1.4 Division 01 Specifications Management Plans - Electronic Process (SharePoint)

Contractors Commissioning Plan (CCxP), Contractor Quality Control Plan (CQCP), Historic Preservation Treatment Plan (HPTP), Indoor Air Quality (IAQ) Management Plan, Storm Water Pollution Prevention Plan (SWPPP) or Under-an-Acre Pollution Prevention Plan (UPPP), Waste Management Plan (WMP)

Contracting Officer's Representative (COR) or Construction Management Representative (CMR)

  • Review for compliance with the contract documents.
  • Use the CM-SPE form (on the NPS/DSC SharePoint Project website) to document comments and indicate acceptance or rejection.
  • Process all re-submittals and supplements as required until acceptable plans have been completed.
  • The UPPP template and guideline are attached below for the contractor to review.

Guideline:

Template: