UNITED
STATES DEPARTMENT OF THE INTERIOR
NATIONAL PARK SERVICE
Dams and Appurtenant Works
Maintenance, Operation, and Safety
Reference Manual 40
Release No. 1
April 2005
This guideline provides an outline of responsibilities for NPS personnel in the planning, design, preservation, rehabilitation/construction, maintenance and operation, inspection, acquisition or disposal of dams under NPS management. Instructions on recommended coordination with local officials and non‑NPS dam owners are given also: It is not intended as a technical manual but as a management guideline. A list of recommended technical references is provided in Appendix B.
Application of the guideline by NPS personnel should be commensurate with each dam's size, complexity, operational importance, hazard potential classification, and ownership. Inquires about the application of the guideline may be made to the park, regional, or Washington Office NPS Maintenance, Operation, and Safety of Dams (MOSD) Program coordinators.
CONTENTS
Chapter 1. INTRODUCTION
A. General...................................................
B. Management Objectives.........................
C. Applicability...........................................
D. Definitions.............................................
Chapter 2. ORGANIZATIONAL MANAGEMENT
A. Authorities............................................
B. Management Responsibilities...............
C. Inventory Data Base Management........
D. Staffing.................................................
E. Funding and Personnel Resources........
F. Documentation.....................................
G. Technical Reviews..............................
Chapter 3. NPS PLANNING AND ENVIRONMENTAL EVALUATION PROCESS FOR PROPOSED OR EXISTING DAMS
A. General................................................
B. Acquisition, Holding, or Disposal.......
C. Floodplain and Wetland Protection.....
D.
Chapter 4. MANAGEMENT OF TECHNICAL ACTIVITIES - SITE INVESTIGATION AND DESIGN FOR PROPOSED OR EXISTING DAMS
A. General...................................................
B. Hydrology..............................................
1. Hazard Evaluation...............................
2. Flood Development.............................
3. Flood Selection for Design (or Evaluation)......
4. Hydrologic Design of Reservoir.......................
5. Downstream Effects...................................
6. Warning Systems.......................................
C. Earthquake Investigation and Design.......................
1. Investigation Factors.................................
2. Selection of Design Earthquakes.......................
3. Engineering Seismology................................
4. Need for Earthquake Analysis..........................
5. Seismic and Geologic Studies..........................
6. Design for Earthquake Forces..........................
D. Geotechnics...............................................
1. General...............................................
2. Exploration and Identification of Geotechnical Problems
3. Geotechnical Design........................,..........
4. Foundation Treatment...............................
5. Instrumentation.......................................
6. Inspection and Continuing Evaluation During Construction
7. Reevaluation at Existing Structures
E. Hydraulic, Appurtenances................................,
1. General..:..........................................
2. Design Flood Releases................................
3. Other Water Releases.................................
4. Reservoir Evacuation................................
5. Control of Flows During Construction.................
6. Design Criteria and Guidance..............................
F. Concrete Dams and Concrete Elements of Embankment Dams....
1. Site Specific Design...............................
2. Materials............................................
3. Design of Structures............................
4. Definition of Loads..................................
5. Design Methods......................................
6. Design Evaluation.....................................
7. Instrumentation.......................................
8. Construction and Operational Follow-up.................
G. Embankment Dams..........................................
1. Site Specific Design...............................
2. Materials.............................................
3. Design Constructability................................
4. Embankment Design....................................
5. Instrumentation......................................
6. Construction and Operational Follow-up...............
Chapter 5. MANAGEMENT OF TECHNICAL ACTIVITIES - CONSTRUCTION & REHABILITATION OF DAMS
A. Introduction..............................................
1. Construction Contracts.............................
2. Construction/Design Interface.........................
B. Evaluation During Construction............................
1. Design Related........................................
2. Foundation............................................
3. Materials.............................................
4. Construction General................................
D. Construction Assurance...................................
1. Construction Procedures...............................
2. Construction Materials Testing.......................
3. Quality Assurance.....................................
Chapter 6. MANAGEMENT OF TECHNICAL ACTIVITIES - OPERATION AND MAINTENANCE
FOR PROPOSED OR EXISTING DAMS AND APPURTENANT WORKS
A. General...................................................
B. Operation and Maintenance..................................
1. General...............................................
2. Operating Procedures..................................
3. Maintenance..............................
C. Periodic Inspection Program..............................
1. General.............................................................
2. Types and Frequencies of Inspections................
3. Instrumentation......,.............................
4. Correction of Deficiencies..........................
5. Documentation.....................................
6. NPS Observer Status at non-NPS Dams...................
D. Emergency Action Planning.................................
1. General..............................................
2. Coordination with non-NPS Dam Owners.............
3. Evaluation of Emergency Potential.....................
4. Actions to Prevent or Minimize Effects of Failure....
5. Actions upon Discovery of a Potentially Unsafe (Seriously Deficient) Condition…
APPENDICES
A. NPS Inventory of Dams
B. Recommended References For Maintenance, Operation, and Safety of Dams
C. Regional Coordinators and
D. Data Book Listing
E. Example Emergency Action Plan
F. State Safety of Dams Officers
G. Example Letter To Non‑NPS Dam Owner or Regulatory Agency (Preferably)
H.
List of Official Technical Supplements to Director’s
Order #40 and Reference Manual(RM)-40
CHAPTER ONE
INTRODUCTION
A. General
Dams and their appurtenant works represent a valuable resource to the National Park System and require careful management. The purpose of this guideline is to outline management responsibilities for the preservation/maintenance, operation, and safety of dams under NPS jurisdiction as respectively required by Statute 16 U.S.C. 1 and Departmental Manual Part 758.
These responsibilities include, but are not limited to, planning, design, preservation, rehabilitation/construction, maintenance and operation, inspection, acquisition or disposal of dams under NPS management, and coordination with local officials.
The guideline is not intended as a standard for technology of dams. Current references dealing with the technology of dams and appurtenant works are provided in Appendix B. The guideline may be used, as appropriate, when coordinating with non‑NPS dam owners.
Application of this guideline by Regional Directors, Superintendents, and Manager, Denver Service Center (DSC), should be commensurate with each dam's size, complexity, operational importance, hazard potential, and ownership.
Non‑NPS dams also will be monitored carefully and information about them kept within the NPS inventory data base management system. These are dams and appurtenant works for which NPS managers have no direct operational responsibility; but where their failure or misoperation could have a definite effect on park safety or operations. Regional Directors and Superintendents will request observer status during inspections and in the preparation and review of emergency action plans at non‑NPS dams that significantly affect park areas. A list of such dams is available in the most current NPS Inventory of Dams, Appendix A.
The NPS Park Facility Management Division has overall responsibility for the coordination of the Maintenance, Operation, and Safety of Dams (MOSD) Program; however, there are many NPS programs‑land acquisition, cultural resources management, design, construction, law enforcement, security, and public safety that are closely interrelated and should be properly coordinated. A qualified engineer should be assigned by each Regional Director to assure the implementation of all appropriate portions of this guideline when a major action is undertaken in the acquisition, advance planning; preservation/design/construction formal inspection, or disposal of either high (1) or significant (2) hazard potential dams under NPS management. Low (3) hazard potential dams will still receive periodic inspections to assess any changes in their hazard potential, to evaluate maintenance and repair needs, and to determine if they are still essential to park operations. Non‑essential dams and appurtenant works should be dewatered and removed in an environmentally sound manner.
Regional Directors and Superintendents will provide, as appropriate for each type and size dam, documentation and reporting as indicated in Chapter Two, section F.
B. Management Objectives
The following objectives are given for the Maintenance, Operation, and Safety of Dams (MOSD) Program:
‑Establishment of MOSD Program within WASO and Regional Park Facility Management Divisions with designated program coordinators and/or project engineers;
‑Assure management control of technical activities;
Maintain inventory data base on any size, type, owner, or status dam that will affect or is affecting park operations or safety,
Conduct proper planning, design, construction management, or periodic inspection of all dams under NPS management,
Perform corrective action or disposal of deficient dams under NPS management,
‑Provide sufficient funding and personnel to support these responsibilities;
‑Integrate MOSD Program into other NPS activities, funding sources, and programs;
Routine Maintenance (park facility and maintenance staff),
Cyclic Maintenance (park facility and maintenance staff ),
Repair and Rehabilitation (park facility and maintenance staff ),
Cyclic Maintenance of Cultural Resources (cultural resources and facility/maintenance staff),
Cultural Resources Preservation Fund (cultural resources staff),
Construction and Major
Rehabilitation (park facility/maintenance and
Risk Management (occupational and public type safety at dam as pertains to heights/depths, dangerous flows and equipment),
Visitor Services Division (guard against vandalism and coordinate emergency action plans at certain NPS and non‑NPS dams),
Land and Structures Acquisition (purchase of dams and appurtenant works).
This is not an all‑inclusive list. NPS managers should be constantly alert to what impact both NPS and non‑NPS dams have on park safety and operations.
C. Applicability
Regional Directors and Superintendents will be responsible for the upkeep of the NPS inventory data base system (Appendix A) for any size, type, owner, or status dam (planned acquisition or disposal) that affects park maintenance, operations, resource, or safety. Where projects do not have any purpose, they should be dewatered and removed under the supervision of qualified personnel and project areas restored. For those dams that are used for park management and operations, NPS managers will annually schedule, as appropriate, funding and personnel to assure that their structures are properly planned, designed, rehabilitated, constructed, maintained, operated and periodically inspected. MOSD program personnel should be contacted immediately when a dam is planned for acquisition or disposal. They will be responsible for the evaluation and inventory of the structure into the MOSD program. A formal safety report including cost estimates to correct identified deficiencies should precede the appraisal of a dam site. The condition of the dam may have a bearing on the fair market value of the property.
D. Definitions
1. General. The following definitions apply to this guideline. More detailed definitions are provided in the explanation of terms used in the NPS inventory of dams database management system as given in Appendix A.
2. Dam or Project. Any artificial or natural barrier including appurtenant works (spillways, inlet and outlet works, tunnels, pipelines, penstocks, power stations, diversions. penstocks, canals, gates, conduits, navigation locks, instrumentation, or mechanical and electrical equipment) that impounds, controls, stores, or diverts streamflow and affects park maintenance, operation, resource, or safety. In some cases these structures will include embankments used for trails, roads, or railroads and during heavy runoff would act as dams and thus pose a possible hazard potential. Also landslides and ice formations need to be evaluated as a possible dam. For the management of NPS dams, there is no limitation to size, type, or status (proposed acquisition or disposal) in regard to these criteria. Dams not essential for environmental preservation, management, or operation of parks should be dewatered and breached under the supervision of qualified personnel and the project area restored. In some cases, the impoundment areas have become filled with sediment or covered by vegetation such that removal or restoration is too expensive or damaging to park resource. In these cases, the dam will still need to be maintained to prevent the impounded sediment or any other material from being discharged downstream if the dam were to fail. This guideline applies with equal force whether the dam has a permanent reservoir or is a detention dam for temporary storage of floodwaters.
In addition to conventional structures, this definition of "dam" specifically includes "tailing dams," embankments built by waste products disposal and retaining a disposal pond.
3. Hazard Potential. Potential loss
of life or property or resource damage downstream of a dam from floodwaters
released at the dam, or water released by partial or complete failure of the
dam, and upstream of the dam from effects of rim slides or upstream dam
failure. Also the effect of a failure, partial failure, or other incident
should be considered for highways, roads, or trails crossing over the dam. A
hazard potential is considered significant if there is a potential to cause
loss of life or major damage to permanent structures, utilities, or
transportation facilities. A detailed description of hazard potential is
provided below. It is not an indicator of structural, maintenance,
operational or safety condition.
HAZARD POTENTIAL CLASSIFICATION |
|||
|
CATEGORY |
Loss of Life (Extent of Development) |
Economic or Environmental Loss (Extent of Development or Resource) |
|
|
5=Deactivated |
Not possible including
any serious injury from remnants of deactivated projects |
None Possible |
|
|
See Note 1 |
4 = Unknown |
Unknown (A hazard assessment should be performed promptly) |
Unknown (A hazard assessment should be performed promptly) |
|
3 = Low |
None expected (No permanent facilities, campsites, or other visitor use areas) |
Minimal (Undeveloped to occasional facilities or agriculture. No significant park resources) |
|
|
See Notes 1 and 2 |
2 = Significant |
Few (No urban developments and no more than a small number of inhabitable facilities, or visitor use areas) |
Appreciable (Notable agriculture, industry structures, or park resources) |
|
1 = High |
More than few |
Excessive (Extensive community, industry or agriculture, or park resources) |
|
Note 1: Annual Informal Inspection required. See Chapter 6, section C, 2, a.
Note 2: Formal Inspection required every five years. Intermediate Inspection required every two years. See Chapter 6; section C, 2, b and c.
4. Occupational and Public Type Safety. See Chapter 6, section B, 2. The following features or conditions may exist at a structurally sound dam but still pose a hazard potential to NPS personnel or public safety:
a. Waterways
(1) Spillways
(2) Sluices
(3) Intake and release structures
(4) Submerged objects
b.
(1) Embankments
(2) Walls
(3) Cat Walks
c. Mechanical or electrical equipment at dam
5. Dam Failure. Catastrophic type of failure characterized by the sudden, rapid, and uncontrolled release of impounded water. It is recognized that there are lesser degrees of failure and that any malfunction or abnormality outside the design assumptions and parameters which adversely affects a dam's primary function of impounding water is properly considered a failure. They are, however, normally amenable to corrective action.
6. Maintenance. Maintaining structures and equipment in intended operating condition; equipment repair and minor structure repair.
7. Listed are some of the essential National Park Service Operations for dams.
a. Irrigation
b. Hydroelectric Power Generation
c. Flood Control
d. Navigational Lockage
e. Water Supply
f. Recreation
(1) Camping, Sunbathing, or Sightseeing
(2) Swimming and Bathing
g. Conservation of Natural Habitat and Cultural Resources
h. As Bridges, Roadways, and Hiking Trails
8. Rehabilitation or Improvement. Repair of structural deterioration to restore original condition; alteration of structures to improve dam stability; enlarge reservoir capacity, or increase spillway and outlet works capacity; replacement of equipment.
9. Emergency Action Plan. Formal plan of procedures to alleviate dangers during construction of or after completion of a dam to reduce loss of life or damages if conditions develop in which dam failure or misoperation is likely or unpreventable.
