Orange Block Graphic PRELIMINARY STEPS IN THE EVACUATION FROM WATER-DAMAGED AREAS

If the materials are to be frozen, prior arrangements should have been made to ship the packed materials immediately to freezing facilities. Packed materials must not be allowed to remain on or near the site for more than a few hours, since such delay will further increase the possibility of mold development. Before actual removal of the water-soaked material begins, lighting, fans, dehumidifiers, and all possible venting should be fully operational. All work surfaces should be covered with polyethylene sheeting. Areas selected for packing or drying should be prepared for the operation by emptying them of all unnecessary equipment and furniture.