North Parkway Construction, News, and Impacts

This infographic displays the project rehabilitation area
This infographic displays the project rehabilitation area

NPS

The National Park Service (NPS) has reached substantial completion of the north parkway rehabilitation project on the George Washington Memorial Parkway. The project, which began construction in 2022, improves safety and resilience through rehabilitated pavement and drainage, strengthened roadside features and restored historic overlooks. Some finishing work will continue into the spring during off-peak travel hours. Motorists can expect travel impacts once crews begin rehabilitation efforts on the Route 123 Interchange bridge.
View construction updates under Current Construction.

  • To opt in to receive email updates about traffic impacts and other news please click here.
  • To contact the project team please  e-mail us.  
  • View recordings of informational public meetings on our public meeting webpage.

Rehabilitation Completion Along the Parkway

The National Park Service has completed all major construction efforts for the Rehabilitation Project. Crews have performed the following:

  • Repaired or replaced the guardwall, upgrading motorist safety.
  • Repaired bridges, rehabilitating aging infrastructure.
  • Replaced the roadway, improving drivability and safety. 
  • Completed drainage installation and repairs, reducing erosion and sediment run off.
  • Repaired the outfalls have been repaired, completing work to improve drainage structures that discharge water to nearby streams. 
The National Park Service thanks you for your patience over the last three years as we worked to rehabilitate 7.6 miles of the parkway, improving the driving experience and safety for motorists, while maintaining the culture of this historic landmark near our nation’s capital. See below for current construction details and impacts in each segment.
 

Current Construction (Updated March 2026)

I-495 to Route 123

Crews continue curb work at the I-495 Interchange. Periodic lane closures also continue for median restoration activities.

 

Route 123 to Spout Run Parkway

Repairs on the concrete median and guardrail are complete. Motorists can expect finishing work during off-peak travel hours for median restoration activities.

 

Bridge Construction

Crews have completed repairs on and below the bridge surface at Glebe Road, Pimmit Run, Dead Run, Turkey Run, Windy Run and Spout Run Northbound and Southbound Arch bridges, rehabilitating aging infrastructure.

Crews have completed stonewall work and removed traffic barriers on Windy Run Bridge. Crews are working on under bridge platform removal at Gulf Branch Bridge. No additional traffic delays are anticipated at this time.

All work is weather permitting. In the event of inclement weather, work will be rescheduled. Any changes in the closure schedule above will be reflected on this page.

 

Construction Zone Safety

Please slow down and be cautious while driving through work zones on the parkway. Commercial vehicles are restricted from the parkway at all times. Signage will direct drivers to the appropriate lanes.

  • Drivers should observe traffic signs for updated information.
  • A 40 MPH speed limit remains in effect from the I-495 interchange to Spout Run Parkway to help keep construction crew and motorists safe. This speed limit will be in place for the remainder of the project and is enforced as such.
  • To avoid traffic delays on the northern section of the parkway, drivers should consider alternate routes and plan for additional travel time.
  • Remember vehicles over 10,000 lbs. are always prohibited from using the parkway.
 
Mill and Overlay Map
Resurfacing work will occur in two segments from Spout Run Parkway South and I-395 and between Ronald Reagan Washington National Airport and Alexandria.

NPS

Additional Rehabilitation Work on the George Washington Memorial Parkway
The National Park Service has identified additional rehabilitation work on the George Washington Memorial Parkway. This work has begun, taking advantage of the current construction workforce to facilitate this additional work and reduce traffic impacts.

  • Route 123 Interchange Bridge Work and Traffic Impacts 
    Structural repairs on the Route 123 Interchange bridge are underway as part of efforts to rehabilitate aging infrastructure. The exit ramp to Route 123 eastbound and westbound has a reduced deceleration lane. The National Park Service anticipates that there will be a single travel lane closed and that lanes adjacent to the exit ramps will also be closed during rush hour. More details will be provided on those lane closures before they are in effect. Work on the bridge is anticipated to last through mid-May.

  • Additional Mill and Overlay Work
    Just south of the project limits between Spout Run Parkway south to I-395 and between Ronald Reagan Washington National Airport to First Street in Alexandria, the George Washington Memorial Parkway will undergo resurfacing work. Crews will remove a layer of the northbound and southbound lanes and rehabilitate the asphalt to extend the life of the roadway in this section of the parkway.

    This work is anticipated to start the week of March 23 once weather conditions are suitable for asphalt work and continue through mid-June. Crews anticipate back-to-back milling and paving during the day and overnight on weekdays and weekends, weather permitting.

    Traffic pattern
    Crews will begin work in the segment from Spout Run Parkway to I-395.

    Weekday morning rush hour (5:30–9:30 a.m.): One northbound lane will be closed. Motorists can expect two lanes traveling southbound toward Washington, D.C., and one lane traveling northbound toward Maryland and Virginia.

    Weekday evening rush hour (2:45 –7:15 p.m.): One southbound lane will be closed. Motorists can expect two lanes traveling northbound toward Maryland and Virginia, and one lane traveling southbound toward Washington, D.C.

    Weekdays (9:30 a.m.–2:45 p.m.), overnight (7:15 p.m.–5:30 a.m.), and weekends: One lane will remain open in each direction.

Construction may result in ramp closures. The National Park service will share more information on traffic impacts and detours ahead of these closures.

 

Turkey Run Loop Drainage Repairs
The NPS will close the northbound and southbound George Washington Memorial Parkway exits to Turkey Run Loop in early April through early May, weather permitting. The closures will repair drainage structures along the loop.

Crews will begin by closing the northbound parkway exit to Turkey Run Loop and, once work is complete, proceed to work on the southbound parkway exit. Lane closures will be on weekdays from 7 a.m. to 5 p.m. Motorists traveling on Turkey Run Loop Road will continue to the parkway in both directions.

Detour information:
Northbound parkway exit to Turkey Run Loop closure: To reach Turkey Run Loop Road, motorists on the northbound parkway should continue to I-495 south, turn at Georgetown Pike, and proceed to the southbound parkway. Motorists traveling on the southbound parkway will still be able to access Turkey Run Loop and proceed to the northbound parkway.

 
Southbound parkway exit to Turkey Run Loop closure: To reach Turkey Run Loop Road, motorists on the southbound parkway should continue to Route 123 and proceed to the northbound parkway to Turkey Run Loop Road. Motorists traveling from the northbound parkway will still be able to access Turkey Run Loop and proceed to the southbound parkway.

The NPS understands the parkway's importance for motorists and is working efficiently to complete its rehabilitation to minimize prolonged congestion for this additional effort while ensuring safety for the public and construction crews. The NPS will provide additional information on the work and traffic impacts ahead of the construction.
 
 

Frequently Asked Questions (FAQs)

 
Aerial view of Route 123 and the proposed GWMP Interchange Option One. The curved sections in purple would be removed and the proposed configuration is in blue and is more linear. The Limits of Disturbance boundary is a dashed yellow line.
 

North Parkway News

Loading results...

    Last updated: March 19, 2026

    Park footer

    Contact Info

    Mailing Address:

    George Washington Memorial Parkway Headquarters
    700 George Washington Memorial Parkway

    McLean, VA 22101

    Phone:

    703 289-2500

    Contact Us