CHAPTER TWO
ORGANIZATIONAL MANAGEMENT
A. Authorities
1. 16 U.S.C. 1. General legislative authority for the management and operation of park areas. It includes the maintenance and rehabilitation of those facilities as designated an integral part of the park operation.
2. Public Law 107-310 (The Dam Safety and Security Act of 2002) Re-authorization of the National Inventory for Federal and non‑Federal dams, safety inspections of non‑Federal dams, development of a comprehensive program for the inspection and regulation of dams for safety purposes, and inclusion of security.
3. Federal Guidelines for Dam Safety,
4. Executive Memorandum,
5. Departmental Manual Part 753 ‑ Specific implementation of DOI program
a. Each agency has responsibility of operating own program.
b. Bureau of Reclamation coordination and advice on DOI agency programs.
c. Important objectives:
(1) Complete an accurate inventory,
(2) Initiate periodic inspections and necessary corrective action,
(3) Develop emergency action plans at appropriate dams.
6. NPS Management Policies, sections 1.5, External Threats and Opportunities; 8.2.5.2, Emergency Preparedness and Emergency Operations; and 9.5 Dams and Reservoirs
B. Management Responsibilities
1. General. The Director is responsible for the development and implementation of policy, resources, and procedures for the maintenance, operation, safety, or else deactivation (non-essential) of each dam under his control. The Associate Director of Park Planning, Facilities, and Lands, with her/his park facility management staff, assists the Director in discharging this responsibility and shares in it. The Maintenance, Operation, and Safety of Dams Program is established as a component of the Park Facility Management Division. The field directorate is responsible for obtaining compliance with this guideline and assuring that procedures are carried out.
Regional Directors, Superintendents, and Manager,
2. Design Responsibility. The design function can never be considered finished as long as the dam remains in place; design involvement should continue throughout construction and operation of the project. Regional Directors should establish appropriate programs for on‑site construction and operational inspections for review by appropriate design personnel and technical specialists. The program will include frequent and mandatory inspections during construction to confirm that site conditions conform to those assumed for design or to determine if design changes may be required to suit the actual conditions.
The design function includes responsibility for planning any dam instrumentation to be installed during construction and/or operation to monitor conditions that could potentially threaten dam safety.
An initial reservoir filling and surveillance plan will be prepared by the design staff.
3. Construction Responsibility. The responsibility for administering construction and supply contracts, for understanding the design and contract intent, for maintaining technical coordination between design and construction engineers, and for managing the construction staff to assure compliance with specifications should be vested in an identified engineer at the construction project for important dams. Important dams are those classified as high (1) or significant (2) hazard potential, those whose failure would significantly impact park operations or resources, or involving substantial investment. The project engineer should have the administrative and technical control of all resources necessary to accomplish safe construction of the dam. Construction personnel should understand the conditions upon which the design is based and the relationship between these conditions and the design features. When unanticipated conditions are encountered, design personnel should be involved in determining their effect.
4. Maintenance and Operation. The responsibility for project maintenance and operation is assigned to the facility/maintenance or engineering staff. They will handle any requirements for coordination with the Denver Service Center Regional Team or an engineering firm. They will be responsible for preparing annual informal inspection reports for all dams and appurtenant works under NPS management and assure that periodic formal and intermediate type inspection reports are prepared by qualified and licensed engineers for high (1) and significant (2) hazard potential dams under NPS management responsibility.
5. Technical Coordination. A project engineer should be assigned technical coordination responsibility for each dam under NPS management that has either a high (1) or significant (2) hazard potential classification. He should handle necessary technical coordination within the agency and with private and public organizations.
6. Emergency Action Planning. An emergency plan should be formulated by the appropriate Park Manager and his maintenance and law enforcement staff for each NPS dam that has either a high (1) or significant (2) hazard potential. The plan should be in the detail warranted by the size and location of the dam and reservoir. It should evaluate inundation areas resulting from floods or dam failure, and upstream conditions that might result from major land displacements or increased flood flows, including the effects from failure of upstream dams. Regional Directors and Superintendents will coordinate with non‑NPS dam owners when applicable to assure that appropriate emergency action plans are implemented for areas within park boundaries.
Where applicable, the plan should include inundation maps for the flows resulting from design floods and from possible failure of the dam. The complete emergency plan should be transmitted to appropriate local, state and Federal governmental bodies. The plan should be periodically reviewed and kept up to date, and periodically publicized to maintain awareness of its existence.
In addition to the emergency plan for the complete dam, a similar plan should be prepared for the construction period, including area facilities that may remain during the period and floods that may be anticipated.
7. Risk‑Based Analysis During Floodplain Evaluations. NPS managers should evaluate potential losses due to failure or misoperation, particularly when considering non‑structural alternatives in correcting dam deficiencies. Although the value of potential property losses can be estimated„ it is recognized that potential loss of lives can only be quantified, but not evaluated. On new dams, potential losses can be used in study of project alternatives and in assessment of additional safety incorporated into the dam facilities. On existing dams, a risk‑based analysis should be considered in establishing priorities for examining and rehabilitating the dams for improving their safety or for the disposal of the dam.
In compliance with Public Law 107-310 and Departmental Manual Part 753, the National Park Service has developed an inventory of dams based upon information from the U.S. Army Corps of Engineers National Inventory of Dams (NID), Bureau of Reclamation Inspections, and NPS field reports. See Appendix A. This inventory lists both NPS and non‑NPS dams that are located within or immediately adjacent to park boundaries and affect safety, operations, property, or resource. Dams are sorted in the following sequence:
1. Regional codes in alphabetical order;
2. Park Codes in alphabetical order;
3. Hazard Potential classification
4. Size Classification;
5. Structural height in feet;
6. Maximum impounding capacity in acre feet.
The current inventory provides information about inspection results, corrective action, emergency action plans (EAP's) and financial information. This data base will be reviewed periodically by NPS field management for completeness and accuracy and any changes submitted annually by September 30 to the Washington Office of the Park Facility Management Division. More frequent updating should be performed whenever any formal inspection reports or corrective actions are completed on either high (1) or significant (2) hazard potential dams.
Dams in this inventory are classified primarily by their hazard potential which is an indicator of risk and not structural condition. Dams are classified as high (1) or significant (2) hazard potential when their failure or misoperation would jeopardize life or damage significant park resources or facilities. Low (3) hazard potential dams normally would not.
NPS structures will receive annual informal inspections to evaluate operational reliability, maintenance, and any changes in hazard potential classification. Inspection and other evaluation results will be used to update the NPS inventory of dams.
Information requests from, and coordination with, non‑NPS dam owners should be well documented.
D. Staffing
1. Technical and Support. NPS managers should assure adequate and competent technical staffing or consultants from other agencies or engineering firms are available to perform the essential functions in planning, design, construction, operation and maintenance, acquisition, or disposal of dams under NPS management. These personnel should be well supported by administrative, clerical, and other elements to ensure that technical staff is not diverted from technical work.
Construction inspection staffing should assure quality as well as quantity inspection coverage. Staffing should be reviewed by higher authority than the local construction office.
The operating personnel must be qualified to perform the many functions required in the operation, including the recognition of conditions possibly detrimental to dam safety. Operation and maintenance staffing requires careful attention to personnel responsible for operating inspections, and to personnel who participate in the periodic inspection program. It is essential that support personnel and equipment are provided to accomplish needed maintenance activities.
2. Professional Advancement. NPS managers should maintain a positive program for advancement of technical personnel in recognition of acquired experience, training and education, and increased competence. It is essential that technical as well as the managerial expertise be required for safe, effective dam design, construction, and operating programs. Professional registration and active membership in professional and technical societies should be given due consideration in assessing qualifications for higher technical positions. Provision should be made for the establishment of procedures to screen and disseminate information on technical advances relating to dam design, construction, and maintenance and operation. Programs for continuing professional training should be oriented toward keeping the technical staff abreast of improved technology.
3. Training. To supplement technical staffing, NPS managers should provide internal personnel training. Provisions should be made for technical personnel to observe and participate in decision‑making meetings and to make site visits with more experienced staff. Staff members should be allowed to attend consultants meetings in order to gain valuable experience.
Technically qualified maintenance personnel should be trained in problem detection and evaluation, and application of appropriate remedial (emergency and non-emergency) measures.
Personnel involved in inspections should be trained for the requirements of these duties. The training should cover the types of information needed to prepare for the inspections, critical features that should be observed, inspection techniques, and preparation of inspection reports.
MOSD coordinators, maintenance personnel, and park emergency action plan (EAP) coordinators should complete training every two years to assure they stay abreast of developments in the maintenance, operation and safety of dams. Training for the inspection of dams is normally provided by the Bureau of Reclamation (USBR) on an annual basis. These courses are geared to persons not familiar with engineering or geology but who are responsible for the safety and maintenance of small dams. Contact Inspections and Emergency Management Group, Bureau of Reclamation, 303-445-2740 for further details.
Designated park emergency operations plan coordinators should attend training in the preparation, exercising, or use of EAP's and ensure their integration into the park’s overall emergency operations plan.
E. Funding and Personnel Resources
1. General. Continuity and adequacy of funding and personnel are essential to carry out the MOSD program objectives. The NPS budget formulation and execution system offers an opportunity for managers to identify funding priority for those activities, programs, staff levels, or other operating requirements to assure a sound MOSD program. Long‑term programming objectives should be developed and adhered to in order to establish a systematic program. To meet these objectives, the following activities should be properly staffed, funded and scheduled by Regional Directors and Superintendents:
|
Period |
Activity/Resource |
|
As necessary |
Staff |
|
Every two years |
Training |
|
Annually |
Update NPS Inventory of Dams |
|
Periodic Inspections: |
|
|
Annually |
Annual Informal Inspections ‑ All dams under NPS management responsibility and essential to park management and operations. |
|
Every two years |
Intermediate Inspection ‑ high (1) or significant (2) hazard potential dams only. |
|
Every five years |
Formal Inspections ‑ same type as above. |
|
As necessary |
Acquisition |
|
As necessary |
Project engineer assigned to either high (1) or significant (2) hazard potential dam during major rehabilitation or construction. |
|
As necessary |
Design, Plans, Specifications |
|
As necessary |
Independent Review of Design.(high (1) or significant (2) hazard potential dams) |
|
As necessary |
Major preservation, rehabilitation, or construction |
|
As necessary |
Independent Review of Construction (high (1) or significant (2) hazard potential dams) |
|
Annually |
Maintenance and Operations |
|
Prepare or update annually |
Emergency Action Plans |
|
As necessary |
Disposal (sale or removal) |
A base level program will be established in each applicable region, park, and DSC to assure that routine and recurring activities are properly funded and staffed. To assure cost effective management of NPS dams, the above sequence should be followed as closely as possible, particularly the periodic inspections which give a comprehensive evaluation of the dam's purpose and condition in relationship to park objectives.
2. Sources.
The primary funding and personnel source for this program is the maintenance,
repair/rehabilitation, or construction programs. Although Servicewide funding
for the MOSD program has been made available out of the Washington Office Park
Facility Management Division, it is now the responsibility of Regional
Directors, Superintendents, and Manager,
‑Cultural Resources Cyclic Maintenance
‑Preservation, Design and Construction
‑Risk Management Division (occupational and public type safety)
‑Law enforcement and ranger Activities (evacuation during imminent disasters)
‑Land Acquisition (acquire existing dams during land purchases).
3. Methods. There are several methods of requesting funding and personnel to assure the maintenance and safety of NPS dams. Reprogramming of funds/personnel is only for extremely, urgent action within the current fiscal year. This type of programmatic change would occur only when an NPS dam is found to be seriously deficient and poses an imminent threat to life and significant property, and immediate corrective action is necessary. Supplemental budget requests may be used during the current budget year to provide urgently needed funds or personnel, but some delay is allowable in performing corrective action. The regular budget formulation and execution process is used to program funds for routine but yet necessary activities. The NPS Operating Financial System (OFS) is used for preparing requests of annual operating type funding or personnel increases. Activities that would be programmed with this form are as follows:
‑Staff
‑Inventory Data Base Management ‑Training
‑Travel
‑Periodic Inspections
‑Routine Maintenance, Repairs, and Operation
‑Develop and Update Emergency Action Plans
The NPS Project Management Information System (PMIS) is normally used for multi‑year funding for substantial development projects involving major rehabilitation, reconstruction, or acquisition. In developing these funding and personnel resources, close coordination should be made with the budget officer.
4. Cost Accounting. Cost accounting should be used to assure cost effective management of funds and manpower utilized in the maintenance, operation, and safety of dams.
F. Documentation
1. General. Throughout project acquisition, development, and operation, all data, computations, engineering and management decisions should be documented for planning, site investigation, design, construction, initial reservoir filling, maintenance and operations, or disposal of dams under NPS management. The amount of documentation should vary with the level of hazard potential or operational importance of the structure. Dams under NPS management that have either a high (1) or significant (2) hazard potential classification will receive full documentation.
2. Design/Construction. Written documentation should be maintained in standardized format on all designs for the project. All phases of the construction should be documented, including reporting of routine and special activities. Changes in construction plans and departures from expected site conditions should be documented, with any consequent design changes. As‑built drawings should be prepared as facilities are completed, and should be made available to operation and maintenance personnel and to the dam inspection staff. An initial reservoir filling and surveillance plan should be prepared by the design staff. Initial filling should be well documented, including a record of reservoir elevations arid controlled water releases during the filling.
3. Operation and Maintenance Log. Operation and maintenance should. be fully documented, including the routine activities and systematic inspection processes, and complete information on project maintenance, rehabilitation, and improvements. In addition to records on the actual operations, the operating record should include data on reservoir levels, inflow and outflow, drainage system discharge and structural behavior.
If there are maintenance problems that require continuing remedial work, a thorough record of the work should be maintained, and a final report made after complete remedy of the problem.
4. Data Books. Data Books will be prepared by the Bureau of Reclamation (USBR) or other inspecting organization for all NPS high (1) or significant (2) hazard potential dams which are scheduled for formal inspection. Appendix E is a checklist of the types of existing data which will be valuable for evaluating the safety, maintenance, and operation of these dams. Existing information for these Data Books should be prepared and distributed by Regional Directors or Superintendents to USBR or other inspecting organization two months prior to the actual on‑site examination.
