North Parkway Construction, News, and Impacts

GWMP Construction Infographic
This infographic displays the areas that are under construction and the anticipated schedule.

NPS

Construction efforts to rehabilitate the George Washington Memorial Parkway (GWMP) are underway between I-495 and Spout Run Parkway. Construction activities will impact drivers and park visitors for the duration of the rehabilitation. View construction updates under Current Construction. The roadwork is anticipated to be completed in late 2025.

  • To opt in to receive email updates about traffic, meeting notices and information about major milestones please click here.
  • To contact the project team please e-mail us. 
  • View recordings of informational public meetings on our public meeting webpage.

Rehabilitation Progress Along the Parkway

Crews continue to make progress on rehabilitation work daily. As of Summer 2025:

  • 65% of the roadway has been replaced, improving drivability and safety. 
  • 85% of the guardwall has been repaired or replaced, upgrading motorist safety.
  • 90% of the drainage work is complete, reducing erosion and sediment run off.
  • 75% of the bridge repairs are complete, rehabilitating aging infrastructure.
  • 100% of the outfalls have been repaired, completing work to improve drainage structures that discharge water to nearby streams.
 
A graphic depicting how the new traffic arrangement will look.
During the morning rush hour, two lanes will carry traffic southbound toward Washington, DC. During the evening rush hour, two lanes will carry traffic northbound toward Maryland.

NPS

Current Construction (Updated September 2025)

I-495 to Route 123


The National Park Service (NPS) continues working in this segment. Crews continue temporary lane demolition and reconstructing the curb, drainage, and masonry guard wall and planting trees through 2025. Drainage installation, roadway demolition, paving, and lane striping are complete on the northbound and southbound lanes. Crews continue tree replanting requiring continued temporary traffic closures. View detailed lane closure schedules below.

Lane Configuration
The three-lane configuration extends from I-495 to Route 123. The lane schedule is as follows:

Weekday morning rush hour (5:30 a.m. – 9:30 a.m.)
  • Two lanes southbound (toward Washington, DC).
  • One lane northbound (toward Maryland/Virginia).
Weekday evening rush hour (2:45 p.m. – 7:15 p.m.)
  • Two lanes northbound (toward Maryland/Virginia).
  • One lane southbound (toward Washington, DC).
Weekdays (9:30 a.m. – 2:45 p.m. and 7:15 p.m. - 5:30 a.m.) weekends and major holidays
  • One lane southbound (toward Washington, DC).
  • One lane northbound (toward Maryland/Virginia).
 
Map of GWMP Schedule A-C NB Detour
Northbound GWMP traffic traveling toward Maryland will need to exit at Route 123 and follow signs to reach I-495 north.

NPS

September Northbound Lane Weekend Closures for Roadwork

This month, the NPS will continue temporary lane closures between I-495 and Route 123 for landscaping work along the northbound lanes. The closure schedule and details are listed below:

Northbound Lane Closure Schedule: Route 123 to I-495

  • From 7 a.m. on Saturday, September 20 until 6 p.m. on Sunday, September 21

Detour Information: Motorists traveling northbound on the George Washington Memorial Parkway (GWMP) must exit at Route 123 and follow detour signs to reach I-495 north towards Maryland as shown on the detour map.

The exit to and from Turkey Run Park will be closed from northbound GWMP during these weekend closures. During this time, visitors should follow the detour to northbound I-495 and proceed to southbound GWMP to access Turkey Run Park.

 
Map of southbound closure and detour
Southbound Detour: Exit at Route 123 and follow signs to Spout Run Parkway to re-enter GWMP.

NPS

Route 123 to Spout Run Parkway Construction Outlook

Crews continue weekend work including temporary lane closures for barrier relocation, paving activities, and ongoing ramp work at the Route 123 interchange. One southbound lane remains closed for construction from Route 123 to Windy Run Bridge through 2025. There will be no reversible lane in this section of the parkway. View below for construction details in each segment.

Route 123 to Spout Run Southbound Lane Closure Schedule

  • From 7 a.m. on Saturday, September 20 until 6 p.m. on Sunday, September 21
  • From 7 a.m. on Saturday, September 27 until 6 p.m. on Sunday, September 28

Detour Information: All southbound GWMP traffic must use the southbound GWMP ramp to Route 123 and follow detour signs to Spout Run Parkway to re-enter southbound GWMP toward Washington D.C. One northbound lane on GWMP will stay open. 

