• Many Glacier Hotel at Glacier National Park, Montana

    DSC Workflows

2.5.3 Value Engineering Change Proposal

Construction Management Representative (CMR)

  • Review Value Engineering Change Proposal (VECP) for the minimum information required in contract clause entitled “Value Engineering - Construction,” FAR 52.248-3.
  • Notify Contracting Officer Representative (COR) that VECP has all required elements and forward information to COR.
  • If essential elements are missing from proposal, draft rejection letter for COR signature.

Guidelines: