Update: Site Observation Update Week of Jan 20th

January 25, 2020 Posted by: Anna Mateljak
Due to snowy weather conditions for the week of Jan 13th, concrete pouring for the foundations resumed this week. In preparation for the pouring, installation of formwork for the Visitor Center’s foundation walls and north retaining wall structure continued.

Excavation activities continued on the lower parking lot area, while grading and compaction activities continued for the interpretative plaza area. Excavation and footing formwork outside the visitor center entry were completed for future trellis installation.

Wood boards and panels create a frame for the building foundation.
Foundation formwork construction continues in preparation for the cement pour.

Wooden panels and boards along the building perimeter are used to construct cement formwork for the building’s foundation.
Overall view of the visitor center’s foundation formwork in preparation for the cement pour.

Five square boxes made of wooden panels and reinforcing steel are being installed at the entry of the building foundation
The trellis support footings for the visitor center entry and interpretative plaza were first excavated and then the cement formwork was built for cement.

Cement truck in the foreground with a crane-like arm helps construction workers guide cement by a boom pump to the wooden foundation formwork.
Cement truck with a boom pump is used to guide cement into the foundation formwork.
 

SAJH, San Juan Island NHP, American Camp Visitor Center, American Camp, Visitor Center Construction



Last updated: January 29, 2020

Park footer

Contact Info

Mailing Address:

P.O. Box 429
Friday Harbor, WA 98250

Phone:

360 378-2240

Contact Us