 
Aerial view of Route 123 and the proposed GWMP Interchange.
Route 123 Interchange

The NPS has completed construction of the modified interchange at GWMP and Route 123. The ramps to and from southbound GWMP have been consolidated and are located east of Pine Tree Road. Crews demolished the old ramps from southbound GWMP to westbound Route 123 and from westbound Route 123 to southbound GWMP. Two new ramps are open at this intersection to improve safety and access between Route 123 and southbound GWMP. Additionally, the acceleration and deceleration lanes have been extended for safer merging onto the parkway and exiting off of the parkway. This new traffic configuration realigns entrances to southbound GWMP using the following traffic pattern:

Route 123 traffic:

  • All traffic on Route 123 heading to southbound GWMP will use the new ramp.
  • Motorists on eastbound Route 123 heading to southbound GWMP will continue to bear right onto the existing short ramp and connect to the new southbound GWMP ramp.
  • Motorists traveling westbound on Route 123 will yield to eastbound Route 123 traffic before turning left onto the new southbound GWMP ramp.

Southbound GWMP traffic:

  • The new ramp will allow right turns from southbound GWMP onto westbound Route 123. Southbound GWMP traffic heading to eastbound Route 123 will use the existing exit ramp.
  • A stop sign is placed on Route 123 for motorists exiting southbound GWMP onto Route 123 until the planned traffic signal is operational.

Crews also performed drainage and curb installation and paving at this intersection. The northbound GWMP exit ramps to eastbound and westbound Route 123 will remain as is.

 
A graphic depicting work occurring in the left most lane while three other lanes have traffic.
During the evening rush hour, two lanes will carry traffic northbound toward Maryland / Virginia. There will be one lane of traffic in each direction at all other times.

NPS

Route 123 to Windy Run Bridge

Construction continues on the left southbound lane including:

  • Curb installation
  • Guardwall and median reconstruction
  • Asphalt paving
Lane Configuration
  • PM Rush Hour (2:45 – 7:15 p.m.): One lane will carry traffic southbound toward Washington D.C. and two lanes will carry traffic northbound toward Maryland/Virginia.
  • All other times: There will be one lane open to traffic in each direction
 
Windy Run Bridge to Spout Run Parkway

Crews completed roadwork in this segment and reopened the left southbound lane to traffic. Periodic single lane closures continue for median restoration, signage installation, and construction at Spout Run Arch Bridge.

 
A graphic depicts construction workers in the Southbound lane, while traffic moves in three lanes (two nouthbound and one sorthbound) next to it.
During bridge work, a three-lane configuration will be in place with a barrier to separate traffic from the work zone.

NPS

Bridge Construction

Crews continue with bridge work:

  • Crews will close one lane on Spout Run Arch Bridge for structural repairs. During non-rush hours, one southbound lane will be open from Windy Run Bridge to Spout Run Parkway and through the work zone on the bridge.
  • Repairs continue on and below the bridge surface at Glebe Road, Windy Run, Pimmit Run, Gulf Branch, and Route 123 interchange bridges
Temporary barriers remain in place at Pimmit Run, Glebe Road, Gulf Branch, and Windy Run bridges with narrower lane widths as work continues. No additional traffic delays are anticipated at this time.

All work is weather permitting. In the event of inclement weather, work will be rescheduled. Any changes in the closure schedule above will be reflected on this page.
 

Construction Zone Safety

Please slow down and be cautious while driving through work zones on the parkway. To increase safety, small physical barriers divide the narrow travel lanes. Commercial vehicles are restricted from the parkway at all times. Signage will direct drivers to the appropriate lanes. During non-rush hour periods, weekends, and holidays, the center reversible lane will be closed, and motorists can expect two travel lanes: one traveling northbound and one traveling southbound.

  • Drivers should observe traffic signs for updated information.
  • A 40 MPH speed limit remains in effect from the I-495 interchange to Spout Run Parkway to help keep construction crew and motorists safe. This speed limit will be in place for the remainder of the project and is enforced as such.
  • To avoid traffic delays on the northern section of the parkway, drivers should consider alternate routes and plan for additional travel time.
  • Remember vehicles over 10,000 lbs. are always prohibited from using the parkway.
 
 

Frequently Asked Questions (FAQs)

 
Aerial view of Route 123 and the proposed GWMP Interchange Option One. The curved sections in purple would be removed and the proposed configuration is in blue and is more linear. The Limits of Disturbance boundary is a dashed yellow line.
 

North Parkway News

Loading results...

    Last updated: September 16, 2025

    Park footer

    Contact Info

    Mailing Address:

    George Washington Memorial Parkway Headquarters
    700 George Washington Memorial Parkway

    McLean, VA 22101

    Phone:

    703 289-2500

    Contact Us