Due to snowy weather conditions for the week of Jan 13th, concrete pouring for the foundations resumed this week. In preparation for the pouring, installation of formwork for the Visitor Center’s foundation walls and north retaining wall structure continued.
Excavation activities continued on the lower parking lot area, while grading and compaction activities continued for the interpretative plaza area. Excavation and footing formwork outside the visitor center entry were completed for future trellis installation.
Foundation formwork construction continues in preparation for the cement pour.
Overall view of the visitor center’s foundation formwork in preparation for the cement pour.
The trellis support footings for the visitor center entry and interpretative plaza were first excavated and then the cement formwork was built for cement.
Cement truck with a boom pump is used to guide cement into the foundation formwork.
January 25, 2020
|
Last updated: January 29, 2020