• The Point Reyes Beach as viewed from the Point Reyes Headlands

    Point Reyes

    National Seashore California

There are park alerts in effect.
show Alerts »
  • Bear Valley Visitor Center Lighting Retrofit:

    Due to safety concerns during the installation of new LED lights, sections of the Bear Valley Visitor Center's exhibit area may be closed through the end of July. More »

  • The Kenneth C. Patrick Visitor Center will be closed on Saturday, July 26.

    We are sorry for any inconvenience, but the Kenneth C. Patrick Visitor Center at Drakes Beach will be closed on Saturday, July 26. It will open at 10 am on Sunday, July 27.

Point Reyes National Seashore Initiates Limantour and Glenbrook Restoration Project within the Phillip Burton Wilderness

Subscribe RSS Icon | What is RSS
Date: September 14, 2009
Contact: Brannon Ketcham, 415-464-5192
Contact: John Dell’Osso, 415-464-5135

Glenbrook Dam
Glenbrook Dam

This week the National Park Service will initiate the Glenbrook Restoration and Dam Removal Project within the Estero de Limantour and Glenbrook drainage. The 15 foot lower Glenbrook Dam failed in 1982 during a major storm event. The NPS will remove the remainder of the dam to reduce sediments and reestablished the natural hydrologic regime in Limantour Estero. Limantour Estero is part of the Phillip Burton Wilderness and is a biologically rich estuary that was recently designated a Marine Reserve.

In 1960s, landowners excavated materials for the dam from the adjacent hillsides and spillway areas. The project will restore natural hydrologic conditions and increase estuarine habitat at Point Reyes National Seashore by removing remaining infrastructure which impedes the development and function of the tidal marshplain. The project area is subject to sea level rise and restoration of natural process within this estuary is a climate change adaptation strategy to ensure maintenance of a healthy and functional estuarine ecosystem.

Contractors will remove approximately 19,000 cubic yards of former dam, using that material to restore the associated spillway. The restoration activities will take approximately three weeks, with completion by mid-October. While no trail closures are anticipated, there may be limited trail interruption associated with vehicle access occurring along portions of the Muddy Hollow, Glenbrook and Estero trails.

Public review and environmental compliance was completed on this project in February 2008. A Finding of No Significant Impact was signed in May 2009 and posted on the park website. Funding for this project has been provided through the NPS Abandoned Mine Lands program, the Bella Vista Foundation, and Point Reyes National Seashore Association. More information is available at http://www.nps.gov/pore/parkmgmt/planning_glenbrook_restoration.htm