ANNUAL PERFORMANCE PLAN

 

WHITMAN MISSION NATIONAL HISTORIC SITE

 

 

 

 

 

 

 

 

 

 

FISCAL YEAR 2003

 

OCTOBER 1, 2002 – SEPTEMBER 30, 2003

 


 

 

 

 

Fiscal Year 2003

Annual Performance Plan

 

for

 

Whitman Mission National Historic Site

 

 

 

 

 

 

 

 

 

 

Approved:     /S/        Francis T. Darby_____________       November 15, 2002    

                                     Superintendent                                          Date

 


TABLE OF CONTENTS

 

 

I.   Introduction

 

II.   Mission Statement

 

III. Accomplishing Goals

 

IV. Annual Goals

 

Ia10A  - Disturbed Lands not meeting criteria of Ia1A

Ia1B    - Exotic Species not meeting criteria of Ia1B

Ia5      - Historic Structures

Ia6      - Museum Collections

Ia7      - Cultural Landscapes

Ia8      - Archeological Sites with condition assessments

IIa1     - Visitor Satisfaction

IIa2     - Visitor Safety

IIb1     - Visitor Understanding and Appreciation

IVa4    - Workforce Diversity

IVa6A  - Employee Safety (Lost-time Accidents)

 

 

V.  Annual Performance Plan Preparers

 

 

Appendix A    “Annual Work Plan”

 

 


I.  INTRODUCTION

 

About This Plan

 

This is the Annual Performance Plan for Whitman Mission National Historic Site, (N.H.S.).  It covers October 1, 2002 – September 30, 2003 (Federal fiscal year 2003),  one-year of our six year (2001-2005) Strategic Plan.  Our separate Strategic Plan contains our mission and long-term goals and contributes to the nationwide National Park Service (NPS) mission.  Copies of our Strategic Plan are available by request, phone 509-522-6360, mail, Whitman Mission N.H.S., 328 Whitman Mission Road, Walla Walla Wa., 99362 or off the internet at www.nps.gov/whmi.

 

Our Annual Performance Plan lists each annual goal in the context of its parent mission and long-term goal.  Like the parent goal, each annual goal is “results” or “outcome” oriented.  Each goal is objective, quantified and measurable, with performance measures built into each goal statement. Each goal has a brief background explanation, an overview of how the goal will be accomplished, and a statement of how accomplishment will be measured.  See Section III Accomplishing Goals for information on the fiscal and human resources we plan to use to achieve the desired outcomes or results.

 

Each park also develops internal management documents -- annual work plans.  They describe the specific activities, services, and products that will be carried out or produced to accomplish goal results in greater detail and list the dollars and staffing (in terms of “full-time equivalents” or FTE) required to accomplish these goals.   Annual work plans and budgets guide the daily activities throughout the year.

 

 

The Government Performance and Results Act of 1993  (GPRA)

 

This Annual Performance Plan is written in part to fulfill the requirements of the Government Performance and Results Act (GPRA).  Congress passed this law in 1993 to bring the federal government into the “performance management revolution.”  Performance management is a goal-driven management concept and practice already widely adopted by the private sector, state and local governments, and many others.  GPRA requires federal agencies to develop 1) a Strategic Plan, 2) Annual Performance Plans, and 3) Annual Performance Reports in order to more effectively and efficiently manage their activities to achieve their missions, and to more effectively communicate with the Congress and the American people.  Please see the park’s Strategic Plan for more information about GPRA and performance management.

 

It should be noted, however, that the following Annual Performance Plan is much more than just a response to legislative mandate.  The law was a catalyst that caused the park staff to reexamine its daily activities and its routine products and services, as well as funding and staffing expended to accomplish them.  It motivated and energized us to make sure these things were well aligned with the mission of the National Park Service and Whitman Mission N.H.S., and the long-term goals established to achieve those missions.  We believe the results will be better planning, better management, and better communication with all of our constituencies and stakeholders, as well as amongst ourselves, about where we are, where we need to be, and how we are going to get there in the most effective and efficient ways.


