him to go by foot to the fire station. Each squad is drilled one hour daily in the use of the fire equipment and extinguishers.

Foamite extinguishers have been installed in the hospital units, each boiler room, laundry building and mess kitchen. Buckets of sand have been placed in the boiler room in each block; all available water barrels with buckets have been placed at strategic locations throughout the center, and residents have been instructed in the use of the improvised equipment until the fire department arrives. Locks have been ordered for fuse boxes to prevent solid fusing with pennies or other devices. Open fires are not allowed without a permit and no permits are issued on windy days after 2 p. m. [44]



<<< Previous <<< Contents >>> Next >>>


manz/hrs/hrs8b.htm
Last Updated: 01-Jan-2002