Send comments to
Tim_Harvey@nps.gov
Approved: _______________________
Director
Effective
Date: _________________
Sunset:
_______________________
The provisions of Special Directive 83-2, and any
other conflicting instructions previously issued, are superseded and replaced
by this Director's Order and its implementation procedures.
Contents
1.0
Background and Purpose
2.0
Authorities
3.0
Policies, Procedures, and Requirements
3.1
Implementation
3.2
Measurement of Use
3.3
Existing Capital Assets
3.4
Accountability and Billing
3.5
Exceptions
3.6
Utility Rate Worksheets and Instructions
3.7
Date of Implementation
3.8
Additional Review
3.9
Limitation
_________________________________________________
1.0
Background and Purpose
Section 4 of the Act of August 8, 1953 (16 U.S.C.
1b(4)) grants the Secretary of the Interior the authority to “furnish, on a
reimbursement or appropriation basis, all types of utility services to
concessioners, contractors, permittees, of other users of such services within
the national park system.” Utility
services include such things as electricity, natural gas, water, and solid
waste. The National Park Service’s (NPS)
authority to sell utility services is discretionary, meaning that the NPS is at
liberty to sell them, but may choose not to do so. Since there are many situations where there
is compelling need for the NPS to provide utility services to non-NPS users,
reasonable policies and procedures need to be in place, and applied
consistently throughout the National Park Service.
The purpose of this Director's Order is to:
· Update NPS policies and procedures for recovering costs associated with providing utility services to non-NPS users.
· Be responsive to the Inspector General’s recommendation that policy and procedural guidance to the field is revised so that they are aligned with OMB guidelines.
· Address a material weakness in accountability and reduce the deferred maintenance backlog in NPS facilities.
The provision of utility services by the NPS has considerable cost implications for both the NPS and those who obtain them from the NPS. In turn, it has cost implications for park visitors and the taxpaying public, who ultimately bear those costs. Therefore, this Director’s Order is intended to provide an equitable balance between:
·
Cost recovery for providing utilities, including, but not limited to,
annual operating costs, cyclical repair and rehabilitation costs, and capital
investment cost.
·
Reasonably priced visitor services and resource protection.
2.0
Authorities
The authority to issue this Director's Order is contained in 16 U.S.C. 1 through 4 (the NPS Organic Act), and Part 245 of the Department of the Interior Manual, in which the Secretary of the Interior delegates to the NPS Director the authority to supervise, manage, and operate the national park system.
The 16 U.S.C. 1b(4) authority to sell utility
services under the procedures prescribed in this Director’s Order shares some
similarities with the authority contained in 16 U.S.C 1a-2(e), which allows the
national nark system to enter into contracts that provide for the sale or lease
of services, resources, or water. The
major distinction between the two authorities is that 16 U.S.C. 1a-2(e) is
generally applicable outside the parks, whereas 16 U.S.C. 1b(4) is applicable exclusively within the
parks. The implementation of 16 U.S.C.
1a-2(e) is the subject of Director's Order 35A:
Other references that are related in whole or in
part to this Director's Order include:
A-25
- Policy guidance for federal agencies in setting fees.
A-45
- Policy governing charges for rental quarters and related facilities.
32 - Cooperating
Associations.
36 - National Park Service
Housing Management
48 - Concessions Management.
81 - Maintenance Management.
[Not all of the documents referenced above are
available at this time.]
3.0 Policies, Procedures, and
Requirements
Whenever possible, the managers of NPS areas are expected
to secure utilities from other agencies or entities. In other cases, where there are no outside
providers, managers may generate or otherwise self-provide utility services,
not only for direct NPS use, but also for non-NPS users under an operating
agreement with the NPS within the park boundaries. Neither the law nor NPS policy obligates the
NPS to sell or lease any utility services.
The decision to sell is within the sole discretion of the Secretary of
the Interior (or the Director, as the Secretary's designee). The NPS is generally required to recover the
costs of utilities provided to non-NPS users.
Utilities may be necessary to protect park resources
and support appropriate visitor use, and contribute to the NPS mission of
making parks available for use and enjoyment by the public. Because of regulatory, environmental,
physical, and public policy reasons, park utilities are usually more expensive
to construct, operate, and maintain than services in cities and towns.
3.1 Implementation
- Park superintendents may exercise the Director's authority to provide utility
services to non-NPS users, provided that the requirements contained in this
Director's Order are met.
3.2 Measurement of Use - All utilities will be
measured or metered for all users, including the NPS, so that a percentage of
use can be accurately assessed. This
will typically be accomplished with the use of meters or scales (e.g.: scales
for the weight of solid waste; water meters for water and sewage use; electric
meters; gas meters; fuel dispensers; telephone timers). A Utility Worksheet will be
used in determining appropriate methods of measurement. Any losses in the system between the
production and the actual user will be prorated to each user based on actual
consumption.
3.3 Capital Assets - Capital assets installed
after 1999 will be included as an existing Capital Asset. Capital assets installed prior to 1999 are
not included in the capital portion of the rate basis until they are upgraded
or replaced. After implementation of this Director’s Order, any replaced,
upgraded or additional utility capital costs will be included as a Capital
Asset.
3.4 Accountability and Billing - All costs will be based on a unit cost and on utility use records for a recent 12-month period. The rates will be computed and valid for one year. If for any reason, new rates are not developed and approved in a year's time, the previous rates will remain in effect. All rate changes will have a 90-day notice before implementation takes place.
3.5
Exceptions – Except as otherwise
authorized by law, all utility users are expected to comply with this
order.
(a)
A waiver of all or part of the implementation requirements of this
Director's Order may be granted by the Associate Director for Park Planning,
Facilities and Lands, in consultation with the Assistant Director of Business
Services, after a careful feasibility
analysis is conducted.
(b) Where complying with this
Director’s Order would jeopardize the economic viability of a non-NPS user’s
operation or result in unreasonable rates for visitor services, a waiver of
this order must be requested by the user.
The request must include a financial analysis of the impact of the
rates. The request for waiver must be
completed within the 90-day notice of rate change, see 3.4.
(c) For procedures relating to
concession operations, refer to Director's Order 48.
(d) NPS employees who occupy NPS
owned housing units are exempt from paying full costs because utility costs are
computed in accordance with OMB Circular A-45.
3.6
Utility Rate Implementation - Detailed instructions
will be included in Reference Manual 35B to ensure that implementation is
consistent throughout the NPS.
3.7
Date of Implementation - Implementation of this
Director’s Order will be instituted for all non-NPS users at the next yearly utility
rate computation after the effective date of this Director’s Order in
accordance with the associated Reference Manual.
3.8
Additional Review - Regional
directors may
impose additional review procedures or considerations beyond those required by
this Director's Order.
3.9
Limitation - As is the case with all components of the NPS directives system,
this order is intended only to improve the internal management of the NPS and
it is not intended to, and does not, create any right or benefit, substantive
or procedural, enforceable at law or equity by a party against the United
States, its departments, agencies, instrumentalities or entities, its officers
or employees, or any other person.
---------End
of Director's Order -------