Update: Site Observation Update Week of Dec 16th

December 21, 2019 Posted by: Anna Mateljak
The formwork operations and perimeter footings commenced with the delivery of reinforcing steel, building the footing formwork, and pouring the cement footers. The contractors got a lot of work done this week, just in time for the holiday break to resume construction efforts in the New Year.

Four construction workers build a wooden frame for the building’s cement footing on the prepped sub-layer site
Construction workers construct the building footing framing in preparation for the cement pour.

Piles of various shaped and sized reinforcing steel bars are piled at the construction site waiting to be installed.
Reinforcing steel was delivered to the site to be installed within the footing framing before cement is poured.

A construction worker guides a cement hose along building foundation footing framing in the foreground with a cement truck and crane in the background
Concrete pouring for the building foundation footers.

SAJH, San Juan Island NHP, American Camp Visitor Center, Visitor Center Construction