Update: Site Observation Update Week of May 26th

May 26, 2020 Posted by: Ranger Jeff
This week, electrical infrastructure work (conduit, j-boxes, fixtures, etc.) was ongoing within the temperature electrical meter installed west of the site. Installation of storefront windows at the vestibule moved forward while a surveyor was on site to establish grades for pedestrian walkways and curb delineation at the drop off/entry to the building. Excavation, along with archeological monitoring, has been ongoing at the west end entry of American Camp Road. Backfilling of the utility trench ongoing along the road is ongoing. Another week of great progress.

It’s important to note that all crew members are employing all those health and safety measure that we are all practicing, including social distancing. Work crew members are being monitored regularly, and sanitation facilities are available for the crew. While the project is certainly important, the health and safety of employees and workers is much more important.

Front elevation and grading work
(A) Photo a above gives us our first good look at the structure since windows and doors were installed. Notice also the trellis out front that offers shade as well as a place from which to hang exhibits.

In photo (B) we look southeast at the structure and see in the foreground survey stakes which mark where sidewalks will soon be ready for concrete

Surveyors stakes marking future sidewalks
In photo (C) we get a good look at the conduit that carries wiring throughout the building.
Installed electrical conduit in walls
Utility trench being covered prior to paving
Photo (D) looks North down the entry road where the trench that carries utilities to the site is being covered. In the distance, on the right, you can make out the debris that will soon be cleared. This is where the new entry road to the site will connect.
Granite boulder wall in front of building
In the photo above (E) a worker positions the granite boulders that will serve as both a retaining wall in front of the restrooms. Granite is not native to the islands. These granite boulders were carried hundreds of miles from the North Cascades and Canada. Oddly, just across the straights, the Olympics also have no naturally occurring granite.

In photo (F) below we see storefront windows that will hold informational posters and exhibits.

Storefront windows installed
Photo (G) shows two workers finishing the concrete steps from the lower parking area to the upper lot.
Workers finishing concrete parking lot steps
Photo (H) is taken from the rear of the building showing the plywood board to which siding will be nailed.
Plywood boards ready for new siding
Front entryway doors installed
(I) It’s always a great feeling when the building receives its front door. These double entry doors will swing open for millions of visitors in the coming years.

(J) As we leave you for the week, we see framing going in for the concrete sidewalks from the VC to the interpretive plaza and beyond.

Worker framing for concrete sidewalks
 

Last updated: June 3, 2020

Park footer

Contact Info

Mailing Address:

P.O. Box 429
Friday Harbor, WA 98250

Phone:

360 378-2240

Contact Us