5. Required Reports. At the indicated times, Regional Directors and Manager, DSC, will submit the following reports or documents to the Director, Attention: Park Facility Management Division:
a. Immediately, report any partial or total dam or appurtenant works failure, misoperation, or uncontrolled release of reservoir affecting park resources, operations, or safety.
b. Immediately, report any injury, death, or significant property or resource loss because of dam failure, misoperation, or uncontrolled release of reservoir. Items wand b should be combined if appropriate.
c. Immediately, report any dam in seriously deficient condition, as so determined from a formal inspection, and whose failure or misoperation would affect park safety or operations. State what corrective action is being taken and when it will be completed.
d. Inventory update at least annually by September 30, on any size, type, owner or status dam (planned acquisition or disposal) 'that affects park resources, operations, or safety.
e. Report annually, by September 30, on any planned or actual major preservation, rehabilitation, construction, acquisition, or disposal of dams that affect park safety or operations.
f. Submit annually, by September 30, list of personnel responsible for coordination of maintenance, operation, and safety of dams program and any training that has been attended.
g. Submit annually, by September 30, a brief financial summary of funding, either programmed or spent by fiscal year, for this program. Items e and g should be combined if appropriate.
h. Distribute annually, by September 30, copies of completed and approved NPS Annual Informal Inspection (AII) reports.
i. Report annually, , by September 30, on the status of park emergency operations plans (EOP’s) in which are integrated emergency action plans for any High or Significant hazard potential dams affecting the park. Also for NPS affected areas, an Early Flood Warning, Search/Rescue, Evacuation, and Recovery Plan (ESEP) should be integrated in the park’s EOP.
G. Technical Reviews
1. Extent. All factors affecting the safety of high (1) or significant (2) hazard potential dams under NPS management will be reviewed during design, construction, and operation on a systematic basis. Reviews include those internal to the agency and those external to the agency by individuals or boards (consultants) with recognized expertise in dams.
2. Internal. Provision should be made for automatic internal review of all design and construction decisions, methods, and procedures related to dam safety. Reviews should be at levels of authority above the design section or designer‑supervisor relation.
3. External. An appropriate level of independent review by a qualified engineering firm or other Federal agency (i.e., Bureau of Reclamation) with safety of dams expertise should be performed during design or construction of dams under NPS management.
CHAPTER THREE
NPS PLANNING AND ENVIRONMENTAL EVALUATION PROCESS
FOR PROPOSED OR EXISTING DAMS
A. General
Considerable information has been compiled in Appendix A about dams that affect park maintenance, operations and safety. Information on these facilities is updated periodically in the NPS inventory of dam data base which is discussed in Chapter Two, section C, and is readily available upon request. These dams should be appropriately considered during the NPS planning and environmental evaluation process in the following sequence of activities to assure their systematic management:
‑Inventory of any size, type, owner, or status (proposed acquisition or disposal) dams that affect park maintenance, operations, or safety; ‑Periodic inspection of any of the above dams under NPS management, including dams proposed for acquisition. If possible, estimates of funding and personnel should be included for corrective action or disposal;
‑Acquisition of dams. A formal safety report including cost estimates to correct identified deficiencies should precede the appraisal of a dam site. The condition of the dam may have a bearing on the fair value of the property.
‑Qualified NPS project engineer or coordinator assigned to any high (1) or significant (2) hazard potential dam undergoing detailed investigation to assure coordination with guideline;
‑Preparation of design, plans, and specifications for major preservation, rehabilitation, or construction;
‑Independent review of design, plans, and specifications of high (1) or significant (2) hazard potential dams;
‑Performing preservation, major repair or rehabilitation, reconstruction, or construction;
‑Independent review of preservation, major repair or rehabilitation, reconstruction, or construction on any high (1) or significant (2) hazard potential dams;
‑Maintenance and operations;
‑Emergency action plans at either high (1) or significant (2) hazard potential dams; and
‑Disposal (sale or removal and restoration of drained impoundment).
B. Acquisition, Holding, or Disposal
During the acquisition, holding, or disposal of dams at NPS administered areas, proper planning should be undertaken to assure compliance with the National Environmental Protection Act (NEPA) of 1969, Public Law 91‑190, as amended; various Executive orders on floodplains, wetlands, and safety of dams; and the Section 404 Permit Program by the U.S. Army Corps of Engineers. The objectives of these regulatory requirements are to help provide a safe, ecologically and culturally complementary, and favorable benefit/cost ratio project. This guideline on the maintenance, operation and safety of dams should be properly integrated into the NPS planning and environmental evaluation process. Any dam, regardless of owner, that has a high (1) or significant (2) hazard potential or is/will be important to park management should be discussed in the General Management Plan and its associated environmental document in regard to is purpose and required care. Dams that are not essential to park management and operation should be properly disposed. Information should be requested from non‑NPS dam owners during the NPS planning and environmental evaluation process to determine the safety and operational significance of their structures on NPS floodplain management and the need for any emergency action plans. Refer to Appendix G for an example letter for coordinating with non-NPS dam project owners and/or regulators. The Corps will assist in providing information about non‑NPS dams and hydrologic and hydraulic analyses in determining the 100 and 500‑year floodplains. When possible, the floodplain and emergency action plan inundation mapping should be combined. Flood profiles should be presented with the mapping. A current list of these dams by region and hazard potential is also given in Appendix A.
C. Floodplain Management and Wetland Protection
The NPS floodplain/wetland protection guidance should be carefully reviewed with proper consideration as to the effects of dam safety and operation on floodplains in NPS administered areas. Any dam having a high (1) or significant (2) hazard potential that is located upstream, at, or downstream of a particular floodplain study reach under NPS investigation will be evaluated as part of the environmental assessment process and reported in the "Statement of Finding" as to its safety and operational effects on floodplain development. The Regional Dams Coordinator will provide the necessary evaluation. Many of the older high (1) or significant (2) hazard potential dams in or adjacent to park boundaries were not designed or maintained to safely operate during the 100 and 500‑year base floods which are used for park planning in floodplains. Consequently, because the probable failure of these older dams would produce significant flooding above the natural 100 or 500‑year floods, it is paramount that these types of structures receive periodic inspection and appropriate corrective action. For non‑NPS dams whose operational safety cannot be ascertained, conservative design and operational procedures in park administered areas should be utilized to compensate for this condition. Inhabitable facilities, utilities or transportation systems will not be built or operated in floodplains subject to the effects of dams in seriously deficient conditions, and there are no active and funded programs for corrective action.
D.
The protection of wetlands is interrelated to the U.S. Army Corps of Engineers Section 404 Permit Program for dredging (digging) or filling in or near any significant stream, river, lake, or harbor. This dredging or filling permit requirement is applicable for new dams or existing dams proposed for modification or disposal. Requirements are based upon volume of material and other considerations. Local U.S. Army Corps of Engineer Districts will provide advice on the applicability of the Section 404 Permit Program for dams and appurtenant works under NPS management.
CHAPTER FOUR
MANAGEMENT OF TECHNICAL ACTIVITIES - SITE INVESTIGATION
AND DESIGN FOR PROPOSED OR EXISTING DAMS
A. General
This section of the guideline outlines the site
investigation and design technical activities that Regional Directors,
Superintendents, and Manager,
B. Hydrology
1. Hazard Evaluation. Areas impacted by dam construction and existing dams should be examined for potential hazards to present and future developments in the event of major flooding by controlled flood discharges or flooding induced by dam failure or misoperation. This hazard evaluation is the basis for selection of the performance standards to be use in am design or in evaluation of existing dams. See Chapter 1, Section D, 3.
2. Flood Development. Hypothetical floods, generally of severe magnitude, should be developed for use in design or evaluation of major dam and reservoir features, including development of appropriate floods for the construction period.
3. Flood Selection for Design (or Evaluation). The selection
of the design flood should be based on an evaluation of the relative risks and
consequences of flooding, under both present and future conditions. Higher
risks may have to be accepted for some existing structures because of
irreconcilable conditions. Reference should be made to U.S. Army Corps of
Engineers Publication, ER 1110-2-106, National Program for Inspection of
Non-Federal Dams,
When flooding could cause significant hazards to life or major property damage, the flood selected for design should have virtually no chance of being exceeded. If lesser hazards are involved, .a smaller flood may be selected for design. Ideally, spillway operation should be evaluated in such a way that dam failure resulting from overtopping would not-significantly increase the hazard to loss of downstream life or property from that flooding condition which would exist just before overtopping failure.
To reduce hydrologic and hydraulic engineering costs, systematized computer programs like HEC-1 Dam Break by U.S. Army Corps of Engineers could be utilized effectively for many small National Park Service dams. This computer program will generate an inflow design flood, route the flood through and/or over the dam (including outflow from any defined hypothetical dam failure), and then route the flood wave to a downstream damage reach for evaluation, all in a single operation. This systematic method allows for a rapid optimization of spillway requirement to adequately protect existing and any anticipated downstream development.
4. Hydrologic Design of Reservoir. In addition to selection of a design flood, the hydrologic design of a new reservoir or the evaluation of an existing project involves consideration of discharge and storage capacities, reservoir regulation plans including constraints, land requirements, and wind/wave effects.
Reservoir regulation plans should be developed in the planning of projects so that realistic release rates will be used in routing the design flood. Regulation plans should include the construction period.
The reservoir regulation plans; water control management plan, and data. Information systems should be periodically reviewed for deficiencies and potential for misoperation during both severe flood events and normal conditions. Necessary corrections should be made as soon as practicable.
5. Downstream Effects. Safety design includes studies to ascertain areas that would be flooded during occurrence of the design flood and in the event of dam failure. The areas downstream from the project should be evaluated to determine the need for land acquisition, flood plain management, Flood Insurance Program or other methods to prevent major damage. Information should be developed and documented suitable for releasing to downstream interests regarding remaining risks of flooding.
6. Warning Systems. Safety design should include an emergency flood warning system and action plan that would effectively notify all concerned in ample time for appropriate action.
C. Earthquake Investigation and Design
1. Investigation Factors. The following factors should‑be considered in selection of design earthquakes.
a. Geologic and tectonic setting of the site area by analysis of the lithology, stratigraphy, structural geology, and tectonic history.
b. Historic earthquake record to include the size, location, and other seismological characteristics as available, and the relationship, if possible, with the tectonic setting of the area‑in which the earthquakes have occurred.
c. Influence of the properties of the surficial materials on the determination of the size of historical earthquakes.
d. Influence of faulting or other tectonic features on the estimate of the occurrence, size and location of possible future earthquakes.
2. Selection of Design Earthquakes. From the above factors, earthquakes should be selected that have sufficient potential of occurring to require consideration in the dam design. Earthquake description should include estimates to the extent practical of' the size, location, depth, focal mechanism, and frequency of occurrence.
3. Engineering Seismology. Determination should be made of the characteristics of ground motion that would be expected from the design earthquakes, to the extent possible, to include amplitude (displacement, velocity and acceleration), frequency content, and duration.
4. Need for Earthquake Analysis. The probable effects of earthquakes on the dam and its appurtenant structures should be evaluated to determine the need for inclusion of earthquake forces in the structures analyses. Evaluation includes consideration of factors such as the project stage, hazard and risk factors, the size of the dam and reservoir, the potential ground motion at the site, site geology, and type of structure. Where determination is made that no earthquake forces are required in analysis, the determination should be justified.
5. Seismic and Geologic Studies.
a. Earthquake Sources. The essential first step is determination of the design seismic events (usually the maximum credible earthquakes) and an estimate of the ground motion: at the site due to these events. From a study of the regional tectonics and seismicity, and both regional and local‑ geology, potential sources for seismic events are identified, and the maximum credible earthquake magnitudes postulated.
b. Design Events. A maximum credible earthquake (MCE) is defined herein as the hypothetical earthquake from a given source that could produce the severest vibratory ground motion at the dam. Time histories of the estimated rock motion (accelerograms) at the dam for the various seismic events are selected to characterize the severity of the strong motions by their peak accelerations, frequency content, and duration.
6. Design for Earthquake Forces.
a. Safety Concerns. All earthquake‑related safety concerns should be identified. Potential safety concerns include but should not be limited to dam foundation integrity stability, unacceptable stress levels, fault displacements; abutments stability; effects of dam overtopping; dam stability; susceptibility of embankment dams to embankment or foundation liquefaction, cracking or excessive deformation.
b. Analysis Method. Determination of appropriate earthquake analysis methods for evaluation of safety concerns may be, as appropriate, by qualitative evaluations, pseudostatic analysis, and dynamic analysis. The methods selected should be appropriate to the identified safety concerns in accordance with good engineering practice and with currently available technology.
c. Structural Adequacy. Structural adequacy assessments should be made of all safety‑related components and concerns identified. These assessments should incorporate all applicable data and analysis.
D. Geotechnics
1. General.
a. Site specifics. After a site is selected, a program for the geotechnical exploration, design, and analysis of that specific site is required. No checklist can be made which would cover all eventualities at all sites, or at any one site, and attempts to formulate such a list would be counterproductive to the intent to ensure dam safety. The best insurance for adequate geotechnical work is a well‑trained and experienced staff actively involved in field inspections throughout all phases of the development of the site.
b. Documentation. Because many evaluations are possible for a given set of geotechnical conditions, it is important that full documentation be made of the reasoning process involved in geotechnical decisions. General guidelines for documentation are given in Chapter Two, section F.
c. Management of Diverse Technical
Expertise. Geotechnical work encompasses the expertise of geologists,
geophysicists, and engineers‑all with diverse experience, training, and
technical terminology. The administrative and technical supervision of these
experts should be structured to optimize coordination and cooperation.
Management should encourage intellectual curiosity and an inquisitive approach
to all geotechnical work. Since the field of geotechniques is rapidly
expanding, Regional Directors and Manager,
2. Exploration and Identification of Geotechnical Problems.
The exploration program needs to be site specific, flexible, and executed so as
to obtain the maximum data from each part of the program. Regional Directors
and Manager,
4. Foundation Treatment.
a. General. The preparation of the foundation, including the abutment, is one of the most important phases of construction. The primary purposes of foundation treatment are to provide stability, obtain positive control of seepage, and minimize adverse deformation. The geology, foundation conditions, foundation treatment, and proposed structure should be considered together.
b. Stability. Surfaces should be prepared to provide a satisfactory contact between the foundation and the overlying structure by removal of unsuitable materials. Deficiencies in the foundation which are not removed should either be treated by modification of the structure or by appropriate foundation treatment tailored to handle the conditions encountered.
c. Positive Control of Seepage. Highly permeable foundations should be treated by such measures as cutting off the pervious material, grouting, increasing the seepage path by upstream blankets, or controlling the seepage with drainage systems. Where appropriate, surficial cavities should be traced, cleaned out, and backfilled with material satisfying the design requirements. When cavities exist at depth, measures should be taken to ensure against the migration of cavity material.
d. Control of Piping. Silts and fine sands in the foundation, which are susceptible to piping, should be removed if practical, cut off near the downstream limits of the dam, covered with impervious material, or provided with filtered drainage systems. If pipable material is used in the dam, the foundation surface treatment should prevent migration of dam material into the foundation.
e. Deformation. Foundations subject to differential settlement or foundations having highly compressible anomalies can cause stress concentrations or cracking in dams. The foundation excavation should be shaped to remove abrupt changes in elevation to preclude excessive differential settlement or stress concentrations. Low shear strength material in a foundation can cause shear failure. Excavation and replacement of low strength material is a positive method for treating a foundation that has either or both of these unfavorable conditions.
