Donald Benson remembers the prospect of a modernist visitor center
on the Outer Banks of North Carolina as more controversial than the
colorful beach shelter he designed for Cape Hatteras National Seashore
a few years earlier. The shelter's sun shades rose out of the beach
like sculptures, but such artistic license was acceptable in a recreational
facility devoted to seaside entertainment. In contrast, the visitor
center was expected to be functional, dignified, and a public building
for the local community. If the Park Service was now familiar with the
Mitchell/Giurgola design, local contractors must have been surprised
when sets of plans and specifications were sent out for bidding in January
1959. [48] Modern architecture was not part
of the design vocabulary of the region, nor were modernist buildings
prevalent in the state of North Carolina. [49] Bids were opened on February 4, 1959, and the contract
was awarded to Hunt Contracting Company of Norfolk, Virginia, for their
offer of $257,203. [50]
Construction of the visitor center began in March 1959, and foundation
piles had been driven by the end of the month. In early spring, the
beam forms were at grade level. Superintendent Dough predicted rapid
progress now that "the slow process of getting the building staked out,
supplies on hand and work organized has been completed." [51]
Concrete columns and piers were erected in June and most of the floor
slabs poured. On July 24, the contractors' work was inspected by Tom
Vint, chief of design and construction, and Chief Safety Officer Baker,
both of the Washington office. [52] By the
end of the summer, the east elevation had begun to take shape. A view
from the south shows the beams for the exhibit room standing apart from
the office wing. The next month, contractors were laying the ribbed
ceiling forms for the corrugated concrete overhang around the perimeter
of the assembly room. [53] The major concrete
portions had been cast, and Mitchell and Giurgola may have witnessed
some of this form work during their "field inspection" at the site on
September 24-25. [54] Form work for the patterned wall was well underway
by October. A steel grid was used to create the protruding shapes on
the surface of the wall. While the decorative wall was under construction,
contractors were also assembling the arch beam forms of the dome. The
general shape became visible in November; a plywood shell framed the
central half sphere, and intricate interior scaffolding supported the
dome framework throughout this construction. Engineer Don Nutt of EODC
witnessed the "dome pour" later in the month. Smooth reinforced concrete
covered the central portion first. The contractors then turned to form
work for the "flange overhangs," which were subsequently poured. The
dome sat on four coupled columns and was "tied" at its base by four
tension rods. A December photograph of the assembly room interior shows
the completed dome and semi-circular windows, the supportive scaffolding
removed.
Despite colder temperatures, contractors were able to pour the steps
of the visitor center in January 1960. Chief of EODC Zimmer and Supervising
Architect Cabot spent two days "reviewing progress and details" of the
construction that month, and Don Benson and Ann Massey, both of EODC,
visited the site to discuss color and design. [55] Interior framing was still exposed in February, but
the dome, overhang, and exhibition area roof were considered complete.
Roofing compound was applied to the lobby section of the visitor center
the next month, although glass sections of the building remained empty.
Wall panels and windows were not installed until April, when engineer
Don Nutt and landscape architect Ed Peetz (EODC) visited for a construction
review. Sometime during the month, the contractor made his third estimate
for a completion date, settling on June 10. The final inspection of
the visitor center took place on June 20, 1960. Evidently no major changes
were required, and specialists from the museum division were busy installing
the twenty-two museum exhibits during the first weeks of July, when
work also began on the surrounding landscaping. [56]

Figure 24. Wright Brothers Visitor
Center, exterior view looking north, ca. 1960.
(Courtesy National Park Service Technical Information Center,
Denver Service Center.)
|
The contractors for "planting and miscellaneous construction"Cotton
Brothers, Inc., of Churchland, Virginiahad replaced existing concrete
walks and additional pathways by mid-August. Landscape work involved
grading and spreading topsoil as well as "considerable experimentation
and effort . . . with native groundcovers." After completing the walks,
seeding, planting tubs and flagpole base, the contractors began work
on the wooden fence. Progress was interrupted by Hurricane Donna, which
struck September 11 and leveled sections of the fence, but repairs were
accomplished by the end of the month. In addition, the contractors planted
twelve varieties of trees and provided plants for inside the museum.
Before the final inspection, Cotton Brothers installed the Park Service's
signs and gate. [57]

Figure 25. Wright Brothers Visitor
Center lobby, ca. 1959.
(Courtesy MGA Partners, Architects, Philadelphia.)
|
The Wright Brothers Memorial Visitor Center was officially opened to
the public on July 15, 1960. By all accounts, the building met with
a positive reception. Superintendent Dough wrote that "hundreds of compliments
have been received about the exhibits and the building's design since
it was opened. Visitors are generally surprised to learn of the aeronautical
principles formulated by the Wrights, and the descriptive term 'beautiful'
is used repeatedly in describing the building." He also noted that although
about two thousand visitors passed through the visitor center every
day during the summer season, "these are so well distributed during
visiting hours that there are seldom over 75 visitors within the building
at a time . . ." [58] During the month of August, the site received 62,177
visitors, a 34 percent increase since the year before, and approximately
three thousand more visitors than visited in August 1998. [59]
Although Dough seemed optimistic about these figures in his initial
report, by September he had become concerned about the "too interesting"
museum exhibits, which he blamed for causing congestion in the visitor
center. On five peak days ". . . 3,500 plus jammed into the visitor
center." Dough indicated that the Park Service had not expected such
crowds until 1966, as shown by graphs included in their Mission 66 prospectus.
Rather than consider a building expansion, however, Dough suggested
changing the exhibition layout: "More museum exhibits to further spread
out the visitors may be the answer, but in our view the law of diminishing
returns sets in when many more than about 19 exhibits are installed
in a visitor center." [60] Mission 66 planning documents indicate that the Park
Service anticipated record numbers of visitorsnearly ninty thousand
per month by 1966and judged the visitor center facility adequate
to serve their needs. [61] By that time, Dough
had retired and Superintendent James B. Myers assumed his post.
CONTINUED
