Work resumed from the holiday break with the stripping of the footing formwork and then delivery and the installation start of the foundation wall formwork. Foundation wall formwork construction involves snapping lines to delineate foundation wall elevations and installing reinforcing steel before the molds are built in preparation for the cement pour.
The excavation and regrading of the new interpretive plaza and picnic area started this week in preparation for future survey work, while surveying the sub layout boundaries and elevations for the lower parking lot area was completed.
Once the foundation footing cement dried, the wooden formwork was erected around reinforcing steel for the foundation wall cement to be poured.
The new interpreation plaza area is regraded and prepped with a sub-layer aggregate.
A land survey crew uses survey equipment to distinguish the new lower parking lot area.
January 11, 2020
|
Last updated: January 28, 2020