5. Instrumentation. Although a well conceived foundation instrumentation program serves to monitor the foundation and give an indication of distress, it cannot of itself certify the safety of the foundation. , The expertise of the engineer/geologist to analyze, design and prepare a foundation that will safely carry the loads and water pressure imposed by the dam and the reservoir is fundamental to the design adequacy of the foundation. The purposes of foundation instrumentation are fourfold: to (1) provide data to validate design assumptions; (2) provide information on the continuing behavior of the foundation; (3) observe the performance of critical known features; and (4) advance the state of the art of foundation engineering.
6. Inspection and Continuing Evaluation During Construction. Those responsible for the investigation and design of the foundation should make on‑site evaluations to confirm that actual conditions conform to those assumed in the design and to review documentation of site conditions.
7. Reevaluation at Existing Structures. Older dams under NPS jurisdiction may not have been designed to standards equal to current criteria. Also, a substantial portion of safety‑related dam incidents are associated with foundation problems which develop in a time‑dependent fashion after construction. For these reasons, systematic reevaluations of existing dams should be made for appropriate structures.
E. Hydraulic Appurtenances
1. General.
a. Protective Measures. All hydraulic appurtenances used for releasing water should be designed to preclude jeopardy to the damming provisions.
b. Blockage. Allowances for or preclusion of blockage of hydraulic facilities should be incorporated in the design.
c. Reliability. When operational failure of a gated passage would jeopardize the damming provisions, alternate capacity should be provided. When operation of a gated passage is essential to safety, reliable manpower, communications and accessibility should be assured.
d. Hydraulics and Hydrology. Hydraulics and hydrologic design considerations should be correlated with Chapter 4, B.
2. Design Flood Releases.
a. Spillway and Outlets. Gated spillways are the usual hydraulic appurtenances for control of all, or the major portion of, the design flood and major emergency releases. Outlets (sluiceways, conduits and tunnels) may be used alone or in conjunction with spillways to control flood discharges.
b. Selection of Type. Spillways and outlets should be selected to meet the site specific purposes of the project. For a drainage area with short concentration time combined with reservoir storage capacity that is small relative to the flood volume, especially for embankment dams, (1) the spillway should usually be uncontrolled, and (2) outlets should not normally be used for sole or part control of the design flood except in special cases where the outlet can be uncontrolled.
3. Other Water Releases. Other water release hydraulic appurtenances such as navigation facilities, locks, fish facilities, ice sluices, trash sluices, and water quality facilities should conform to the requirements of section E.1.
4. Reservoir Evacuation. Where practicable, reservoir release facilities ' should be provided to lower the pool to a safe level adequate to correct conditions that might threaten the integrity of the dam.
5. Control of Flows During Construction. The provisions of section E.1 also apply generally to the design of hydraulic appurtenances used during construction. The capacity of these appurtenances should be sufficient to satisfy the discharge requirements of the regulation plan for control of water during construction.
6. Design Criteria and Guidance. If existing design criteria and guidance from past projects and experience are used for design of the hydraulic appurtenances, their sufficiency should be documented.
F. Concrete Dams and Concrete Elements of Embankment Dams
1. Site Specific Design. Because all dam sites are unique, the type of dam and its appurtenances should be specifically matched to site conditions and project requirements. It is essential when reviewing the safety of‑existing dams to consider conditions which may have changed physically, new concepts resulting from new technology, and additional project information since construction, i.e., foundation deterioration, increased flood hydrographs, or larger design earthquakes.
2. Materials. Concrete for the structures requires competent investigation of material sources and adequacy of supply testing of materials properties in accordance with accepted standards, and proper proportioning of concrete mixes (including additives) for strength, durability, control of thermal properties, and economy.
3. Design of Structures. There are three components of a dam which must be considered for safety; the foundation, the dam, and its appurtenant structures.
a. Foundation. Proper design of a concrete dam requires information on the foundation geological conditions and material properties to assure its capabilities to support the loads of the dam and reservoir, in its natural state or as improved by foundation treatment.
b. Dam. Concrete dams should be designed to be safe against overturning and sliding without exceeding allowable stresses of the foundation and the concrete for all loading conditions imposed on the dam. The shape and/or curvature of a dam and its contact with the foundation are extremely important in providing stability and favorable stress conditions. Proper consideration should be given to ensure the dam's safety in the event of overtopping.
c. Appurtenances. Safety‑related appurtenances such as outlet works structures, spillways, penstocks, powerhouses, and navigation locks should be designed with the same degree of safety as the main dam. If the project has a powerhouse as an integral part of the dam, it should be designed for the same safety requirements as the dam.
4. Definition of Loads. The dam and appurtenances should be designed or evaluated for all static and dynamic loads to which they will be subjected.
5. Design Methods. The methods required for design of the several types of concrete dams and their appurtenances vary from simple to complex, depending on the type and size of the structure, the hazard potential, the site, the kinds of loading, and foundation conditions. The design process involves judgment and analytical expertise to select appropriate methods to analyze a structure whether it requires a simple or complex analysis and to determine design input that is representative of the range and variation of foundation and structural material properties. The selection of input parameters is just as important as the mechanics of the analysis used.
6. Design Evaluation. Technically qualified supervisory personnel should assure that structures are designed to meet the requirements for safety. This includes confirmation of design input parameters, design methods, and utilization of allowable factors of safety against overturning, sliding, and stressing appropriate to the probability of the loading conditions.
7. Instrumentation. Knowledge of the behavior of structures and their foundations may be given by studying the service action of the structures using observations on embedded and other internal instrumentation and external measurements.
G. Embankment Dams
Section F contains general dam considerations. The following additional considerations are applicable to embankment dams:
1. Site Specific Design. Embankment design should be developed for specific site conditions and based on adequate exploration and testing to determine all pertinent geologic and material factors with particular emphasis on shear strength and stability, permeability and control of seepage, and consolidation and settlement
2. Materials. Embankments can generally be designed to utilize locally available construction materials; investigation of materials characteristics is required and problem materials should be either discarded or protected by defensive design. There is often a need for importing special materials for slope protection, filters, and drainage systems. Any embankment zoning should consider the properties and quantities of available materials and the effect of their characteristics on the construction process.
3. Design Constructibility. Embankment designs should be constructible with regard to such items as location of borrow areas with respect to flooding, in situ moisture conditions, climatic effects on construction schedules, width of zoning, and needs for special material processing Design should include protection of critical features from overtopping by floods during construction.
4. Embankment Design. The safety of an embankment is dependent on its continued stability without excessive deformation under all conditions of environment and operation, and on control of seepage to preclude adverse effects on stability and prevent migration of soil materials. Design considerations given below are specific to embankment dams.
a. Seismic. Where earthquake design is necessary, consideration should be given to earthquake‑related concerns of soil liquefaction and cracking potential, stability and excessive deformation, abutment stability, overtopping effects, and required defensive measures.
b. Stability. Embankment stability should be analyzed for all pertinent static and dynamic loading conditions without exceeding allowable shearing stresses in the embankment or foundation.
c. Settlement and Cracking. The potential for transverse cracking of the embankment caused by differential settlement, tension zones, and possible hydraulic fracturing should be minimized by careful consideration of abutments, foundation and cutoff trenches, and their geometry and treatment.
d. Seepage. The design should attempt to prevent or minimize seepage through the embankment and its foundation and abutments; however, the designer should recognize that seepage usually occurs and that protective control measures must be provided. Filtering transition zones and foundation and abutment treatment to seal openings should be provided wherever necessary to preclude migration of soil materials into or out of all embankment element contacts both upstream and downstream. Filters, drainage blankets, and transitions should be of a quality and size to conservatively control and safely discharge seepage for all conditions for the life of the project. Particular attention should be given to contacts with foundation, abutments, embedded structures, and the end slope of closure sections to ensure adequate compaction and bonding to control seepage.
e. Zoning. Embankment zoning when used should ensure adequate stability for all pertinent conditions, and should control seepage through the embankment and provide filter action to prevent migration of material.
f. Erosion. Upstream and downstream slopes and foundation and abutment contacts should be protected against erosion from surface runoff, wave action, and impinging currents. Spillways and outlet works should be located and designed so that discharges do not erode the embankment or its foundation.
5. Instrumentation. Embankment design and prediction of embankment performance are based on an imprecise combination of theory and empirical procedure; consequently, performance during construction and operation should be monitored by a design system of external measurements and/or installed instrumentation.
6. Construction and Operational Follow‑up: Stability should be evaluated during and after construction using strength parameters from as‑placed materials and observations of pore pressure and seepage if and when condition, warrant. Designers should inspect and review performance of embankments during and after reservoir impoundment to detect and provide prompt remedial treatment for problems. While major emphasis is placed on initial impoundment the surveillance should continue for the life of the project
CHAPTER FIVE
MANAGEMENT OF TECHNICAL ACTIVITIES –
CONSTRUCTION OR REHABILITATION OF DAMS
A. Introduction
This section of the guideline outlines the construction
technical activities that Regional Directors, Superintendents, and Manager,
1. Construction Contracts. Construction contracts should be based on site conditions as interpreted at the time of contract award. All anticipated work on foundation cleanup, preparation, and treatment should be included as specified items of the work. Contract provisions should require the contractor to submit to the construction engineer advance notice of significant shift change to enable adequate inspection coverage of multi-shift operation.
2. Construction/Design Interface. Many aspects of construction directly overlap in design considerations. Reference is made below to numbered paragraphs in Chapter 4, Management of Technical Activities ‑ Site Investigation and Design, which concern such common interests:
a. Geotechnics
(1) General
(i)Site Specifics
(2) Exploration and Identification of Geotechnical Problems
(3) Geotechnical Design
(4) Foundation Treatment
(5) Instrumentation
(6) Inspection and Continuing Evaluation During Construction
b. Hydraulic Appurtenances
(1) Control of Flows During Construction
c. Concrete Dams and Concrete Elements of Embankment Dams
(1) Site Specific Design
(2) Materials
(3) Design of Structures
(i) Foundation
(4) Instrumentation
(5) Construction and Operational Follow‑up
d. Embankment Dams
(1) Site Specific Design
(2) Materials
(3) Design Constructibility
(4) Embankment Design
(i) Settlement and Cracking
(ii) Seepage
(6) Construction and Operational Follow‑up
B. Evaluation During Construction. Field personnel must be highly trained and experienced in the design principles and site conditions are to be understood and a safe structure is to be constructed.
When differing site conditions (different from those anticipated) are encountered construction supervisory forces must have authority to suspend any or all portion of the work affected until the design engineers, with assistance as needed, can evaluate the condition and determine if design modification is required.
Construction milestones should be identified when the design engineers will inspect the work and concur with the progress of construction.
C. Orientation of Construction Engineers and Field Inspectors. Construction engineers need to e aware of design philosophies and assumptions as to site conditions and function of project structures, and must understand the designers' intent concerning technical provisions in the specifications.
Construction specifications, supplemental reports, and conferences to orient field personnel to the particular site, the features of the dam, and the designers' intent for construction should, as applicable, include the following:
1. Design Related
a. Design concepts. An explanation should be given of philosophies and assumptions and the reasons for special requirements in the specifications to assure accomplishment of design intent.
b. Construction sequence. Identification and explanation of the dates to which construction progress must conform to satisfy project requirements, and the special sequences for construction activities that are required by design.
c. Instrumentation systems. Description should be given of the instrument types, their purpose, the procedures for installation of each instrument type, the method and time interval for reading each instrument, and the importance of prompt data transmission for analysis and feedback.
d. Care and diversion of water. Description of the design features included to prevent and/or control flooding and turbidity and accomplish diversion and closure of the dam. This should also contain the design requirement for controlling normal flows through the work area to assure that construction is always accomplished under dry conditions. Critical aspects of the construction schedule related to flood problems should be emphasized.
2. Foundation
a. Description. Discussion of the type of foundation conditions expected to exist, i.e., overburden, general rock description, formation weaknesses (such as joints, shears and faults), and acceptable foundation conditions.
b. Excavation. Discussion of the depth and nature of materials expected to be encountered, the controls for dewatering and blasting, identification of critical areas, quantity estimates, and an acceptable foundation.
c. Preparation. Review of the methods of rock foundation preparations such as: cleaning; the use of wire mesh, mortar, shotcrete, or cock bolts; grouting, and treatment of faults, shears and joints; as well as subsequent exploration to assure desired results. Review of methods of earth foundation preparation.
3. Materials
a. Materials from required excavation. Definition should be given of acceptable and unacceptable properties of materials, the usage and the processing required if used, and identification of waste area locations.
b. Other excavated materials. Identification of the location and amount of useable material, "based on current test data," available from all designated areas, including borrow pits. Review of the blasting methods that are expected to produce the desired rock quality and sizes. Discussion should be given of the expected amounts of waste and the areas where borderline material may be used in lieu of wasting, such as in berms or certain zones of the downstream shell of an earthfill dam.
c. Embankment. Description should be given of both acceptable and unacceptable material properties, placement, and compaction procedures for each zone. Review of required procedures for areas adjacent to abutment, around instruments, and at interfaces between zones and/or structures.
d. Concrete and concrete materials. Identification should be given of acceptable aggregate sources and review of mix designs, joint and surface treatment, finish requirements, form tolerances, and placement procedures. Cooling as well as hot and cold weather protection requirements should be defined.
4. Construction General
a. Field control. Discussion of the quality assurance procedures required to control all phases of construction. Acceptable placement standards should be established for concrete, earth and rock materials, and embankments.
b. Structural. Discussion should be given of structural steel installation, reinforcing steel placement, and anticipated problem areas and specified treatment for such areas.
c. Mechanical‑electrical. Description of equipment installation requirements, special procedures, performance tests, protective coatings, and protection devices such as ground fault indicators.
d. Environmental. Identification of those construction controls required to minimize environmental damage, comply with environmental regulations, and assure public involvement.
