May 7, 2002

Today's Accomplishments: We unloaded the U-Haul truck and got things organized. Our work trailers will not come until tomorrow, so we were somewhat limited.  Supplies were purchased from Corinth, the U-haul truck was returned, and water pumps were picked up from Florence, Al.  Supplies for the rail system tracks that are to aid excavation at the mound were also dropped off at the base of the mound.  In the afternoon we began to assemble the tracks, and completed the portion of the track leading to the water screens on the summit of the mound.
The track sections laid out showing approximate route the railing system will take to the water screening area. The track sections laid out showing approximate route the railing system will take to the water screening area.
Josh Wells, Rachel Horlings, and Klinton Baggett cutting the wooden supports for the track. Josh Wells, Rachel Horlings, and Klinton Baggett cutting the wooden supports for the track.
DSC00038.jpg (75177 bytes) Ben Barnes and Addison Carter bolting sections of track together.
Steve Kidd, Kellie Jefferson, Ben Barnes, and Klinton Baggett assembling sections of track. Steve Kidd, Kellie Jefferson, Ben Barnes, and Klinton Baggett assembling sections of track.
A turn section where the track makes a quarter turn to the northwest. A turn section where the track makes a quarter turn to the northwest.
The completed section of the track at the end of the first days work. The completed section of the track at the end of the first days work.