Return to Table of Contents

 

II.  MISSION STATEMENT

 

It is the mission of the National Park Service at the Whitman Mission National Historic Site to preserve the Mission site established by Marcus and Narcissa Whitman at Waiilatpu, to maintain and preserve the memorial established to the Whitmans and to provide insight into the events surrounding the mission and the people and cultures those events affected.


Return to Table of Contents

 

III.  ACCOMPLISHING GOALS

 

The Whitman Mission N.H.S.’s annual goals for FY 2003 will be accomplished using the fiscal, human, and infrastructure resources summarized below.  Following this overview, a work plan, see Appendix A, for each annual goal outlines the activities, services, and/or products, along with their personnel and fiscal costs that will be carried out to achieve the annual goal.  Worksheets also indicate baseline information, performance definitions and measures, responsible parties, etc.

 

Human and fiscal resources available to achieve the park’s FY 2003 annual goals include a base operating budget of approximately $661,000.00, and a “full time equivalent”, (FTE), work force of 13.  The primary facilities located at this historic site include a maintenance shop, public water supply, and a visitor center that incorporates the administrative offices, museum, archives, auditorium, and visitor information desk.

 

Given the mission of the National Park Service, and Whitman Mission N.H.S., all expenditures, both fiscal and human, are related to resource protection.  However, four conventional categories are used to identify where the budget and people are allocated. 

 

Resource Preservation and Management:  Approximately $180,000.00 and three (3) F.T.E.s are dedicated to “hands on” resource protection.  This would include actions such as maintaining the ground cover over archeological sites, controlling invasive, non-native plants, documentation of the archives collection and a host of other activities.

 

Visitor Services:  Approximately $205,000.00 and four (4) F.T.E.s are dedicated to conducting Visitor Center operations, school programs, orientation and museum operations.  In general, cost associated with this category have direct bearing on visitor satisfaction, and understand, of the mission of the park.

 

Faclities Operations and Maintenace:  Approximately $204,000.00 and four point five (4.5) F.T.E.s are dedicated to roads and trails maintenance, landscape/grounds maintenance and cleaning the restrooms.  Actions and cost associated with this general category normally relate to visitor satisfaction and resource protection.

 

Park Administration:  Approximately $72,000.00 and one point five (1.5) F.T.E.s are dedicated to administrative overhead.  The actions and cost associated with this category include much of the “compliance and process” work associated with running a park.  These actions are made in support of all the goals.

 

Resource Preservation and Management

        $180,000.00

        3.0

Visitor Services

        $205,000.00

        4.0

Facility Operations and Maintenance

        $204,000.00

        4.5

Park Administration

            72,000.00

        1.5

                           Total

        $661,000.00

      13.0 F.T.E.

 

 

The Whitman Mission N.H.S. staff is led by a superintendent.  The staff is organized into three operating divisions: Interpretation and Resource Management, (I&RM), Maintenance, and Administration.  Staff expertise and specialties in the Interpretation and Resource Management division include 1 chief ranger, 2 full time park rangers, 1 part time park ranger and 1 education specialist.  There are approximately 5 seasonal (temporary) park rangers working in interpretation during the spring, summer and fall.  The Maintenance division includes 1 facility manager, 2 maintenance workers and 2 seasonal laborers.  The Administration division includes 1 administrative officer and 1 administrative assistant.  Park infrastructure for accomplishing the FY 2003 annual goals includes 1 visitor center with attached, theater, museum, and support offices plus the maintenance facility, and the memorial.


Return to Table of Contents

 

IV.   ANNUAL GOALS

 

Annual goals are the current year’s increments toward achieving the park’s long-term goals.  Long-term goals, in turn, are five-year increments toward achieving mission goals.  Mission goals are statements of ideal conditions pursued “in perpetuity” to achieve the mission of the Whitman Mission National Historic Site.  The annual goals below are listed in the context of their long-term and mission goals.  Please see the park’s Strategic Plan for details and background on mission, mission goals, and long-term goals.

