Windows Number
20
Aluminum
Replacement Windows for Steel Projecting Units with
True Divided Lights and Matching Profiles
Chad Randl
Technical Preservation Services
National Park Service
Sears
Roebuck and Company Mail Order Store
(Landmark Center)
Boston, Massachusetts
The Sears Roebuck and Company Mail Order Store
was constructed in 1928 in the Fenway section of Boston. Designed to
meet the needs of traditional
catalog sales and the company’s rapid expansion into urban retail
markets, the eight-story brick clad structure combined one million square
feet of warehouse and shopping space. Retail activity was concentrated
on the lower levels, while the upper six floors were devoted to processing
catalog sales and providing warehouse facilities. The reinforced concrete
framed structure has modest Art Deco detailing that is particularly prominent
on the eleven story central tower and flanking piers that project above
the roof parapet. Over 1,100 steel industrial windows were original to
the structure. Placed individually or in groupings of two or three, most
featured either a single projecting ventilator or a pair of stacked ventilators
set within the multi-light window. Each vent in turn was typically divided
into two or three vertical lights.
After more than a decade of disuse, a $100 million rehabilitation was
undertaken in the late 1990s to convert the building into a mixed retail-office
complex called Landmark Center. Through a process of evaluating the surviving
windows and experimenting with various treatment solutions and design
proposals, the decision was made to replace the majority of the windows
while retaining and repairing units in select locations. A new custom
aluminum window featuring true divided lights and insulating glass was
developed that replicated both the interior and exterior details of the
original windows.
Problem
The design and placement of the original rolled steel industrial windows,
manufactured by the now-defunct firm of David Lupton’s Sons, contributed significantly
to the historic character of the Sears building. Utilitarian yet distinctive,
the windows reflected the dual function of the structure as warehouse and
showroom. Of the building’s seventeen window types, almost all shared
some variation of the centrally located projecting ventilator (or ventilators)
framed by a group of fixed lights (see figure 1). Details such as muntin
patterns, muntin widths and profiles, and the profiles of the operable vent
were integral to the look of the windows and the building as a whole (see
figure 2). Because of the distinctive character and prominence of the windows,
any treatment plan required careful regard for the historic appearance of
the original units.
A window inventory and condition survey was the first step in determining the
most appropriate course of action. The assessment revealed that a majority
of the original units had survived, though with varying degrees of wear, corrosion
and other damage. Water penetration had led to deterioration along the interior
glazing beads of the muntin in the ventilator. In some locations structural
settlement had caused the window frames to rack and bend out of plumb making
the vents inoperable. A number of windows had been altered to accommodate air
conditioner units, including the removal of individual muntins. Accumulated
layers of lead paint were common to all of the windows.
Beyond the condition of the existing windows, there were other factors that
influenced the types of window treatment considered. Increased energy efficiency
and aesthetics were two such considerations that were particularly important
with the structure’s function changing from primarily storage to office
use. While the level of conducted heat flow through the existing single glazed
units was previously acceptable, the new office use required greater climate
control. Additionally, the original units did not meet stringent state energy
code requirements. The conversion to office use, in which workers would be
in close proximity to the windows, also strengthened preferences that the
interior profiles remain clean and as accurate to the original configurations
as possible.
Repair Options
From the outset, serious consideration was given to repairing the majority
of the existing windows and upgrading the units for improved thermal
performance. Any repair program had to be accomplished in situ, as
the original window frames were embedded directly in the masonry surround
without an intermediary subframe. Their removal for repairs or to salvage
and substitute windows from one area of the building to another could
only be achieved by cutting the frames free from the anchors, a process
that would cause considerable damage.
If the windows were retained, energy efficiency could be increased by
either of two alternative treatments: reglazing with insulating glass
units, or installing interior storms. The former approach was quickly
discarded when the thickness of the original steel muntin sections proved
insufficient to support the added weight of new dual-paned glass units.
The second retrofitting option appeared more promising. To avoid obstructing
the muntin arrangement of the historic windows, the proposed interior
storm units had to be fashioned as single sheets extending from the
head to the sill of each steel window. Installation of a mock-up, however,
pointed out the limitations of the system. Because of the depth of
their
placement, the storm unit reflected the existing muntin pattern,
creating a visually confusing appearance of two distinct grids when seen
from
the outside. On paired and tripartite windows, the multiple storms
required 3-inch wide vertical mullions, which, although aligned with
the existing
mullions, were not desirable from an interior aesthetic perspective.
A mock-up of the applied
muntin system was fabricated utilizing available extrusions and was temporarily
installed in the Sears building. The flat
profiles of the stock extrusions did not, in this case, successfully
recreate the historic window appearance. Had the applied muntin approach
been adopted, it would have been possible to match the outside and
inside profiles of the original muntin and such details as the drip moldings
and grooves along the operable ventilators through the use of custom
extrusions. However, because of the importance of the windows to the
building’s historic character, it was determined that only a
true divided light solution would adequately reproduce the visual qualities
of the original windows.
