Ongoing reinforcing steel installation on top of the vapor barrier and finished subbase plumbing and electrical infrastructure for the cement pour.
February 15, 2020
The plumbing and electrical infrastructure within the sub-base of building foundation was completed this week so that the installation of rigid insulation, a vapor barrier, and reinforcing steel could be installed for next weeks cement slab pour. Other work continues on the visitor center canopy and trellis with compacted gravel subbase around the pier supports, foundation backfilling, and general site clean-up.
Ongoing reinforcing steel installation on top of the vapor barrier and finished subbase plumbing and electrical infrastructure for the cement pour.
|