The second week of construction efforts continue with setting up a construction support system, such as dumpsters, a water tank, and the work trailer. Incoming equipment was properly treated to prevent introduction and spread of invasive, nonnative species.
In order to continue prepping the site, removing various barriers such as split rail fencing, the old visitor center building, and reusable signage was completed. Green practices were taken into place on concrete and steel for salvaging and recycling.
The old electrical meter was replaced and readied for activation, while the septic tank perimeter was excavated for future removal with onsite archeological monitoring.
Split rail fencing, which was originally used around the old visitor center, was temporary relocated out of the construction area for future use
Excavation of old visitor center cement slab being removed
National Park Service archeologist monitors the evacuation of the old visitor center concret slab foundation
Park signage and reclaimed wood is staged to be saved for furture reuse
November 09, 2019
|
Last updated: January 23, 2020