This week’s activities at the site continue to focus on completing the new access road and preparing curbs and walkways in anticipation of new pavement throughout the site. Additionally, the stone base that accents the building has finally made its appearance as we do touch-up work on the horizontal siding and soffit work and install outdoor fixtures. The concrete pad for services entering the site has been poured and a security screen to conceal the pad will be added. All in all, progress was significant this week as the project is now in the home stretch.
It’s important to note that all crew members are employing all those health and safety measure that we are all practicing, including social distancing. Work crew members are being monitored regularly, and sanitation facilities are available for the crew. While the project is certainly important, the health and safety of employees and workers is much more important.

(A) The stone base that accents the exterior of the building is being installed and the affect is better than anticipated.

(B) This view of the new access road from Cattle Point road shows most of the grading and compacting complete. Soon, pavement will arrive and be laid down throughout the site.
(C) In photo (C) below, we see a worker preparing curbs and flatwork for a concrete pour next week.

(D) At the intersection of the new access road culvert has been laid, one more element in preparation for long awaited pavement.

(E) Pendant fixtures are now installed for lighting outside the main building.

(F) The meter pad for services entering the site is now in place. All that remains here is the addition of a security screen.