• Kenilworth Aquatic Gardens, Tropical Water Lily

    National Capital Parks-East

    District of Columbia

Kenilworth Park Landfill Project Milestones

Project Milestone

Actual or Target Dates

Feasibility Study (FS):

FS Report

April 2012

Proposed Plan

February 2013

Public Comment Period

March 5 - May 6, 2013

Supplemental Groundwater Study

Sampling and Analysis Plan

Winter 2013-2014

Record of Decision

Summer 2014

Implementation of the Selected Remedy:

Remedial Design

2015

Remedial Action

2015-2017



 

Did You Know?