Update: Site Observation Update Week of Feb 10th

February 15, 2020 Posted by: Anna Mateljak
The plumbing and electrical infrastructure within the sub-base of building foundation was completed this week so that the installation of rigid insulation, a vapor barrier, and reinforcing steel could be installed for next weeks cement slab pour. Other work continues on the visitor center canopy and trellis with compacted gravel subbase around the pier supports, foundation backfilling, and general site clean-up.

A construction worker stands in the middle of the building foundation among rebar grid pattern which is ready for a cement pour for the foundation slab.
Ongoing reinforcing steel installation on top of the vapor barrier and finished subbase plumbing and electrical infrastructure for the cement pour.

SAJH, AmericanCampVisitor Center, AmericanCamp, VisitorCenterConstruction, SanJuanIsland NHP



Last updated: March 9, 2020

Park footer

Contact Info

Mailing Address:

P.O. Box 429
Friday Harbor, WA 98250

Phone:

360 378-2240

Contact Us