D. Construction Assurance
1. Construction Procedures. Criteria must assure that acceptable methods and procedures are specified and utilized to accomplish design requirements. At the time, the design and construction organizations must maintain the flexibility necessary to modify design, material requirements, and construction specifications as conditions dictate without altering the basic design intent.
2. Construction Materials Testing. A materials laboratory must be established at the field construction office that is adequately staffed and equipped to accomplish the on‑site testing requirements set forth in the engineering considerations and instructions to field inspection personnel.
3. Quality Assurance. It is mandatory that adequate construction quality assurance systems and procedures be established to assure safe dam construction. The quality assurance system must guarantee, by direct inspection and testing, that construction is accomplished in compliance with the contract plans and specifications. Daily inspector's reports, laboratory test data records, and photographs are the minimum mandatory methods of documentation. General guidelines for documentation are given in Chapter two, section F.
As part of the quality assurance program, the contractor should normally be required to submit various plans for approval not limited to, but including, the following:
Construction Schedule
Safety Program
Care and Diversion of Water (including pollution control)
Fire Protection
Plant layout (including haulroads)
Environmental measures
Equipment Inventory
Dewatering Foundations and Borrow Areas
Excavation Sequence of Foundations and Borrow Areas
Drilling and Blasting Procedures
Concrete Placement
Restoration of Construction Area
CHAPTER SIX
MANAGEMENT OF TECHNICAL ACTIVITIES ‑ OPERATION AND MAINTENANCE
FOR PROPOSED OR EXISTING DAMS AND APPURTENANT WORKS
A. General
This section of the guideline outlines the management
responsibilities for operation and maintenance, periodic inspection program,
and emergency action planning that Regional Directors, Superintendents, and the
Manager,
B. Operation and Maintenance
1. General. All features of NPS dams and appurtenant works should receive maintenance or operation as recommended from inspection reports‑annual informal, intermediate, or formal. These reports should be prepared by trained and experienced engineers familiar with the maintenance and operation of small dams.
Unless it is an extenuating condition, extensive maintenance or testing of dam equipment should only be performed because of recommendations in an inspection report. These recommendations should be performed by personnel familiar with the maintenance and operation of small dams.
Serious maintenance, operational, or safety problems that are discovered during maintenance or operation work should be reported immediately to the Park Superintendent and personnel responsible for inspections as to the proper action to be taken. Maintenance and operations should be scheduled far enough in advance to take advantage of good weather periods, terrain conditions, and manpower and equipment availability to assure safe and economic work.
A log of maintenance and any required operation will be maintained and filed with the previous Annual Informal Inspection. The log will list the crew supervisor's name, date, activity accomplished or attempted, if incomplete, and total cost (overhead, materials, and labor, if readily available). Information about failures (partial or total), misoperation, accidents, floodings, or instrumentation readings should also be kept in the log.
2. Operating Procedures. Operations consist of the periodic testing of gates or any other type equipment to assure reliable use, establishing instrumentation as required, or reviewing any operating manuals or emergency action plans for completeness and accuracy. When appropriate, written operating instructions should be prepared for the dam and its associated structures and equipment. The instructions should cover the functions of the dam and reservoir and describe procedures to follow during flood conditions to ensure dam safety.
If appropriate for more critical NPS dams, reservoir operating rule curves should be available for each normal mode of operation and for emergency conditions.
An auxiliary power system, such as a gasoline, crane or diesel‑operated generator, is essential if the outlet and spillway gates and other dam facilities are electrically operated.
All spillway and outlet gates should be tested on a regular schedule. The tests should include use of both the primary and the auxiliary power systems.
Project security is a matter of concern at important dams and appurtenant works. This includes preventing structural damage by vandals or saboteurs and unauthorized operation of outlet or spillway gates. In some cases restricting public access is essential and security patrols may be necessary.
Occupational and public type safety is of paramount importance at certain dams and reservoirs. Specifically, this type safety at the dam, appurtenant works, on and around reservoirs, and below the dam should be considered, particularly in recreational areas. Safety measures should include identification of high watermarks to indicate past or probable reservoir levels and streamflows, posting of safety instructions at highly visible and key locations, and providing audible safety warnings upstream of and below outlets as appropriate.
When applicable, occupational and public safety should be evaluated by personnel from the Safety Division. They should accompany the engineering team for the dam inspection to evaluate hazard potentials to personnel and visitors such as heights, depths, dangerous flows, mechanical and electrical equipment, and supplies. Their recommendations should be referenced in the inspection report.
Communication should be maintained among affected governmental bodies and with the public to enhance the safety aspects of the operation of the dam, if warranted. Communication alternatives include written communications, radio, telephone, television, and newspapers.
In the following sections, outlets or outlet gates refer to gates or valves on any outlets such as sluices, conduits or tunnels, pumps, generating units, and infrequently operated plant intake and discharge gates. If the project has a navigation lock, emergency closure and other infrequently operated equipment should also be included.
3. Maintenance. Maintenance is normally the preserving of structures, appurtenant works and equipment in intended operating condition by the proper control of vegetation, removal of debris and trash, equipment repair, and minor structural repair. It is not the repair of structural deterioration to restore original condition, improvements for dam safety, enlarging reservoir capacity, increased spillway and outlet capacity, or the replacement of equipment. Such major rehabilitation of construction should be carried out with the assistance of NPS, Denver Service Center (DSC), and Bureau of Reclamation (USBR).
The following list of typical maintenance work is provided:
‑harmful vegetation, debris, and trash should be removed from the dam, appurtenant works, immediate upstream and downstream areas, and access roads to assure structural integrity, reliable operation, visual observation, and accessibility. Undesirable material should be removed and properly disposed of so as to prevent problems during high water, winds, fire, or vandalism; ‑vegetation maintenance for erosion control and esthetics;
‑large vegetation which has become an integral part of the dam or appurtenant works needs to be carefully evaluated to determine if removal is warranted;
‑lubrication of equipment;
‑painting;
‑maintaining internal drainage systems; ‑minor mechanical and structural repairs;
‑correcting minor deterioration of concrete and embankment surfaces;
‑taking measurements from instrumentation;
‑placement of signs warning of heights/depths, dangerous flows, and equipment, when applicable;
‑placement of barriers to prevent unauthorized access;
‑all maintenance work is to be performed in a safe manner. The use of personal‑protective and safety devices is required when so determined by the supervisor or the Superintendent in consultation with the area safety officer or Regional Safety Manager.
C. Periodic Inspection Program
1. General. The purpose of the NPS periodic inspection program is to verify throughout the operating life of the project the structural integrity of the dam and appurtenant structures and assure the protection of human life and property.
All NPS dams will receive some level of evaluation based on current technical guidelines and criteria prior to any significant repairs, rehabilitation, or construction. New dams added to the inspection program should be planned, designed, and constructed in accordance with current technical criteria. Improvements in dam technology require that dams and appurtenant structures be reassessed to assure dam safety for more stringent design and materials criteria.
Regional Directors and Superintendents are responsible for assuring that the existing dams for which they are responsible are periodically inspected, and that new dams are inspected initially upon completion of construction and periodically thereafter.
2. Types and Frequencies of Inspections. The inspection types and intervals herein recommended are for guidance in developing inspection programs for all dams under NPS management. This guideline does not preclude other inspections or more frequent inspections if deemed necessary, depending on project history and importance of the facility.
Inspection personnel should be selected carefully, have qualifications commensurate with their assigned levels of responsibility, and receive training in the inspection procedures. Qualifications and training required for inspection personnel may vary with the complexity of the facility and with the level of the inspection.
a. Annual Informal Inspection. All dams and appurtenant works under NPS management will receive this type of inspection. Inspection is performed annually by NPS or contract personnel to evaluate hazard potential classification, maintenance, structural and mechanical integrity for operational reliability, visitor safety on or around the dam and updating or completing the NPS inventory of dams data base management system. Immediately after any unusual event such as large floods, earthquakes, suspected sabotage, vandalism, or structural or operational failure, an inspection will be performed by NPS personnel. Particular attention should be given to detecting evidence of (or changes in) leakage, erosion,‑sinkholes, boils, seepage, slope instability, undue settlement, displacement, tilting, cracking, deterioration, and improper function of drains and relief wells.
The checklist given in Appendix C of Safety Evaluation of Existing Dams, USBR, 1980, or equivalent form, should be used to assure thoroughness. Previous inspection reports should be reviewed to see what earlier corrective action recommendations were or were not performed. ‑A brief explanation should be written as to why previously recommended maintenance or operations were not performed.
The annual informal inspection report package should consist of the following items:
‑Map;
‑Any photographs or drawings;
‑Completed checklist of dam and appurtenant features
‑Very brief memorandum with recommended corrective action for use by maintenance and operations personnel;
‑Operational and maintenance condition code specified;
‑Updated inventory listings or forms;
The following codes should be used to describe the operational and maintenance condition of structures and related equipment, and reported into the NPS Inventory:
1‑Will fulfill intended purpose and required annual maintenance or operations are performed;
2‑Will fulfill intended purpose but required maintenance, operations, or minor repairs is needed;
3‑May not fulfill intended purpose and maintenance or major repair is needed;
4‑Will not fulfill intended purpose and major repair or rehabilitation is needed.
Reports should receive review and be given signature approval, and the following distribution made:
1‑Director (Park Facility Management Division)
1‑Regional Director (Park Facility Management Division)
1‑Park Superintendent
b. Intermediate Inspections. This type inspection is required of dams under NPS management that have either a high (1) or significant (2) hazard potential. For low hazard potential dams, intermediate inspections are not required. Intermediate inspections should include a thorough field inspection of the dam and appurtenant structures, and a review of the records of inspections made at, and following, the last formal inspection.
If unusual conditions are observed that‑are outside the expertise of these inspectors, arrangements should be made for inspections to be conducted by specialists.
(1) Frequency of intermediate inspections. Intermediate inspections, should be performed every three years where there is a high probability that dam failure or misoperation could result in loss of life or significant property damage.
(2) Qualifications of personnel for intermediate inspections. Intermediate inspections should be performed by technically qualified engineers, experienced in the operation and maintenance of dams and trained to recognize abnormal conditions. The inspectors should have access to and be familiar with all pertinent histories for the dam, and should be directly responsible for and intimately familiar with the operating characteristics of the dam. The dam tender or operator should be a participant in these inspections.
(3) Currently this type of inspection will be performed by USBR personnel as deemed necessary.
c. Formal and Special Inspections. This type inspection is required of dams under NPS management that have either a high (1) or significant hazard (2) potential. Formal inspections will not be performed for dams under NPS jurisdiction and classified as low hazard potential. A formal inspection is required periodically to verify the safety and integrity of the dam and appurtenant structures. Formal inspections should include a review to determine if the structures meet current accepted design criteria and practices. The inspection should include a review of all pertinent documents including instrumentation, operation, and maintenance and, to the degree necessary, documentation of investigation, design, and construction. In making the detailed inspection of the dam, appurtenant structures and equipment, diving inspections of‑underwater structures affecting the integrity of the dam should be included. All formal inspections should be conducted by a team of highly trained specialists. To assure that a dam and its appurtenant facilities are thoroughly inspected, checklists should be prepared to cover the condition of structural, electrical, and mechanical features. This inspection should also verify that operating instructions are available and understood, instrumentation is adequate and data assessed to assure structures are performing as designed, and there are emergency provisions for access to and communication with all project operating facilities.
(1) Frequency of formal inspections. Formal inspections should be made periodically at intervals not to exceed 6 years. Depending on past experience or the project history, some dams may require more frequent formal inspections.
(2) Frequency of special inspections. Special inspections should be performed immediately after the dam has passed unusually large floods and after the occurrence of significant earthquakes, sabotage, or other unusual events reported by operating personnel.
(3) Qualifications of personnel for formal and special inspections Formal and special inspections should be conducted under the direction of licensed professional engineers experienced in the investigation, design, construction, and operation of dams. The inspection team should be chosen on a site‑specific basis considering the nature and type of the dam. The inspection team should be comprised of individuals having appropriate specialized knowledge in structural, mechanical, electrical, hydraulic, and embankment design; geology; concrete materials; and construction procedures. They must be capable of interpreting structural performance and relating conditions found to current criteria and safety aspects. It is imperative that the inspection team adequately prepare for the inspections by reviewing and discussing all documents relative to the safety of the dam.
(4) The Bureau of Reclamation (USBR) is the preferred organization to perform both formal and intermediate inspections and any special studies or emergency services for NPS, particularly on either the high or significant hazard potential dams. However, NPS managers may, at their discretion, utilize other qualified agencies or contractor services when USBR would not be able to respond in sufficient time. NPS personnel will accompany the team and act as observers during this inspection.
(5) Data Books will be prepared by USBR or other inspecting organization for all NPS high (1) or significant (2) hazard potential dams which are scheduled for formal inspection. Appendix E is a checklist of the types of existing data which will be valuable for evaluating the safety, maintenance, and operation of NPS dams. Existing information for these Data Books should be prepared and distributed by Regional Directors or Superintendents to USBR or other inspecting organization two (2) months prior to the actual on‑site examination.
|
S‑Satisfactory |
No existing or potential dam safety deficiencies are recognized. All essential elements can be expected to function under all conditions, including such events as the maximum probable flood (MPF) or maximum creditable earthquake (MCE), which have only a remote chance of occurring; |
|
F‑Fair |
No existing or potential dam safety deficiencies are recognized for normal operating conditions. All essential elements can be expected to function under normal operating conditions. Remotely occurring events of magnitudes approaching a MPF or MCE will likely cause a dam safety deficiency; |
|
P‑Poor |
A potential dam safety deficiency for normal operating conditions is recognized. Major damage has occurred at one or more of the essential elements or may be anticipated to occur during normal operating conditions. Immediate corrective actions to resolve the deficiency(s) are recommended and reservoir or other project restrictions may be necessary until problem is resolved; |
|
U‑Unsatisfactory |
A dam safety deficiency is recognized for normal operating conditions. One or more essential elements will not operate adequately under normal operating conditions. Problem resolution requires immediate action. |
In association with any classification term, maintenance work to correct an existing condition of one or more essential elements, or installation of additional equipment to enhance dam safety and/or to monitor performance, may be advised. It is expected that adequate maintenance can prevent many dam safety deficiencies from occurring.
