Chapter Nine:
New Directions and a Second Century (1972-1990)
IN EARLY 1973, the management of Sequoia and Kings
Canyon national parks found itself attempting to overcome a growing list
of difficult planning and resource problems. The new Master Plan
for the parks, completed in early 1971, identified many of these issues,
including visitor congestion in developed areas; aging and inadequate
facilities; understaffed resources management, research, and
interpretive programs; and a lack of broad-based planning in and around
the parks. Issues not specifically mentioned in the plan, but directly
threatening the two parks in the same year included the ongoing Forest
Service effort to develop Mineral King, increasing heavy use of adjacent
Forest Service lands, enormous growth in backcountry travel, and the
rapid population increase of both California in general and Tulare and
Fresno counties in particular. For these problems the National Park
Service had no bold solutions. The Master Plan, as mentioned, did
not call for any major facility removals from congested areas like Giant
Forest. Instead, the plan conservatively suggested a highway bypass
around the Giant Forest area, a bus system, and relocation of the Giant
Forest Lodge to a nearby site with fewer sequoias. [1] About Mineral King the agency had almost
nothing to say. With the top of the federal executive branch committed
to the project, neither the Department of Interior nor the National Park
Service was in a position to object. Some other problems had proven more
amenable to change, however. The experimental limiting of backcountry
use along the Rae Lakes Loop had worked out well during the summer of
1972; and as the new year began, park managers seriously discussed
extending backcountry entry quotas to the remainder of the two parks.
The staffing shortfalls identified in the master plan also showed
promise of improvement. In many ways, calls for additional programs and
additional staffing were easier for the parks to present than
initiatives which threatened existing facilities or uses, or challenged
incompatible uses on adjacent lands.
The last two decades of the first century at Sequoia
and Kings Canyon would see rapidly intensifying debate over proper use
and management of the two parks. For the first time, the public would be
invited to join the planning process, a change that would have large
consequences because of the enormous shift in public awareness of
environmental issues. During the period, this same shift would become
apparent in the Park Service itself, as a new generation of
science-trained and environmentally-aware personnel entered management
levels within the agency. This new generation of park managers would
take the recommendations of the 1963 Leopold Report to heart and
seriously attempt their full implementation. In the process, the
veracity and attainability of the Leopold goals would themselves
ultimately fall into question. The final chapter of the parks' first
hundred years would also see vastly exacerbated threats from outside the
parks' boundariesthreats of a magnitude never before faced by
Sierran parks' managers. And against all these changes, the haunting
legacy of traditiontraditional uses and traditional
attitudeswould prove to be a formidable obstacle. As Sequoia and
Kings Canyon moved toward their second century, questions of management
philosophy and technique, questions of public and personal values, and
questions of human/land interaction loomed larger than ever.
Inside the front cover of the 1971 Master Plan
could be found a note informing readers that the document was "based on
plans presented at the Public Discussions held in conjunction with the
Wilderness hearings in 1966." This simple note, quite unlike anything
that had previously appeared in NPS planning documents for the parks,
marked the opening wedge of a new era. In 1969 Congress passed the
National Environmental Policy Act (NEPA), an elaborate statute that
resulted in revolutionary changes in the federal planning process. NEPA
required that the environmental consequences of all major federal
actions be evaluated, and those consequences mitigated to the greatest
degree possible; the statute also required public input as a part of the
evaluation and consideration process. Henceforth the resolution of any
park management question which affected the natural or human environment
would require some form of public disclosure and participation. One of
the unintended consequences of NEPA and the formalization of the
planning procedure would be to minimize the delays and confusion of
personnel changes. During the 1970s, Sequoia and Kings Canyon would have
no less than five superintendents, but a combination of NEPA regulations
and a stable upper-level management team kept the planning procedure on
a relatively steady course.
|