Solution
In the search for appropriate replacement units, an aluminum window manufacturer
was contacted that had a track record of creating new systems for large
historic renovations. The company was charged by the development team
with providing an aluminum window that had true divided lights, matching
profiles and sight lines, and insulating glass. The replacement system
that was designed used a large number of new custom extrusions to replicate
the dimensions, profiles and sightlines of the original windows (see
figure 3). Individual insulated glass lights provided increased energy
efficiency while more accurately recreating the characteristic variations
of the original glass panes.
Existing historic windows in areas that were not to be continuously occupied,
such as common lobbies and fire stairwells, were retained and repaired
in situ. In addition, all of the tall windows on the second level (which
would be devoted to retail functions) were repaired and reglazed where
needed with historic glass salvaged from other locations in the building
(see figure 4).
Fabrication
A significant challenge to developing the Sears building replacement
window was matching the original narrow muntins. Common industry
practice for true divided light aluminum windows was to utilize wider
muntins
that conceal the spacer bar in the insulating glass unit and protect
the edge sealant from light degradation. This approach would significantly
encroach into the sightlines of the original windows as a result
of the wider muntin and proportion changes to the window. In the
case
of the Sears building, however, the window manufacturer utilized
a narrow spacer bar that permitted an accurate replication of the
original
7/8-inch muntin (see figure 5). Substituting a dark bronze anodize
finish for the conventional aluminum finish further reduced the visibility
of the spacer making it appear as a shadow line when viewed from
an angle.
Each replacement window developed for the Sears building was fabricated
from over forty new aluminum extrusions. The large variety of custom
designed elements allowed for a faithful reproduction of the original
profiles. At the request of the developer, the replacement windows were
not operable, yet their appearance suggested the functional nature of
the original projecting ventilators. Tabs were added to resemble the
weathering flange closed flush against the fixed outer frame, while drip
caps shielded simulated hinges. The muntin, rail, head, sill and jamb
profiles were also accurately reproduced. In order to replicate shadows
cast on the original frames, the manufacturer included cosmetic bolt
heads on the mullions running between each of the paired and tripartite
window arrangements.
The Inside Look
The inside appearance of the windows was important to the developer in
marketing the new office space. A similar effort was made, therefore,
to duplicate historic interior details and profiles. As was typical
of multi-story warehouses, the Sears building’s historic steel
windows were glazed on the inside so that the individual panes could
easily be replaced when broken. To simulate the original interior putty
profiles, the fixed-light muntins were tapered to the same 1/8-inch
thickness of the original sections while stepped muntins were used
in the central
vent where steel beads had originally secured the glazing. Jambs in
the replacement units were also beveled to recall the shape of the
old glazing putty (see figure 6).
Testing and Installation
Being a new window system, the manufacturer had independent firms conduct
standard performance tests on both the insulating glass and a mock-up
of the complete window. In accordance with ASTM guidelines, tests on
the complete window evaluated air infiltration, water resistance, and
deflection and structural deformation under uniform load. With the
test units meeting required specifications, window fabrication proceeded.
Lengths of the new spacer were shipped to a glass fabricator where
the insulating glass units were produced with a standard butyl and
silicone dual-seal. Completed glass units were then shipped to the
manufacturer for final assembly of each window.
While the new windows were being manufactured, a local contractor began
the three month long process of stripping, repairing, repainting and
reglazing the historic second floor windows and other retained units
in stairwells and other non-office locations. As the new windows began
to arrive in Boston, the general contractor removed the original units
that were slated for replacement and a team of eight to ten workers started
installing the new windows.
Evaluation
Decisions involving the treatment of the original Sears building
windows were reached after understanding the significance of
the windows’ historic
appearance and by evaluating their condition and the requirements imposed
by the rehabilitated building’s new function. Various proposals
were explored to determine how well they reconciled these factors.
The process suggested that the most appropriate solution was to retain
approximately
18% of the original windows while replacing the remainder with aluminum
true divided light units that carefully matched the originals in
both detail and general appearance (see figure 7).
The replacement window system used on floors three through eight
had two important advantages over earlier design proposals. First,
it did
not rely upon applied muntin grids that read less as individual glass “panes.” Second,
by developing new custom extrusions, the replacement window successfully
matched the dimensions and sightlines of the original muntins.
The design of the Sears building windows shows the degree to which aluminum
windows with insulating glass units can accurately replicate historic
windows. Attention to seemingly small details such as drip caps and the
interior appearance of the window proved crucial to the success of the
replication effort (see figures 8 and 9). This understanding led to a
new engineered window that met the challenge of combining narrow muntins
with insulating glass units and true divided lights.