3. Instrumentation. Instrumentation or performance observation devices are used to supplement visual inspections in evaluating the performance and safety of dams. Careful examination of instrumentation data on a continuing basis may reveal a possible critical condition. Conversely, instrumentation may be a means of assuring that an observed condition is not serious and does not require immediate remedial measures.
b. Observation of Monitoring Devices. The instrumentation data should be collected by personnel trained specifically for the purpose, including training to recognize and immediately report to those 'responsible for inspections any anomalies in the readings or measurements. Performance observation data should be properly established for record purposes. The frequency of instrument readings should be established at the time the instrumentation system is designed in order to give a timely warning of possible adverse conditions.
c. Data Analysis. It is essential that instrumentation data be processed, reviewed and assessed in a timely manner by a specialist familiar with the design, construction, and operation of the project. Operation manuals and design information should be referred to in the evaluation of possible adverse threats.
4. Correction of Deficiencies. The inspection program could reveal those deficiencies or potential deficiencies which, if uncorrected, could eventually lead to failure or misoperation of the dam. Deficiencies may vary from emergency type items where immediate action is required to non-emergency type items which must be corrected in a timely manner but do not present an immediate danger to the safety of the structure. In all cases, corrective action should be made under the supervision of qualified personnel. Emergency action plans to be implemented when failure has already occurred or is imminent are discussed in Emergency Action Planning.
a. High Priority Corrective Action. High priority corrective action is required for deficiencies which could result in failure of the dam within a short period of time. The Director will be notified immediately by the appropriate Regional Director of any dams (NPS or non‑NPS) that are in this condition, and what action is being taken to remove the threat to park safety or operations.
b. Non-emergency Corrective Action. Non-emergency corrective action is action taken when there is no immediate threat to the safety or operation of the dam, or any threat to life or property downstream. The Director will be notified immediately by the Regional Director of any dams (NPS and non‑NPS) that are in this condition. The corrective action should be scheduled in advance of the fiscal year in which the work is to be done to allow time for planning, funding through the normal budgeting process, and arranging for special reservoir operations when required. Some of these deficiencies may be corrected through the regular operation and maintenance program discussed in operations and maintenance.
c. Follow‑up Action. Periodic inspection reports should continue to list identified deficiencies along with any newly discovered deficiencies and show the status of corrective action., Appropriate inspection personnel should make frequent field examinations, as long as the problem exists, to see that all corrective measures are being completed. When deficiencies are not corrected in a reasonable length of time, an investigation should be made to determine the reason for delay, and the Director should be notified of the findings.
5. Documentation. Proper documentation of the dam's current and past performance is necessary to assess the adequacy of operation, maintenance, surveillance, and proposed corrective actions. A complete record or history of the investigation, design, construction, operation, maintenance, surveillance, periodic inspections, modifications, repair, and remedial work should be established and maintained so that relevant data relating to the dam is preserved and readily available for reference. This documentation should commence with the initial site investigation for the dam and continue through the life of the structure. This information will be collected by NPS personnel and delivered to the USBR to develop Data Books on high (1) and significant (2) hazard potential dams. See Chapter Six, section C.2. The data base management system for NPS dams will be maintained to keep current all data elements.
a. Instrumentation. All instrumentation observation data and evaluation thereof should be properly tabulated and documented for record purposes.
b. Inspections. All inspection observations, especially as related to the safety of the dam, should be documented. The extent and nature of inspection reports required for the annual informal, intermediate formal, and special inspections, will vary in proportion to the intensity of the inspection and the nature of the findings. Informal inspection reports may range from memoranda to brief reports. Intermediate inspection reports may vary from memoranda or trip reports to more formal reports containing substantial records, detail, and recommendations. Formal and special inspections require complete, formal technical reports of all findings, corrective actions and recommendations for permanent record and reference purposes in order to form a basis for major remedial work when required. All reports should be in a self‑explanatory form that permits their retention as permanent records and should carefully document times of inspections, inspection personnel, and findings of the inspection.
c. Correction of Deficiencies. All deficiencies corrected as a result of the recommendations contained in periodic inspection reports should be fully documented in report form and made a part of the permanent project record. Alterations made to the facility as a result of changes in criteria to meet current practices or changes in dam technology should be fully documented, including as-constructed drawings. Promptly perform corrective action on deficient dams. Dams listed as SERIOUSLY DEFICIENT should be corrected immediately. A dam is SERIOUSLY DEFICIENT if:
1 An official inspection report classifies the dam safety condition as:
a POOR—this classification is applied when major damage has occurred, or may be anticipated to occur, at one or more of the essential elements during normal operating conditions. Immediate corrective actions to resolve the deficiency(s) are recommended and reservoir or other restrictions may be necessary until problems are resolved; or
b UNSATISFACTORY—this classification is applied when one or more essential elements will not operate adequately under normal conditions. Problem resolution requires immediate corrective action; and/or
2 If the maintenance condition is rated:
a “3”, which indicates it may not fulfill intended purpose and maintenance or major repair is needed) or;
b “4”, which indicates it will not fulfill intended purpose and major repair or rehabilitation is needed.
6. NPS Observer Status at non‑NPS Dams. Refer to Appendix G for an example letter for coordinating with non-NPS dam project owners and/or regulators.
a. General. Dams that NPS has no jurisdiction over, but are located immediately adjacent to or within park boundaries and affect safety or operations, will be carefully monitored. Regional Directors, Superintendents, and Manager, DSC, will report and maintain information about these non‑NPS dams in our inventory data base system. Regional Directors should request the presence of NPS observers during the inspection of non‑NPS dams located within or immediately adjacent to park boundaries and that are in the high (1) or significant (2) hazard potential classification. Such coordination will assure NPS awareness of their condition.
b.
‑For non-NPS dams or appurtenant works may have been assessed as "Unsafe," if deficiencies are assessed to be of such a nature that, if not corrected, they could result in the failure or misoperation of the project with subsequent loss of life and/or substantial property damage. This classification is analogous to the National Park Service and Bureau of Reclamation safety of dams condition classification of Poor (Chapter 6, section C, 2, c, (6)).
‑If the probable failure of an "Unsafe" dam or appurtenant works is judged to be an imminent threat to life or substantial property and immediate action is required to reduce or eliminate the deficiencies, the "Unsafe" condition of the dam should be considered an "emergency." . This classification is analogous to the National Park Service and Bureau of Reclamation safety of dams condition classification of Unsatisfactory (Chapter 6, section C, 2, c, (6)). If the probable failure is judged not to be imminent, the "Unsafe" condition should be considered a "non‑emergency."
D. Emergency Action Planning
1. General. It is intended that this guideline will minimize the risk of future dam failures. Nevertheless, it is recognized that despite the adequacy of this guideline and its implementation, the possibility of dam failures still exists. Even though the probability of such failures is small, preplanning is required to identify conditions which could lead to failure, in order to initiate emergency measures to prevent such failures as a first priority, and, if this is not possible, to minimize the extent and effects of such failure. This guideline provides operating and mobilization procedures to be followed upon indication of an impending or possible dam failure or a major flood. Project information and inspection results will be used to keep the NPS inventory data base system current.
Emergency Action Plans (EAP) are required for all high (1) or significant' (2) hazard potential dams under Federal regulation or jurisdiction: The purpose of an EAP is to provide early warning and evacuation in the event of either a possible or actual dam failure or misoperation. An example EAP is provided in Appendix F for use by the parks. Superintendents should designate an EAP Coordinator, along with other individuals as given in Appendix F, at appropriate parks, with either NPS or non‑NPS dams within the specified hazard potential category (see inventory in Appendix A). EAP coordinators should initiate EAP's for appropriate NPS dams or coordinate with non‑NPS dams owners in the implementation of their EAP within park boundaries. Refer to Appendix G for an example letter for coordinating with non-NPS dam project owners and/or regulators.
Pertinent information about EAP's should be recorded into the NP$ Inventory of Dams. Since coordination is needed with state and local officials in implementing EAP's, a list of state dam safety officers has been, provided in Appendix G.
2. Coordination with non‑NPS Dam Owners. In those regions where high or significant hazard potential non‑NPS dams exist within or immediately adjacent to park boundaries, Superintendents will request from those owners coordination in the preparation and implementation of any Emergency Action Plans as appropriate for park areas.
3. Evaluation of Emergency Potential. Prior to development of an emergency action plan, consideration must be given to the extent of land areas, and types of development within the areas, that would be inundated as a .result of dam failure or flood, and the time available for emergency response.
a. Determination of Mode of Dam Failure. There are many potential causes and modes of dam failure, depending upon the type of structure and its foundation characteristics. Similarly, there are degrees of "failure" and, often, progressive stages of failure. Many dam failures can be prevented from reaching a final catastrophic stage by recognition of early indicators or precursor conditions, and by prompt, effective emergency actions. While emergency planning should emphasize preventive actions, recognition must be given to the catastrophic condition, and hazard potential should be evaluated in that light. Analysis should be made to determine the most likely mode of dam failure under the most adverse condition and the resulting peak water outflow following the failure. Where there is a series of dams on the stream, analyses should include consideration of the potential for progressive "domino" failure of the dams.
b. Inundation Maps. To evaluate the effects of dam failure, maps should be prepared delineating the area which would be inundated in the event of failure. Land uses and significant development or improvements within the area of inundation should be indicated. The maps should be equivalent to or more detailed than the United States Geological Survey (USGS) quadrangle maps, 7‑1/2 minute series, or of sufficient scale and detail to identify clearly the area that should be evacuated if there is evident danger of failure of the dams. Since detailed inundation maps may not be readily available or easily used at a disaster area, a concise and clear word description should also be prepared for easy word‑of‑mouth communication‑' The word description would tell potential evacuees how high they should elevate themselves above the river or by horizontal distance to an area known to be safe from inundation. Copies of the maps should be distributed to local government officials for use in the development of an evacuation plan.
c. Classification of Inundation Areas. To assist in the evaluation of hazard potential, areas delineated on inundation maps should be classified in accordance with the degree of occupancy and hazard potential. The potential for loss of life is affected by many factors, including, but not limited to, the capacity and number of exit roads to higher ground and available transportation.
d. Time Available for Response. Analyses should be made to evaluate the structural, foundation, and other characteristics of the dam and determine those conditions which could be expected to result in slow, rapid or practically instantaneous dam failure.
a. Development of Emergency Action Plan. An emergency action plan should be developed for each dam that constitutes a hazard to life or property, incorporating preplanned emergency measures to be taken prior to and following assumed dam failure. The plan should be coordinated with local governmental and other authorities involved in public safety and approved by the Regional Director for NPS dams. To the extent possible, the emergency action plan should define emergency situations that require immediate notification of local officials. The emergency action plan should include notification plans, which are discussed below in section b. A procedure should be established for review and revision, as necessary, of the emergency action plan, including notification plans and evacuation plans, at least once every year.
b. Notification Plans. Plans for notification of key personnel and the public are an integral part of the emergency action plan and should be prepared for slowly developing, rapidly developing, and instantaneous dam failure conditions. Notification plans should include a list of names and position titles, addresses, office and home telephone numbers, and radio communication frequencies and call signals, if available, for Regional Director, Superintendents, and Managers, or non‑NPS dam owner personnel, public officials, and other personnel and alternates who should be notified as soon as emergency situations develop.. A procedure should be developed to keep the list current.
Each type of notification plan should contain the order in which key agency or owner supervisory personnel or alternates should be notified. At least one‑key supervisory level or job position should be designated to be manned, or the responsible person should be immediately available by telephone or radio 24 hours a day. A copy of each notification plan must be posted in a prominent place at the project site near a telephone and/or radio transmitter.
Where dams located upstream from the dam for which the plan is being prepared could be operated to reduce inflow or where the operation of downstream dams would be affected by failure of the dam, operators of those dams should be kept informed of the current and expected conditions of the dam as the information becomes available.
Civil defense officials having jurisdiction over all or part of the area subject to inundation should receive early notification. Local law enforcement officials and, when possible, local government officials and public safety officials should receive early notification.
When it is determined that a dam may be in danger of failing, the public officials responsible for the decision to implement the evacuation plan should be kept informed of the developing emergency conditions.
The news media, including radio, television, and newspapers, should be utilized to the extent available and appropriate. Notification plans should define emergency situations for which each medium will be utilized and should include an example of a news release that would be the most effective for each possible emergency.
Notification of recreation users is frequently difficult because the individuals are often alone and away from any means of ready communication. Consideration should be given to the use of standard emergency warning devices, such as sirens, at the dam site. Consideration should be given to the use of helicopters with bullhorns for areas further downstream. Vehicles equipped with public address systems and helicopters with bullhorns are capable of covering large areas effectively.
c. Evacuation Plans. Evacuation plans should be prepared and implemented by the local jurisdiction controlling inundation areas. This would normally not be the dam agency or owner. Evacuation plans should conform to local needs and vary in complexity in accordance with the type and degree of occupancy of the potentially affected area. The plans may include delineation of area to be evacuated; routes to be used; traffic control measures; shelter; methods of providing emergency transportation; special procedures for the evacuation and care of people from institutions such as hospitals, nursing homes, and prisons; procedures for securing the perimeter and for interior security of the area; procedures for the lifting of the evacuation order and reentry to the area; and details indicating which organizations are responsible for specific functions and for furnishing the materials, equipment, and personnel resources required.
The assistance of local civil defense personnel, if available, should be requested in preparation of the evacuation plan. State and local law enforcement agencies usually will be responsible for the execution of much of the plan and should be represented in the planning effort. State and local laws and ordinances may require that other State, county, and local government agencies have a role in the preparation, review, approval, or execution of the plan. Before finalization, a copy of the plan should be furnished to the dam agency or owner for information and comment.
e. Locating Local Repair Forces. Arrangements should be made with, and a current list maintained of, local entities, including contractors, and Federal, State and local construction departments, for possible emergency use of equipment and labor.
f. Training Operating Personnel. Technically qualified project personnel should be trained in problem detection, evaluation, and appropriate remedial (emergency and non-emergency) measures.
g. Increasing Inspection Frequency. Frequency of appropriate surveillance activities should be increased when the reservoir level exceeds, a predetermined elevation. Piezometers, water level gages, and other instruments should be read frequently and on schedule. The project structures should be inspected as often as necessary to monitor conditions related to known problems and to detect indications of change or new problems that could arise. Hourly or continuous surveillance may be mandated in some instances. Any change in conditions should be reported promptly to the supervisor for further evaluation.
The supervisor should issue additional instructions, as necessary and alert repair crews and contractors for necessary repair work if developing conditions indicate that emergency repairs or other remedial measures may be required.
5. Actions Upon Discovery of a Potentially Unsafe (Seriously Deficient) Condition. Action to be taken will depend on the nature of the problem and the time estimated to be available for remedial or mitigating measures. As time permits, one or more of the following actions will be required.
a. Notification of Supervisory Personnel. This is essential, if time permits, since development of failure could vary in some or many respects from previous forecasts or assumptions, and advice may be needed.
b. Initiation of Predetermined Remedial Action. It is imperative that at least one technically qualified individual, previously trained in problem detection, evaluation, and remedial action, be at the project or on call at all‑times. Depending on the nature and seriousness of the problem and the time available, emergency actions can be limited, such as lowering the reservoir and holding water in upstream reservoirs. Other actions to be taken include notifying appropriate highway and traffic control officials promptly of any rim slides or other reservoir embankment failures which may endanger public highways.
APPENDIX A
NPS NATIONAL INVENTORY OF DAMS ON-LINE DATABASE ACCESS
Access to database is only available to personnel listed in the NPS email directory
The URL is: http://pfmd2.nps.gov/PRP/Dams/dams/index.cfm



|
|
Been Here Before? |
To Request an Account |
Forgotten your password? |
||||
|
|
|||||||
|
|
If you have
previously registered, enter your user name and password
|
1. Register your name |
If you have
previously registered |
||||
APPENDIX B
RECOMMENDED REFERENCES FOR MAINTENANCE,
OPERATION, AND SAFETY OF DAMS
American Society of Civil Engineers. Proceedings,
Engineering Foundation Conference, "Inspection, Maintenance, and
Rehabilitation of Old Dams,"
American Society of Civil Engineers. Proceedings,
Engineering Foundation Conference, "Safety of Small Dams,"
NOTE: ASCE publications may be obtained by contacting:
American Society of Civil Engineers
Attention: Publications
[New address needed]
Golze, Alfred R. (ed.). Handbook of Dam Engineering. Van Nostrand Reinhold., 1977.
NOTE: Reinhold publication may be obtained by contacting:
Van Nostrand Reinhold Co.
7625 Empire Drive
Telephone: 606‑525‑6600
Hanna, Thomas H. Foundation Instrumentation. Trans Tech Publications, 1973.
NOTE: Trans Tech publication may be obtained by contacting:
Trans Tech Publications
16 Bearskin Neck
Telephone: 617‑546‑6426
NOTE: Soil Conservation Service publications may be obtained by request from SCS field offices or by contacting:
Records and Communications Branch
Administration Services Division
Soil Conservation Service
Telephone: 202‑447‑3907
NOTE: Army publications may be obtained by contacting:
Office of the Chief of Engineers Publications Depot
Telephone: 202‑272‑7772
NOTE: Reclamation publications may be obtained by contacting:
Bureau of Reclamation
Attention: Publications, Code 922
Telephone: 303‑234‑3000
APPENDIX C
LIST OF NATIONAL
AND REGIONAL COORDINATORS AND CONTACTS
FOR THE NATIONAL
PARK SERVICE (NPS) MAINTENANCE, OPERATION, AND SAFETY OF DAMS
(MOSD) PROGRAM
FOR ALL DAMS AND
IMPOUNDMENTS AFFECTING THE NATIONAL PARK SYTEM
NATIONAL PARK SERVICE
NATIONWIDE 24-HOUR COMMUNICATIONS
Name Mailing
Address Telephones
(O) Office (H) Home
Dispatch Office
(They have
24-hour emergency numbers
for all National
Park System parks and offices)
BUREAU OF RECLAMATION CONTACTS
Coordinator for Overall NPS Assistance Bureau
of Reclamation
Civil Engineer, Betty Dinneen 1/
Alternate: Sue Thompson 2/ Attention:
Client and Support Scvs, code 8010 (O) 303-445-2610 2/ *
P.O.
Box 25007 (fax)
303-445-6356
Bldg.
67,
Dam Safety Program Dam Safety Office,
code D-1440 (O)
303-445-2765 1/ *
Chief, Bruce Muller 1/
(H) 303-978-9534 1/
Alternate: Civil Engineer, Rob Rocklin 2/ (O)
303-445-2770 2/
fax 303-445-6463
Coordinator for Examinations, Civil Engineer,
Inspections and
Emergency Mgmt. Group (O)
303-445-2755 1/ *
Chris Danley 1/ code
D-8470 (O)
303-445-2742 2/ *
Alternate: Civil Engineer, Chris Veesaert 2/ fax
303-445-6381
* Work hours
vary; however, one of these individuals will be available from
NATIONAL PARK SERVICE
COORDINATORS
AND CONTACTS
Civil Engineer, Charles Karpowicz 1/ National Park
Service (O)
202-513-7022 1/
Alternate: Mark Hartsoe 2/ Park
Facility Management (O)
202-513-7001 1/
Division, Org. Code 2420 (H)
703-493-8050 1/
Maintenance,
Operation, Safety of Dams O)
202-513-7025 2/
Program
1201
I (Eye) Street, N.W., 10th
Floor, space 41
Civil Engineer, Bill Heubner 1/
Alternate: Facility Manager, Tim Hudson 2/
Planning,
Design and
Maintenance
Division
LIST OF NATIONAL
AND REGIONAL COORDINATORS AND CONTACTS
FOR THE NATIONAL
PARK SERVICE (NPS) MAINTENANCE, OPERATION, AND SAFETY OF DAMS
(MOSD) PROGRAM
FOR ALL DAMS AND
IMPOUNDMENTS AFFECTING THE NATIONAL PARK SYTEM
NATIONAL PARK SERVICE
COORDINATORS
AND CONTACTS, continued
Name Mailing
Address Telephones
(O)
Office (H) Home
Chief Ranger, Robert Gray 1/ National
Park Service (0)
304-535-6171 1/
Alternate: Park Manager,
Park
Office (O)
304-535-6278 2/
C/O
Shipping Address: High Street, Civil War Story Bldg.,
3rd Floor,
Environmental Engineer: Phil Ayers 1/ Intermountain
Support Office (O)
303-969-2606 1/
Alternate: Roger Maxwell, 2/ Intermountain
Region (H)
303-215-0979 1/
Facility
Management, Design, (O)
303-969-2859 2/
and Engineering Division
Civil Engineer, Allen Bengtson 1/ Southwest
Support Office (O) 505-988-6039 1/
Alternate: Program Leader, Richard Niemeyer 2/ Intermountain
Region (O)
505-988-6035 2/
Architecture,
Design, and
Engineering
Office
P.O.
728
Shipping:
Environmental Engineer, Dick Fisher 1/
Alternate: Civil Engineer, Sharon Busch, 2/
Maintenance
and Engineering (O)
402-221-4993 2/
Civil Engineer, Stan Tolman 1/ National
Capital Support Office (O) 202-619-6383 1/
Alternate-1: Don Filsoof 2/ National Capital Region (O)
202-619-7060 2/
Alternate-2: Dave Hammers 3/ Maintenance and Design (O) 202-619-7270 3/
Room
358
LIST OF NATIONAL
AND REGIONAL COORDINATORS AND CONTACTS
FOR THE NATIONAL
PARK SERVICE (NPS) MAINTENANCE, OPERATION, AND SAFETY OF DAMS
(MOSD) PROGRAM
FOR ALL DAMS AND
IMPOUNDMENTS AFFECTING THE NATIONAL PARK SYTEM
NATIONAL PARK SERVICE
COORDINATORS
AND CONTACTS, continued
Name Mailing
Address Telephones
(O)
Office (H) Home
Civil Engineer, Mark Spadea 1/ Northeast
Region,
Alternate: Facility Manager, Ross Flanagan 2/ Maintenance, Design, and
Engineering (O) 215-597-5364 2/
Civil Engineer, David Price 1/ Northeast
Region,
Alternate: Fred Bentley 2/ Engineering
and Facility Management fax
617-223-5260 1/
15
State Street (O)
617-223-5296 2/
Steve Butterworth 1/
Alternate: Geoff Swan 2/ Pacific West Region (O)
206-220-4275 2/
Design
and Engineering (H) 425-643-7739 1/
909
Facility Management Chief, Jack Williams 1/ Pacific
Steven Bosiljevac, Civil
Engineer 2/ Pacific West Region (O)
510-817-1374
Civil Engineer, Gregory Robinson 1/ Southeast
Support Office (O)
404-562-3124, ext 692 1/
Alternate-1: Chief of Engineering, Fred Shott 2/ Southeast Region (O)
404-562-3124, ext 707 2/
Alternate-2: Civil Engineer, John Gopaul 3/ Facility
Management Division cell
404-277-4040 2/
Emergency Incidents: Chief Ranger, Judy Forte 4/
(O)
404-562-3108, ext 617 4/
cell
404-909-2911
(H)
770-594-9021
Structural/Seismic Engineer, Rich Silva 1/ National Park Service (O) 303-969-2552 1/
Alternate: Chief, Facility Design,
Bruce Warneke, 2/
Facility
Design Services, DSC-FDC fax
303-969-2736
LIST OF NATIONAL
AND REGIONAL COORDINATORS AND CONTACTS
FOR THE NATIONAL
PARK SERVICE (NPS) MAINTENANCE, OPERATION, AND SAFETY OF DAMS
(MOSD) PROGRAM
FOR ALL DAMS AND IMPOUNDMENTS AFFECTING THE NATIONAL
PARK SYTEM
NATIONAL PARK SERVICE
COORDINATORS AND CONTACTS, continued
Name Mailing
Address Telephones
(O)
Office (H) Home
OTHER CONTACTS
Program Manager,
FEDERAL
EMERGENCY MANAGEMENT AGENCY (FEMA)
Federal Interagency Committee on Dam Safety (ICODS) National
Dam Safety Program (O)
202-646-3035 1/
Chris Doyle 1/ Mitigation
Directorate (O)
202-646-2802 2/
Alternate: Eugene Zeizel 2/ Federal
Emergency Management Agency (O)
202-646-2704 3/
Alternate: Rita Henry 3/
National Design Engineer, William Irwin National
Dam Safety Program (O) 202-720-5858 1/
Alternate: Ronald Marlow 2/
ASSOCIATION OF
STATE DAM SAFETY OFFICIALS (ASDSO)
Executive Director, Lori Spragens Association
of State Dam Safety Officials (O)
859-257-5140
Conference Coordinator, Susan Sorrell 450
Old Vine Street, Second Floor fax
859-323-1958
Information Resource Specialist, Sarah
Mayfield
Administrative Assistant, Maureen
Chinn
APPENDIX D
DATA BOOK LISTING
I. TYPICAL DATA RECORDS
A. Typical
Types of Records - The following outline represents information
needed by the Bureau of Reclamation or
other inspecting organization in the
MOSD program to adequately prepare a
Technical Data Book. The data book
will be used to evaluate the safety,
maintenance, and operation of a dam.
Information should be presented to
inspection teams 2 months prior to on-site
inspection.
l. Document verifying NPS ownership or
dam safety responsibility
2.
Copy of any contractual agreements between NPS and lessee of NPS
dams therein relating to
acquisition, planning, safety inspections,
design, maintenance, operation,
construction, financial arrangements,
disposal, or any other activity
significantly affecting park safety,
maintenance, or operations
3.
Most current information from any type inventory of NPS dams
4.
Aerial photographs of damsite and reservoir area
5.
Design criteria and technical records
6.
Construction reports
7.
Project history
8.
Correspondence
9.
Previous Safety of Dams report
10.
Emergency Preparedness Plan
11.
Pertinent photographs
12.
Hydrology studies (most recent inflow design flood, other floods
considered at the time of design,
and flood routings)
13.
Instrumentation monitoring records
14.
Operation and Maintenance Reports
15.
Reservoir operation record
16.
SOP (Standard Operating Procedures)
17.
DOC (Designers' Operating Criteria)
18.
Statistics of dam, powerplant (if applicable), and reservoir
19.
Design and as-built drawings
20.
Reservoir area and capacity curves
21.
Discharge curves for all water control structures and conduits
22.
Monthly maximum and minimum reservoir elevations since first filling
23.
Average daily inflow to reservoir (include the source of the information
and the period of record used)
24.
Any current operating restrictions (maximum water surface elevation,
maximum discharge of spillway(s)
and outlet works, etc.)
25.
Records of any known problems experienced in operating and maintaining
the dam, spillway, and outlet works
(seepage, sinkholes,
sloughing of slopes, offsets,
displacements, cracking, erosion,
mechanical equipment failure,
debris, etc.)
B. Geology
1.
Topographic maps, USGS quadrangle maps
2.
Geologic reports (general regional, specific data on
damsite and reservoir, geologic profile along axis of dam, landslide surveillance data, and geologic interpretation)
4.
Geologic and seismic maps and drawings
5.
Liquefaction studies
6.
Geophysical data
7.
Volcanic activity in area
8.
Local petrochemical activity
C. Concrete
Dams
1.
Drawings: section through crown
cantilever including lines
of centers for an arch dam, plan
view of dam, profile of
dam-foundation contact, and surface
contour map (most detailed
USGS map of damsite)
2.
Tailwater data
3.
Most recent reservoir silt survey data (including density of silt)
4.
Maximum and minimum reservoir temperatures - relative to depth in
reservoir
5.
Most recent concrete tests and properties to include data on
compressive, tensile and shear
stresses, density, modulus of
elasticity, Poisson's ratio, and
diffusivity
6.
Contraction joint grout closure temperatures
7.
Depth of ice in reservoir at dam
8. Location and monitoring data for major cracks
in dam
9.
Design and measured uplift pressures
D. Embankment
Dams
1.
Type of dam (homogeneous, zoned, etc.)
2.
Gradation of construction materials
3.
Surface and internal drainage features
4.
Upstream and downstream slope protection
5.
Freeboard
6.
Crest details (including camber)
7.
Placement densities and moisture content
8.
Materials testing (laboratory and field tests performed)
9.
Filter design criteria
10. Toe drain system
11.
Soil parameters (including strength, permeability, void ratio, etc.)
12.
Foundation and abutment conditions
13.
Stability, settlement, and seepage measurements and analyses
14.
Preconstruction and postconstruction investigations (test pits, drill
holes, etc.)
15.
History of reservoir filling and drawdown rates
16.
