The formwork operations and perimeter footings commenced with the delivery of reinforcing steel, building the footing formwork, and pouring the cement footers. The contractors got a lot of work done this week, just in time for the holiday break to resume construction efforts in the New Year.
Construction workers construct the building footing framing in preparation for the cement pour.
Reinforcing steel was delivered to the site to be installed within the footing framing before cement is poured.
Concrete pouring for the building foundation footers.
December 21, 2019
|
Last updated: January 28, 2020