Constitution Ave, 15th to 23rd, NW
Schedule: Construction to begin March 2011 Completion anticipated December 2011
Location: Constitution Ave, 15th to 23rd, NW
Goals of project:
• Replace asphalt road surface and replace all failed expansion joints of concrete base
• Replace storm sewer catch basins, curbs, and street lights with new ones
• Replace sidewalks
Impacts/opportunities for visitor to consider:
• Traffic delays. Road work will take place one block at a time. Within that block, only 4 of 8 lanes will be open.
• Pedestrians will be detoured around active work zones.
Funding: Federal Lands Highway Program
Contractor: