|
PRESERVATION
TECH NOTES WINDOWS NUMBER 20
|
| |
Figure
5. The replacement aluminum muntin accurately replicated original
profiles while accommodating insulating glass and thermal stops.
Drawing: Bruner/ Cott and Custom Window. |
Fabrication
A significant challenge to developing the Sears building replacement
window was matching the original narrow muntins. Common industry practice
for true divided light aluminum windows was to utilize wider muntins
that conceal the spacer bar in the insulating glass unit and protect
the edge sealant from light degradation. This approach would significantly
encroach into the sightlines of the original windows as a result of the
wider muntin and proportion changes to the window. In the case of the
Sears building, however, the window manufacturer utilized a narrow spacer
bar that permitted an accurate replication of the original 7/8-inch muntin
(see figure 5). Substituting a dark bronze anodize finish for the conventional
aluminum finish further reduced the visibility of the spacer making it
appear as a shadow line when viewed from an angle.
 |
| Figure
6. Sections of original and replacement windows. Drawings: Bruner/Cott
and Custom Window. Click here to see a larger version of this
drawing. |
|
Each replacement window developed for the Sears building was fabricated
from over forty new aluminum extrusions. The large variety of custom
designed elements allowed for a faithful reproduction of the original
profiles. At the request of the developer, the replacement windows were
not operable, yet their appearance suggested the functional nature of
the original projecting ventilators. Tabs were added to resemble the
weathering flange closed flush against the fixed outer frame, while drip
caps shielded simulated hinges. The muntin, rail, head, sill and jamb
profiles were also accurately reproduced. In order to replicate shadows
cast on the original frames, the manufacturer included cosmetic bolt
heads on the mullions running between each of the paired and tripartite
window arrangements.
The Inside Look
The inside appearance of the windows was important to the developer in
marketing the new office space. A similar effort was made, therefore,
to duplicate historic interior details and profiles. As was typical
of multi-story warehouses, the Sears building’s historic steel
windows were glazed on the inside so that the individual panes could
easily be replaced when broken.
To simulate the original
interior putty profiles, the fixed-light muntins were tapered to
the same 1/8? thickness
of the original sections while stepped muntins were used in the
central vent where steel beads had originally secured the glazing.
Jambs in
the replacement units were also beveled to recall the shape of
the old glazing putty (see figure 6). Testing and Installation
Being a new window system, the manufacturer had independent firms conduct
standard performance tests on both the insulating glass and a mock-up
of the complete window. In accordance with ASTM guidelines, tests on
the complete window evaluated air infiltration, water resistance, and
deflection and structural deformation under uniform load. With the
test units meeting required specifications, window fabrication proceeded.
Lengths of the new spacer were shipped to a glass fabricator where
the insulating glass units were produced with a standard butyl and
silicone dual-seal. Completed glass units were then shipped to the
manufacturer for final assembly of each window.
While the new windows were being manufactured, a local contractor began
the three month long process of stripping, repairing, repainting and
reglazing the historic second floor windows and other retained units
in stairwells and other non-office locations. As the new windows began
to arrive in Boston, the general contractor removed the original units
that were slated for replacement and a team of eight to ten workers started
installing the new windows.
Evaluation

Contents
Print
Version
|