|
Preservation Problem Early work focused on the need to make the building as weathertight as possible, yet allow for adequate ventilation. Consideration was given to devising a solution that would incorporate the window work with a passive ventilation system. It was recognized that if the house was tightly sealed with insufficient ventilation, the building would be particularly susceptible to condensation and moisture damage, Another factor to consider was that the building would remain unheated and unoccupied for an undetermined length of time. Neither boarding over the openings nor installing full sash throughout would provide optimum ventilation on the interior. This would be required to deter fungal decay of the wood and to avoid condensation damage to plaster walls and to their decorative stencil work. Hot daytime temperatures followed by cold nights in the spring and early fall could result in significant condensation damage to the plaster and stencil work. Damage would be particularly acute when nighttime temperatures fell below freezing. Furthermore, the hot moist air of the long Maryland summer would create problems, since high humidity can present a favorable condition for fungal growth. This is particularly true when the drying effect of air movement, normally induced in an occupied building, is not present. The potential for damage in these circumstances was great. Once wood absorbs enough moisture from the hot humid air and if fungal attack begins, the process of wood decay would enable the fungi to maintain the wood in a wet condition since fungi reduces wood to water and carbon dioxide. While such moisture problems could arise throughout the house, the basement was particularly susceptible to such damage due to moisture infiltration through the dirt floor, the below grade location, and seepage through the walls and basement doors. Special care should be taken to provide sufficient ventilation in unoccupied historic buildings to deter fungal decay and condensation damage. |
|
| Preservation
Solution Since the stabilization plan did not call for the installation of either a heating or a mechanical ventilation system, the solution to the air circulation needs was to install window vents. The basic ''rule-of-thumb'' used by the project staff for determining the amount of open air needed for good air circulation in this building is to use 50 percent of the sash units for ventilation. This approach has been successfully used by the Williamsport Preservation Training Center in previous projects. Depending upon individual conditions, some adjustment needs to be made based on the layout of rooms, interior walls, door locations, and number and location of stair shafts and windows. Because cross-room ventilation was desirable, the location
of the ventilating louvers was critical. With proper planning, natural
ventilation could be induced through the ''chimney'' or ''updraft effect''
within the building by which warm air raises and escapes through higher
level vents, to be replaced with cooler air entering at lower levels.
Good air movement would also tend to equalize interior and exterior temperatures, thus lessening condensation problems within the brick wails and on interior painted plaster surfaces. The window louvers had to be located so as to promote cross-room
ventilation and avoid stagnant air pockets in the rooms. Furthermore,
improvements to the appearance of the exterior of this long neglected
building were desired. Efforts were taken, therefore, to locate as many
of the louvers as possible on side and rear elevations, thereby minimizing
the visual impact on the front elevation. Full double-sash vents could
be placed in some side and rear windows to permit more glass on the front
elevation. Even the glazing in the reconditioned or replacement windows
would help to facilitate air movement within the building, since the sunlight
passing through the glass would heat inside air and cause it to rise out
through upper floor level vents. Cooler air entering through the basement
windows would replace the warmer air.
A survey of the building's 31 window openings established that on the first floor all but one sash were either missing or beyond repair. Altogether, only about one-third of the individual sash units were repairable. Most of those that were reconditioned required muntin replacement. In order to save on the final production costs involved in repairing or constructing the 52 individual sash units, all sash work was completed in one shop operation. The louvered vents were temporarily installed in lieu of the glazed sash on the bottom half of most window openings as part of the ''mothballing'' and stabilization efforts. |
Home | Search | E-mail | Technical Preservation Services | NPS History & Culture