Piezometer data
E. Mechancial Equipment
1. Descriptions
2. Design data on gates, valves, etc.
3. Installation-related problems
4. Air venting system (including test results
available)
5. Emergency gate closure report
6. Manual or automatic operation of equipment
7. Remote control
8. Auxiliary power
9. Steel pipe and its drainage system
10. Trashracks
11. Special operating conditions and restrictions
12. Control equipment
13. Corrosion protection
14. Additional equipment needed to pass the
design flood or to evacuate the reservoir
15. History of gate or valve operation and
associated problems
II. TYPICAL LOCATIONS OF
RECORDS
Suggested locations for
obtaining the engineering-related records are:
A.
B. Regional office
C. District office
D. Subdistrict office
E. Area office
F. Agency office
G. Project office
H. State Department of Water Resources
I. State Engineer
J. State Dam Safety Program Officer (See
Appendix C)
K. City and
L. Private owners
M. Soil Conservation Service
N. National Archives
O. Consulting engineers
P. U.S. Army Corps of Engineers (Regional
Hydrology, Floodplain and Flood
Insurance Studies, Hydraulics,
Geology, and hypothetical dam break studies)
R.
S. Federal Energy Regulatory Commission
T. Federal Emergency Management Agency (National
Flood Insurance Program)
U. NPS Regional and Park Historic or Cultural
Divisions
V.
Suggested locations of
obtaining geologic records are:
1.
2. State Geological Survey
3.
4. State Bureau of Mines
5. State and local university libraries
6. State, city and other local libraries
7. Consulting geologists
APPENDIX E
EXAMPLE EMERGENCY ACTION PLAN
The purpose of the EAP is to facilitate the early warning
and, if necessary, evacuation of persons in areas that would be affected by
possible dam or appurtenant works failure or misoperation. Superintendents
should develop an appropriate EAP for either high (1) or significant (2) hazard
potential dams under their jurisdiction or coordinate with non‑NPS dam
owners to assure implementation of their EAP in affected park areas. Personnel
designations, mapping, and local government contacts should have been made by
BASIC SYSTEM ELEMENTS
An effective Emergency Action Plan incorporates several essential elements.
These are:
1. Dependable and responsible rainfall and staff gage observers. Their duties are to report to the Dam Operator the rainfall accumulation over‑ a given period of time and the elevation of the reservoir pool or flow in the emergency spillway, if any. One of these observers should also give the dam a brief visual inspection at each gage reading to see if it is in danger of failing from reasons other than overtopping. The equipment needed to make these measurements can be a simple plastic rain gage and some sort of pole or staff in the reservoir or spillway area with elevations indicated clearly on it. There are more elaborate instruments available such as automatic rain and water level gages, but at a respectively higher cost. Their use is optional, but not essential.
2. Reliable and rapid local communications system with an emergency backup. This system is used to communicate the data gathered by the gage observers to the Dam Operator and by the Dam Operator in notifying the proper authorities of the need to initiate the warning plan and the evacuation plan. It can be by telephone, ham radio, CB radio, or police, fire, and other emergency radio systems. It is important that any system chosen have an emergency backup.
3. Dam Operator and Alternate. These persons' duties are to interpret the rainfall, streamflow, and spillway flow data given to them by the observers and other available weather information and, when necessary, notify the park EAP Coordinator or other authorities of the need to initiate the warning and evacuation plan.
4. Dam Hydraulic and Hydrologic Data. This information developed by a qualified engineer or gathered from other competent sources is used to establish the various trigger points (rainfall measurements, pool or spillway flow elevations, or other pertinent facts) at which the several progressive phases of the emergency warning system are initiated. This information is obtained from an engineer study which com pares various rainfalls on the watershed with the spillway discharges they create and reservoir elevations. The Bureau of Reclamation is developing some of this type of information during their assessments of NPS Dams classified as high or significant hazard potential.
5. A Warning Dissemination Plan. This basically consists of a list of people to be notified if the conditions dictate. This should include the local government Emergency Services Coordinator or other designated local government officials who will in turn notify the people directly affected by flooding outside the park and carry out the Evacuation Plan, if that becomes necessary.
6. The Evacuation Plan. This consists of a list of homes, businesses, campsites, stream crossings, recreation activities, highways and roads, with their locations clearly identified on an inundation map, that are to be evacuated if necessary, and a means of transporting the people to a designated emergency shelter. Mapping should be of sufficient detail and scale to show where possible homes, businesses, campsites, stream crossings, highway and roads, and recreational activities are located in relationship to the dam and estimated flooding. Access routes should be clearly marked. Since detailed inundation maps may not be readily available or easily used at a disaster area, a concise and clear word description should also be prepared for easy word‑of‑mouth communication. Time word description would tell potential evacuees how high they should elevate themselves above the river or by horizontal distance to an area known to be safe from inundation. The EAP with the map should be filed with the park EAP Coordinator and the local Emergency Services Coordinator or other local government officials. The plan should also pro vide for the protection of the evacuated area until the residents can return to their areas. The local Emergency Services Coordinator or other local government officials are responsible for preparing and carrying out the Evacuation Plan if located outside the park. Proper coordination should be assured with these officials.
The following is a fictitious example of a well‑organized
Emergency Action Plan for a city and is based on one prepared by the Tennessee
Valley Authority for the City of
1. Rain measuring equipment will be inspected and measurements begun initially upon notice of a flood watch or warning. This warning would come from the National Weather Service.
2. Rainfall measured by the gage observer will be compared by the Dam Operator with the rainfall of other weather observers such as local government Emergency Service officials during flood watches and warnings.
3. Rainfall will be monitored around the clock and reported to the Dam Operator on a 24‑hour basis by the rainfall gage observer.
4. Upon receiving notice that two (2) inches of rain in any 24‑hour period has fallen, the Dam Operator will initiate State II by notifying the EAP Coordinator who will notify the:
A. Superintendent
B. Park Ranger,
C. Administrative Manager
1. Every four hours after Stage II is affected, the staff gage observer will personally read the gage at the spillway and record the reading and report it to the Dam Operator.
2. When a depth of two (2) feet in the spillway exists, the frequency of the readings will be increased every two flours, or will be made even more frequently if desired by the Dam Operator.
3. In the event the spillway readings reach three (3) feet, Stage III will be put into effect by the Dam Operator. The Dam Operator will notify the EAP Coordinator of Stage III, who will in turn notify the:
A. Superintendent
B. Park Ranger
C. Administrative Manager
D. Local Government Emergency Official
1. The Emergency Action Plan Coordinator will initiate the Evacuation Plan.
2. The Evaluation Plan will be implemented by the Ranger Division under the direction of the Park Ranger, with assistance from all available Fire, Rescue, and other appropriate personnel.
3. Necessary transportation from the affected area will be provided by a school bus or other means as determined by the EAP Coordinator.
4. Evacuated persons will be sheltered as designated in the evacuation notice.
5. Once the area is evacuated, persons designed by the Park Ranger will secure the area from access except for official business.
6.
CONCLUSION
The local government Emergency Services Coordinator in your city or county should be notified, if appropriate, of your plans to establish the EAP, and its development must be closely coordinated with him so that he will be completely familiar with it. Once the plan is established it should be reviewed annually and updated if the conditions downstream have changed enough, to dictate it.
The Warning Dissemination and Evacuation Plans can also be used if the dam is failing from reasons other than flooding and overtopping. On new or rehabilitated structures this Emergency Action Plan should be established prior to the beginning of impoundment so that an evacuation can be carried out‑if a failure prone situation develops. Hopefully you will never need to use it, but if the need ever arises, such a system will greatly reduce the chance of any loss of life.
APPENDIX F
STATE SAFETY OF DAMS OFFICERS
|
|
Leslie A.
Durham |
|
|
|
|
|
William C.
Jenkins |
|
|
Alvin
Simmons, Jr. |
|
|
David A.
Gutierrez |
|
|
|
|
|
Wesley Marsh |
|
|
Frank M.
Piorko |
|
|
Stephen H.
Partney |
|
|
Francis E.
Fiegle, II |
|
|
Edwin Matsuda |
|
|
Guy
E. Paul |
|
|
Paul
Mauer, Jr. |
|
|
Kenneth E.
Smith |
|
|
Joe D. File |
|
|
Art Clay |
|
|
Zahir 'Bo'
Bolourchi |
|
|
Tony Fletcher |
|
|
Ken Pensyl |
|
|
Michael D.
Misslin |
|
|
David
Hamilton |
|
|
Dana
Gauthier |
|
|
Mike
Meadows |
|
|
James
L. Alexander |
|
|
Laurence Siroky |
|
|
Patrick
Diederich |
|
|
Robert K.
Martinez |
|
|
James W.
Gallagher |
|
NEW |
John H. Moyle |
|
|
Elaine C.
Pacheco |
|
|
|
|
|
Max Fowler
|
|
|
Jason Boyle |
|
|
Mark B. Ogden |
|
|
Cecil R.
Bearden |
|
|
John A. Falk |
|
|
Dennis R.
Dickey |
|
|
Miguel A.
Perez Garcia |
|
|
Paul
Guglielmino |
|
|
Steven M.
Bradley |
|
|
Timothy G.
Schaal |
|
|
Lyle Bentley |
|
|
Warren D.
Samuelson |
|
|
David
Marble |
|
|
Robert B.
Finucane |
|
|
Dianna C.
Sheesley |
|
|
Douglas L.
Johnson |
|
|
Brian R.
Long |
|
|
|
|
|
David S. Benner |
APPENDIX G
Example Letter To Non‑NPS
Dam Owner or Regulatory Agency (Preferably)
Certified Mail, Receipt Requested
Ms. Francis Doe, Chief, Engineering Division
South Lakes, Inc.
Subject:
Dear Ms. Doe:
As discussed during our telephone conversation on
As you can well understand, we need this information so that
appropriate steps can be taken to assure that park visitors and resources are
protected in those areas for which we have warning, rescue and evacuation
responsibilities, in the event of spillway releases, possible dam failure, or
accidents at the dam or reservoir.
Please send the following items to this park periodically
and by certified mail:
1. A copy of your
most current formal safety of dams inspection report, and if the dam has
any serious deficiencies, an explanation of how and when corrective action will
be performed. Please review and revise
the attached NPS Inventory of Dams Report listing for your dam based
upon this report. To be able to assign a
safety of dams condition code [data element 27], this report will need to
include a recent stability analysis including the use of criteria for the
Maximum Probable Flood (MPF) and Maximum Credible Earthquake (MCE). If the
project is proposed for construction or reconstruction, the National Park
Service would appreciate the opportunity to review and comment on your design
and construction documents.
2. Permission
granting NPS observer status during your next formal safety of dams inspection.
3.
Please incorporate the park into your Emergency Action
Plan (EAP) and send us a copy. This EAP contains early warning, flood mapping,
and evacuation procedures and is given to those jurisdictions that would be
affected by spillway releases, possible dam failure, misoperation, or even an
accident at the dam or reservoir. Your
Notification Directory or Call-up List should state that the park is
immediately affected and should be contacted directly by the dam
operator/tender. Based upon these
documents, the park will include your EAP into the park’s Early Flood Warning,
Search/Rescue, Evacuation, and Recovery Plan (ESEP) for those areas which it
has warning, rescue, and evacuation responsibility. Your EAP and the park’s ESEP will become part
of the park's Emergency Operations Plan.
This responsibility is described in the U.S. Department of the Interior,
National Park Service Reference Manual -40 , Dams and Appurtenant Works,
Chapter 6, Section D, and is in accordance with the Federal Guidelines for
Dam Safety, pages 10 and 36.
If you have any questions or comments about this request,
please contact (Park Official) at 999‑999‑9999.
Sincerely,
Regional Director/Superintendent
cc: NPS Regional Maintenance, Operations, and Safety of Dams Program Coordinator
NPS Washington Office, Park Facility Management Division, code 2420
APPENDIX
H
List of Official
Technical Supplements to Director’s Order #40 and Reference Manual(RM)-40
for the National Park Service (NPS)
Maintenance, Operation, and Safety of Dams (MOSD) Program
Reference WASO memorandum dated
Release
Date
Title
of Document and Distribution Description
OPERATIONS AND MAINTENANCE
Reference Rm‑40, Chapter 6.
Operation and Maintenance
Guidelines WASO A7615 (610) Maintenance and operational
For Small Dams, Bureau of Reclamation, memo, August 10, guidelines for all NPS and non-NPS
Dam Safety Office,
December 1982
System and Related Areas
STATE COORDINATORS
Dam Safety, Know the Potential
Danger FEMA Letter dated Reference RM-40, Appendix F.
Federal Emergency Management
Agency (FEMA), August 1988, May 1987 listing of State Dam Safety
Earthquakes and Natural Hazards
Program Servicewide Officers and Emergency Management
Division,
EMERGENCY ACTION PLANS
Reference RM-40, Chapter 6, Section D.
Flood Plain Management ‑
Availability
of Guidelines on Community
Local Servicewide flooding, flash floods, and dam
Flood Warning and Response
System, failures.
National Park Service, Park
Facility
Management Division,
EMERGENCY ACTION PLANS
Flood Warning and Preparedness
Plans, WASO A7615(610) Reference RM-40, Chapter 6, Section D
Hydrology Subcommittee of the
Federal memo,
Interagency Committee on Water
Data, Servicewide flooding, flash floods, and dam
Appendix H
continued, List of Official Technical Supplements to Director’s Order
#40 and Reference Manual(RM)-40
INVENTORYING
Reference RM-40: Chapter 2, Section
NPS Inventory of Dams on-line
database Servicewide C and Appendix A
National Park Service, Park
Facility
Management Division,
2005
HAZARD POTENTIAL Reference RM-40,
Chapter 1, Section
Downstream Hazard
Classification WASO A7615(610) D, 3. Guideline for determining down-
Guidelines, ACER Technical
Memorandum memo,
No. 11, Bureau of
Reclamation,
Regionwide sification at
and downstream of dam ‑
Assistant Commissioner,
condition.
STRUCTURAL AND MAINTENANCE
EXAMINATION Reference RM-40,
Chapter 6, Section
Safety Evaluation of Existing
Dams, WASO A7615(670) C, 2, a. Manual for examining earth
Bureau of Reclamation, memo, February
12, and concrete dams.
Dam Safety Division, 1981, and
Regionwide
PUBLIC SAFETY EXAMINATION
Reference RM-40, Chapter 6, Section B
Public Safety Around Dams and WASO A7615(610), Manual for examining public safety
Reservoirs, Interim Working memo,
Guideline, Dam Safety Inspection Regionwide
Section, Bureau of Reclamation,
Appendix H