 

 

Goals

 

Following are the park’s annual goals for fiscal year 2003.  The numbering sequence follows that of the NPS Servicewide plan.  Goal categories and mission goals are in regular type.  Long-term goals are italicized.  Annual goals are in bold type.

 

 

 

Goal Category I     Preserve Park Resources

 

Ia   Whitman Mission N.H.S. cultural resources and associated values are protected and preserved for present and future generations.

 

Ia01A   By September 30, 2005: 100% of the targeted disturbed lands, (66 acres), within the park will receive mitigation treatments aimed at maintaining the native plants and animals and preventing the invasion of non-native plants and animals on a annual bases.

 

Ia01A  By September 30, 2003: 66 acres of  the targeted park lands will receive treatments, per the Natural Resources Management Plan (RMP), aimed at maintaining the native species and controlling exotic /invasive species.

 

Maintain 66 acres of park lands for native species and prevent the invasion of non-native species .  (100 total acres in park, of which 66 are to be maintained/managed for native species, 41 acres were maintained for native species in FY97, with a goal of adding an addition 5 ac. each FY.)  Specific actions will include maintaining state certification for herbicide applications, developing a “fire management plan”, control fire on 15 acres and spot treatment of invasive plants with herbicides. Work Plan


Return to Table of Contents

 

 

Ia1B  By September 30, 2005: 100% of the targeted  lands, (25 acres), having invasive non-native plants that pose the greatest threat to native species and natural processes within the park will be restored.

 

Ia1B  By September 30, 2003: 3 acres of  the targeted park lands will receive vegetation treatment, per the Natural Resources Management Plan (RMP), aimed at eliminating exotic /invasive plants.

 

Eliminate exotic vegetation in 3 acres of land that has been invaded by non-native plants. ( 100 total acres with 66 acres managed for native species, 25 acres needing restoration as of 1997,  with a goal of eliminating invasive species in an additional 3 ac. during each FY.) Work Plan  


Return to Table of Contents

 

 

Ia5  By September 30, 2005:  100% of the parks structures, on the 1998 LCS, are in good condition.

 

Ia5  By September 30, 2003: 100% of the 6 structures on the 1998 List of Classified Structures (LCS) are in good condition.

 

100% of 6 (all 6 structures on LCS)

 

Good condition is defined as the structure, or significant feature, needs only routine or cyclical maintenance. Measuring goal achievement and verification of measures will be by on-the-ground inspection, photo documentation, and completion reports. Work Plan


Return to Table of Contents

 

 

Ia6  By September 30, 2005: 90% (or 112 of 123 standards) of the preservation and protection conditions in the museum collections meet professional standards as identified in the NPS Checklist for Preservation and Protection of Museum Collections.

 

Ia6  By September 30, 2003: 92% (or 112 of  123 standards) of the standards for preservation and protection conditions in the museum collections meet professional standards as identified in the NPS Checklist for Preservation and Protection of Museum Collections.

 

112 (or 5 new) standards of the targeted 112 standards will be met. (of the 123 standards 88 were applicable and met as of baseline year of 1997.  The goal is to add an additional 5 each year to reach 112 by the year 2003.)  Measuring the goal will be by inspection and completion reports. Work Plan


Return to Table of Contents

 

 

Ia7  By September 30, 2005:  100% of the cultural landscapes on the Cultural Landscape Inventory are in good condition.

 

Ia7  By September 30, 2003:  The historic scene within the park is maintained.  Meetings are held with NRCS and other partners/landowners to develop a plan for a flowing Doan Creek, (per General Management Plan).

 

1 of 1 landscapes maintained, strategies developed. Good condition is defined as the landscape, needs only routine or cyclical maintenance. Measuring goal achievement and verification of measures will be by on-the-ground inspection, photo documentation, and completion reports. Work Plan


Return to Table of Contents

 

 

 

 

 

Ia8  By September 30, 2005:  100% of all documented archeological sites are in good condition

 

Ia8  By September 30, 2003:  The area around the 3 known archaeological sites are managed to minimize the disturbance and protect “in-situ” artifacts.

