Methodology
Mixing the Materials
The concrete mix was composed of the following materials:
· White portland cement meeting ASTM C-150 Type I Standards
· Inorganic masonry pigment, chromium oxide green as manufactured by Mineral
Pigments Corporation
· Coarse aggregate (gravel) 3.8 to #4 “Eau Claire”, dry and
bagged
· Fine aggregate (concrete sand), “Eau Claire” passing a #16
screen, dry and bagged
· Air-entraining agent (liquid admixture of the vinsol resin type conforming
to ASTM 260-77)
· Water-reducing agent, liquid type conforming to ASTM C-494, “Chemical
Admixture for Concrete,” Type A (Pozzolith 122-N)
· Water, clean, clear, potable with a pH reading between 5-8 and the conductivity
not exceeding 100 MILLIMHOS on the 0-200 scale.
These materials were mixed in a paddle mixer large enough to combine
the materials so that each batch would not exceed the number of molds
that could be vibrated without tempering the mix with water. Each day,
before the start of mixing, a minimum of 2 cubic feet of design mix “butter” was
run through the cleaned mixer and dumped. This procedure seasoned the
mixer. If another batch was mixed within 30 minutes, the remnants of
the previous batch was used as the “butter”. The mixer
was cleaned at the end of each day.
Finding the exact concrete mix to replicate the color and appearance
of historic stone is usually a matter of some experimentation. However,
in this case, by using the successful formula derived in part from the
work on the Renwick Gallery, the only major obstacle was finding the
proper pigment color that would match the serpentine stone, and would
not fade. After a series of test stones were manufactured and fully cured,
a close color match was established. The mix that produced a color closest
to that of the serpentine stone, and also meeting all the required strength
tests, was composed of the following materials in the quantities indicated
(the quantities shown are in pounds for ½ cubic yards):
· White portland cement- 376 lbs.
· Pigment- 12 lbs.
· Fine aggregate- 700 lbs.
· Coarse aggregate- 775 lbs.
· Water- 150 lbs.
· Vinsol resin- 4 oz.
· Pozzolith 122N- 18 oz.
These materials were combined in the following sequence:
· Fine and coarse aggregate
· Maximum of 2/3rds of the water
· White portland cement
· Pigment
· Admixtures
· Remaining water
The materials were combined in the mixer until there was a consolidated,
homogeneous concrete of the required slump—usually about two to
three minutes and always less than ten minutes.
Quality Control
Once the materials were thoroughly mixed and ready to be poured, measures
were taken to ensure that the newly-fabricated pre-cast units met the
specified strength criteria. In the manufacturing process adopted for
Six Logan Circle, a minimum of 6 standard testing cylinders (6”x12”)
were filled from a selected batch once a day, and sent to a testing
laboratory. Two of the cylinders were tested for compressive strength
at 7 days and at 28 days. The remaining cylinders were retained for
56 days for additional testing before disposal. A minimum of 2 standard
6”x12” cylinders cast from all the other batches was collected
and also tested for compliance with the design criteria of 5,000 psi
at 28 days.
Pouring the Concrete
 |
| Figure 7. The workmen shown here are cutting
the air bubbles from the sides of the mold using a cake spatula
during the first 10 seconds of the vibration process. Photo:
James Smith |
The consolidated and homogeneous concrete mix was poured from the
mixer into the specified mold which had already been placed on the
vibration table. The vibrating process forces the entrained air and
surface air out of the mold, eliminating in most cases the possibility
of surface imperfections from air bubbles. Proper vibration of the
newly poured concrete was extremely important to obtain a high quality
pre-cast concrete. The vibration table operated at a rate of 2,600
vibrations per minute and could accommodate all the castings from a
batch within thirty minutes after mixing. Small cast units required
approximately sixty seconds of vibration and the larger ones required
approximately ninety seconds. A cake spatula was effective in cutting
many of the air bubbles from the surface of the sides of the mold during
the first ten seconds of the vibration process (see figure 7).
Air Curing, Mold Removal and
Inspection
After the vibration process was completed for each stone, the molds
were placed on heated benches for sixteen hours, after which the molds
could be gently removed without damaging the stone. Each stone was
then inspected for any visual inconsistencies or other imperfections
from the mixing, pouring and vibrating process. The stones were evaluated
for problems such as uneven or non-matching coloring, chips, exposed
aggregate, air bubbles (pin holes), or depressions. During the manufacture
of the new pre-cast stone, more than 400 newly cast stones were rejected
due to surface deficiencies.
 |
| Figure 8. After soaking for
6 hours to remove soluble salts in a polyethylene-lined wood
water tank, the pre-cast units were allowed to dry for another
6 hours. This process was repeated 3 times for each pre-cast
unit. Photo: James Smith |
Removing Soluble Salts
The final step in the manufacturing process was essential
to the successful outcome of the product. In this step, the stones
were submerged in a water tank for a period of six hours, then removed
and dried for six hours (see figure 8). The drying process forced soluble
salts inherent in the concrete mix to the surface of the stone. An
application of a weak solution of muriatic acid with a thorough water
rinse was used to wash away the leaching salts. The procedure of soaking
and drying was repeated three times for every stone. After completing
this process, each stone was transferred to the basement for storage
on wooden skids.
Installation
Before any of the original stone was removed, the corresponding section
of pre-cast material was arranged in the “staging area” in
the basement. Using the measured drawings and numbering system prepared
earlier, the blocks of cast stone were assembled on the basement floor
on top of 4” of sand. Assembling them in the staging area allowed
for final inspection for the blocks and also allowed the master mason
to arrange the new stones during a “dry run” prior to the
actual installation on the building, thereby minimizing problems once
the work on the building began (see figure 9).
 |
| Figure 9. Using the measured drawings
as a guide, the pre-cast units were assembled in the staging
area on top of 4 inches of sand prior to their installation
on the façade. Photo: Robert Powers |
 |
| Figure 10. The new pre-cast
units were hoisted up the scaffolding on wide belt slings with
an electric winch, and installed in place using a portland
cement-based mortar appropriate for cast-concrete. The original
bricks were relaid with a more traditional lime-based, dark
colored mortar. Photo: James Smith |
Once all the new pre-cast concrete blocks were manufactured, inspected
and fully cured, the process of dismantling the existing deteriorated
façade and installing the new material began. Since the serpentine
stone was used as a veneer covering structural brickwork and was not
itself a structural element, sections of the veneer could be removed
without jeopardizing the stability of the building.
With the front elevation fully scaffolded, sections of the serpentine
stone and ornamental brick were removed. Because the brick trim was in
excellent overall condition and was to be reused in the new façade,
it was carefully removed with hand tools, inventoried, and stored for
reinstallation. With the serpentine and face brick removed, necessary
repairs were made to the structural brick, and stainless steel anchors
for the new pre-cast veneer were installed. The new cast stones were
hoisted up the scaffolding on wide belt slings with an electric winch
and installed in place (see figure 10).
Since the new pre-cast concrete blocks are much harder than the original
serpentine stone, a mortar mix containing a large proportion of white
portland cement was used. However, other than the composition, the new
mortar joints match the light-colored, raised mortar joints used on the
original stone façade. The walls were then backfilled with a parching
material.
The original bricks were individually cleaned with bristle brushes and
water before being reset into the new façade. The new brick mortar
was based on an analysis of the original, dark colored brick mortar and
matched it in composition, color, texture, joint width and profile (see
figure 11).
 |
 |
| Figure 11. Close
up views of the newly installed pre-cast concrete units and
the reinstalled original brick. Photo: James Smith |
|