Silo roof repairs, before and after
The final phase of the barn restoration project consisted of repair and restoration of the brick silo and roof. This involved removal of the temporary cover constructed in 2003 to preserve the remaining roof elements. Unfortunately, the roof framing was largely unsalvageable, and the entire roof and roof framing had to be replaced in kind. In addition, masonry repairs were undertaken to address a large crack that extended the full length of the silo, and most of the interior of was parged. Repairs to the silo were completed in 2009.
The Thomas Barn and Silo Restoration project was performed by the National Park Service's Historic Preservation Training Center (HPTC). HPTC is headquartered at Monocacy National Battlefield, in the historic Gambrill House.