 

3 of 3 sites will be maintained in good condition.  Good condition is defined as the sites will need only routine or cyclical maintenance. Measuring goal achievement and verification of measures will be by on-the-ground inspection, photo documentation, and completion reports. Work Plan


Return to Table of Contents

 

 

Goal Category II     Provide for the Public Enjoyment and Visitor Experience

 

IIa   Visitors safely enjoy and are satisfied with the park facilities, services and interpretive programs.

 

IIa1  By September 30, 2005, 90% of park visitors are satisfied with appropriate park facilities, services and recreational opportunities.

 

IIa1  By September 30, 2003:  More than 90% of park visitors continue to rate their satisfaction with park facilities as good or very good.

 

The Whitman Mission N.H.S. is visited by approximately 75 thousand visitors each year.  To maintain visitor satisfaction, the facilities must be constantly cleaned and maintained.  The mission grounds and memorial requires extensive landscaping care.  Security is provided to protect the entire complex. In FY2001, multiple projects will be completed to enhance the visitor’s experience.  These projects include adding “closed captioning” to the orientation film and replacing worn and discolored exhibits. Goal achievement will be measured by visitor feedback about the facilities. Measuring the goal will be through visitor survey cards and comment sheets filled out by visitors at the park. Work Plan


Return to Table of Contents

 

 

 

IIa2  By September 30, 2005: reduce the visitor safety incident rate by 10% from the Park’s five-year average (1992-1996 - 3.16 per 100,000 visitor days.)

 

IIa2  By September 30, 2003, no new visitor incidents will have occurred.  (Given the current visitor incident rate, park visitation and the formula for determining incident rates per 100,000 visitor days, incremental reductions in visitor incident rates is not possible.  One visitor incident over the 5 year period will result in the same incident rate, two (2) incidents over the 5 year period will double the visitor incident rate.)

 

During FY2003 no visitors will be injured.

 

The Whitman Mission N.H.S. baseline for visitor safety incidents is .63 incidents per 100,000 visitor days. The most frequent visitor incident is caused by falling.  The park staff will maintain the facilities and NPS area in a safe condition.  The interpretive staff will stress safety to visitors entering the theaters. Visitor safety incidents will be analyzed and discussed by the staff and corrective actions developed from the analysis. The goal for 2003 is to have no visitor injuries during the year.  Goal achievement will be measured by the number of visitor safety incidents per 100,000 visitor days. Measuring the goal will be by documenting the number of incidents through case incident reports. Work Plan


Return to Table of Contents

 

 

IIb   Park visitors and the general public understand, appreciate and support the preservation of the Whitman Mission N.H.S. and its associated resources for this and future generations.

 

IIb1 By September 30, 2005, 80% of park visitors understand, appreciate and support the significance of the Whitman Mission N.H.S..

 

 

IIb1  By September 30, 2003: Develop and conduct interpretive programs and material that convey the significance of WHMI and inform visitors about the mission of the National Park System.

 

The Whitman Mission N.H.S. receives over 70,000 visitors each year who participate in the interpretive program.  The visitors’ experience and comprehension of the park resources and history grow from the information, orientation, museum exhibits, and library, as well as the interpretation and education programs.  Visitor services are offered 362 days per year.  The school program will be maintained with the junior ranger program school visits, both on and off site, as well as teacher workshops.  Goal achievement will be measured by the number of visitors who understand the significance of the park as reported through the visitor survey cards and comment sheets filled out by visitors at the park. Work Plan


Return to Table of Contents

 

Goal Category IV     Ensure Organizational Effectiveness

 

IVa   Whitman Mission N.H.S. uses current management practices, systems, and technologies to accomplish its mission.

 

 

IVa4  By September 30, 2002: By September 30, 2005: Increase by 20%, over 1998 levels, the representation of underrepresented groups in the park’s seasonal workforce.  Two (2) of the six (6) seasonal positions hired would be from underrepresented groups.  (Due to little turnover in permanent workforce emphasis is being placed on seasonals.)

 

IVa4  By September 30, 2003: To hire one additional seasonal from the underrepresented groups.