Although there were many advantages to the window scheme developed for
the Sears building several drawbacks should also be acknowledged. One
of the most significant disadvantages was the loss of historic material
and integrity that accompanies any window replacement. In this case,
the loss included steel frames and glazing that were removed as well
as the functional nature of the once-operable projecting window.
While the replacement window frames are virtually indistinguishable from
the original frames, the uniform, factory-produced nature of the units
is in contrast to the look of historic steel windows that have aged over
time. Also, the true divided lights, though superior in appearance to
large insulating glass units with applied muntins, still have the reflective
quality of modern insulating glass.
A final concern, relevant to all dual-glazed replacement windows,
involved the integrity of the insulating glass unit seals. Although
the dual-seal
used in the Sears building replacement windows is currently state-of-the-art,
the lifespan of insulating glass units in general has varied widely
and is undoubtedly shorter than traditional monolithic glazing. The
combined
effects of the true divided light design and the narrow spacer bar
suggest that the Sears building windows be periodically inspected.
Small divided
lights significantly increase the perimeter area that is sealed—and
thus vulnerable to degradation—while the narrow spacer reduces
the amount of sealant that can be accommodated along that perimeter.
The glass fabricator is currently offering a ten-year limited warranty
for the window system.
Conclusion
The Sears project illustrates that a combined approach of both window
repair and replacement with a custom window designed to match the historic
unit is a viable alternative when large-scale building rehabilitation
is undertaken (see figure 10). Such a solution provides the opportunity
to retain significant historic fabric and a wholly authentic original
appearance in the most visible locations. In areas where the original
windows have experienced significant deterioration, are in less prominent
locations and where there are no suitable alternative means of enhancing
thermal performance, replacement windows that are intended to match the
originals in detail and appearance are acceptable. The window solution
developed for the Sears building acknowledges modern demands for both
a marketable aesthetic appearance and increased energy efficiency while
retaining the historic visual appearance of the structure. Already the
custom replacement window developed for the Sears building is being installed
on other historic buildings with comparable windows that are deteriorated
and in need of replacement.
PROJECT DATA:
Building:
Sears Roebuck and Company Mail Order Building
(Landmark Center)
309 Park Dr. & 201 Brookline Ave.
Boston, MA 02215
Owner:
The Abbey Corporation
Boston, Massachusetts
Project Date: 1996-2000
Project Architect:
Bruner/Cott and Associates, Inc.
Boston, Massachusetts
Restoration Consultant:
Leslie Donovan
Tremont Preservation Services
Boston, Massachusetts
Window Manufacturer:
Custom Window
Denver, Colorado
Window Contractor:
JK Glass
Boston, MA
Project Cost:
The project’s size and budget were sufficient to absorb the added
expense of developing the new window system and its numerous custom extrusions.
Engineering time and the cost of tooling and producing new extrusion
dies for the Sears project totaled approximately $25,000. As additional
$15,000 was spent on mockups and testing, bringing the development cost
to approximately $45 per frame in 1998 dollars.
The total expenditure for replacement window work including all development
costs, installation labor, perimeter caulking, dealer markup and the
890 window units themselves came to approximately $1.75 million, or $1,966
per window. This figure does not include expenses associated with removing
the original units. Repairing and repainting the two hundred windows
that were retained on the second floor and along the stairwells cost
an additional $158,000, or approximately $800 per unit. The overall rehabilitation
cost for the building was approximately $100 million.
THE PRESERVATION TECH NOTE was prepared by the National Park Service.
Charles E. Fisher, Heritage Preservation Services, National Park Service,
serves as the Technical Editor of the PRESERVATION TECH NOTES. Information
on the window work at the Sears Mail Order Building was generously
supplied by Leslie Donovan, Tremont Preservation Services; Henry Moss
and Simon Tempest, Bruner/Cott Architects; Edward Bartlett, Custom
Window Company; Jim Kfoury, JK Glass; and Alan Aulson, Aulson Company.
Thanks also go to Sharon Park and JoEllen Hensley of the National Park
Service’s Heritage Preservation Services for their review and
comments.
PRESERVATION TECH NOTES are designed to provide practical information
on traditional practices and innovative techniques for successfully maintaining
and preserving cultural resources. All techniques and practices described
herein conform to established National Park Service policies, procedures
and standards. This Tech Note was prepared pursuant to the National Historic
Preservation Act Amendments of 1980 which direct the Secretary of the
Interior to develop and make available to government agencies and individuals
information concerning professional methods and techniques for the preservation
of historic properties.
Comments on the usefulness of this information are welcomed and should
be addressed to PRESERVATION TECH NOTES, Technical Preservation Services,
National Center for Cultural Resources, National Park Service, 1849 C
Street, NW (2255), Washington, DC 20240.
ISSN: 0741-9023 - PTN 48
- November 2003
Introduction

Contents
|