Constructability QA Review Checklist

Predesign / Schematic Design

___
Major constructability issues have been identified including access, staging, utility availability, entry points, and work restrictions.
___
Contract type has been identified and is appropriate for the project needs (fixed price, design build, 8a set aside, competitive negotiation, etc.).
___
All compliance has begun or is complete (SHPO (State Historic Preservation Officer), NEPA (National Environmental Policy Act), EA (Environmental Assessment), etc.).
___
Scope of work consistent with program and within budget.
___
Work on easements, right of ways, cooperative agreements, etc. have been initiated.

Design Development (DBB) or (DB)

___
All required deliverables submitted.
___
All required permits (Water, Sewer, and Road) are outlined.
___
State or local contacts included.
___
Individual permit requirements have been listed.
___
All compliance has been initiated or is complete (SHPO, NEPA, EA, etc.).
___
Logistics - access, traffic control, impacts to park and visitor operations have been considered and addressed.
___
Site access issues, load limits, bridge and/or tunnel height restrictions have been identified.
___
Long lead items, material and equipment availability, special delivery or construction requirements have been considered.
___
Value Engineering potential has been investigated.
___
Notes on drawings are appropriate and do not conflict with the specifications or General Provisions.
___
NPS/DSC Division 1 guide specifications have been incorporated and edited to the greatest extent possible.
___
Preliminary site investigation complete and existing conditions verified and included.
___
Hazardous material testing has been done and scope of work identified.
___
Archeological potential has been assessed and protection specified. Coordination with Park has occurred.
___
Availability of material, labor, and equipment on remote sites has been considered.
___
Draft Constructability checklist has been completed.
___
All legal work completed (easements, right of ways, cooperative agreements, etc.).
___
Estimate is within budget with appropriate mark ups for this stage of development.
___
The draft Price Schedule is completed and coordinated with specifications.

Construction Documents (DBB and DB (as applicable))

___
All required deliverables submitted.
___
Final Constructability checklist included and completed.
___
State and local permit review comments and details have been incorporated.
___
All compliance is complete.
___
No funding issues. Class A estimate is within available funds.
___
Special inspection requirements listed.
___
Staging areas are identified on site plan.
___
Staging areas are adequate for the intended purpose.
___
Clear discussion on availability of temporary utilities for staging (cost and time implications, park supplied or contractor).
___
Logistics - traffic control, impacts to park and visitor operations have been considered and addressed, traffic and pedestrian control plans and requirements are clear as submittals.
___
Site access issues have been included in General Conditions requirements.
___
Long lead items that may affect contract period have been considered and elevated.
___
Specialized equipment and materials have been considered in the estimate and contract period.
___
Sole source materials have been adequately justified.
___
Government furnished equipment and materials are adequate and will be available when the contractor needs them.
___
Requirements for resource protection specified and adequately shown.
___
Accurate survey data on the plans (Benchmarks (BMs), Temporary Benchmarks (TBMs), Topographic (TOPO).
___
Construction limits adequately shown and defined (needed for both access and construction limits).
___
Special signage requirements addressed (traffic, park, etc.).
___
All existing utilities located and accurately shown.
___
Temporary system requirements have been coordinated with park or concession needs.
___
Salvageable items have been identified and listed along with delivery locations if needed.
___
Noise, dust and special safety concerns have been addressed in the special conditions.
___
If rock excavation is expected it is clearly defined and accounted for in the Price Schedule with an estimated quantity.
___
If Blasting is allowed the standard NPS explosives specification is included with all safety requirements.
___
Hazardous material scope of work is clearly shown, quantified and accounted for in the estimate. State and local requirements have been considered. Technical specifications for removal provided.
___
Archeological monitoring requirements have been addressed in the specifications. Sensitive zones are protected.
___
If the availability of material, labor, or equipment is an issue on remote sites has it been considered in the cost estimate and in the overall contract period.
___
Site access constraints for construction operations have been included.
___
Appropriate contract length (considering weather, seasons, long lead items, fabrication and delivery, etc.).
___
Park or Concession imposed restrictions included in the package are appropriate and impacts to cost and schedule have been considered.
___
Clear delineation of local utility responsibilities (scope, equipment supplied etc.) and contractor responsibilities included as a part of this contract.
___
Disruption of utilities and down times have been coordinated with the park and language included in division 1 specifications.
___
Specific phasing requirements for bidding and performance have been included as applicable.
___
Specialized materials are necessary and manufacturing installation and certifications are specified.
___
Park or concessionaire beneficial occupancy's (grand openings, fixed completion dates) have been considered in the overall planning.
___
Overlaps with adjacent and concurrent contracts have been identified with requirements for contractor to coordinate as needed.
___
Training and certifications have been outlined in the individual specification sections.
___
Operation and maintenance requirements have been included.
___
Notes on drawings are appropriate and do not conflict with the specifications or General Provisions.
___
Adequate detail provided.
___
Specified products are detailed on drawings as needed.
___
Check for consistency of terminology between drawings and specifications.
___
Identify outdated code requirements.
___
Identify obsolete materials specified.
___
Verify all specification section references are correct and specifications are included in the package.
___
NPS/ DSC Division 1 guide specifications have been utilized, and fully edited.
___
Contractor's use of premises has been appropriately addressed.
___
Park hours of operation and seasonal shut downs have been included.
___
Relevant reports are included (soils, hazmat, etc.) with dates and authors included.
___
Project schedule requirements and milestones are up to date and appropriate for the project size and complexity.
___
Submittal requirements match internal NPS/DSC processes.
___
All reference standards have been incorporated.
___
Quality control staff requirements are appropriate.
___
All required forms have been attached to individual specification sections.
___
Temporary service requirements have been coordinated with the Park and identified as either Government furnished or Contractor responsibility.
___
Contracting Officer's field office, furnishings, and equipment requirements have been adequately addressed.
___
Adequate barriers specified and shown on the site plan.
___
Requirements for compliance with applicable laws, environmental regulations, and ordinances have been included.
___
Park security requirements and special permits addressed as required.
___
Price Schedule included with Contract line item descriptions that are clearly written.
___
All Options or alternates are accurately described and identified on the drawings.
___
Measurement for payment language included for each Contract line item accurately describes how completed work will be measured for payment.
___
Payment information included for each Contract line item reflects type of payment (lump sum or unit price).
___
Price schedule coordinated with specification section 012700 (Definition of Contract Line Items) and class A cost estimate.
___
Estimate is broken down per CSI (Construction Specifications Institute) format with Materials, Labor and Equipment for each Contract Line Item.
 