 

The Whitman Mission N.H.S. is committed to increasing diversity in the NPS workforce. Permanent position openings are rare at the Whitman Mission N.H.S.. Therefore, the diversity strategy at the park will target recruitment for seasonal employees. Goal achievement will be measured by the number of hires made from underrepresented groups. Measuring the goal will be through documentation of new hire statistics. Work Plan


Return to Table of Contents

 

 

IVa6A  By September 30, 2005 Reduce by 50% from the park’s 5-year (FY1992-FY1996 average, the park’s employee lost time injury rate of 2 incidents per 100 employees and keep the average cost of new worker’s compensations cases (COP) to less than $100.00.  (Reducing cost by 50% based on the park’s  5-year (FY1992-FY1996) average, per the national goal, is not practical given the parks current average costs of  $53.41.)

 

IVa6By September 30, 2003:  The single year employee lost time injury rate (FY2001) will be at, or below, the 5 year average of 2 incidents per 100 employees.  (Incremental reductions will be almost impossible given the FTE and incident rate for the park.  Over the 5 year base period only one employee incident occurred.  Given that, we will either remain at the same incident rate or decrease/increase by 100%)

 

Achievement of the goal will be measured by the number of employee safety incidents per 100 employees. Measuring the goal will be through the SMIS system. Work Plan


Return to Table of Contents

 

 

 

V.  ANNUAL PERFORMANCE  PLAN PREPARERS

 

The following park staff members were involved in preparing this Annual Performance Plan:

 

Francis T. Darby, Superintendent, GPRA Coordinator

Roger Trick, Chief Ranger

Bruce Hancock, Facility Manager

Gloria La France, Administrative Officer


Return to Table of Contents

APPENDIX

FY2003 Annual Work Plan

 

Park/Program Name:         Whitman Mission National Historic Site           

Park/Program Goal Id. No.     Ia01A                                                                          Page         1   of   11        

 

Servicewide Goal Identification number:  Ia01A

NPS Servicewide Mission or Long-term Goal text: By September 30, 2005: 5% of targeted disturbed park lands, as of 1997, are restored, and 5% of priority targeted disturbances are contained.

 

Park/Program Long-term Goal:   By September 30, 2005: 100% of the targeted disturbed lands, (66 acres), within the park will receive mitigation treatments aimed at maintaining the native plants and animals and preventing the invasion of non-native plants and animals on a annual bases.

 

Baseline Year:

 

      1997

Target Year:

 

      2005        

Park/Program Annual Goal:  By September 30, 2003: 66 acres of the targeted park lands will receive treatments, per the Natural Resources Management Plan (RMP), aimed at maintaining the native species and controlling exotic /invasive species.

 

Performance Target this FY:  Maintain 66 acres of park lands for native species and prevent the invasion of non-native species .  (100 total acres in park, of which 66 are to be maintained/managed for native species, 41 acres were maintained for native species in FY97, with a goal of adding an addition 5 ac. each FY.)

 

Indicator (thing measured):

acres maintained/managed  for native species

Baseline number:

 

                66 acres

Status in base year:

 

          41 acres

Desired condition:

 

      maintained

Unit of measure:

 

          acres

Actual Accomplishment this FY:

Comment: (Provide narrative explanation is goal if not met or is exceeded)

 

 

 

FY2003 Annual Work Plan

Work Plan:  Product/Service/Activity

Division

Responsible

Funding Source (optional)

Dollars

(opt)

FTE

(opt)

Maintain certification for herbicide application

 

Darby

         ONPS

     $ 1,000.00

 

Reduce fuel loads on 15 acres through control fire.

 

Darby

         ONPS

        9,000.00

 

Spot treat invasive plants (herbicide, direct attack, fire).

 

Darby

         ONPS

     $10,000.00

 

Plant/Replant native and native like species

 

Darby

         ONPS

     $10,000.00  

 

Manually pull rye grass on east boundary

 

Darby

         ONPS

     $  1,000.00

 

Oversight

 

Darby

         ONPS

      $ 9,000.00

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Total Cost and FTE (must be provided in total for each annual goal)