Work Description First a survey of the bridge was conducted to ascertain which existing or non-historic materials would not be saved. These included extensively deteriorated historic materials as well as recent accretions. Dismantling of the bridge was conducted by experienced private contractors overseen by RIDOT. Materials that could not be saved were removed and discarded, including weight-limit signs, chain link fencing, asphalt paving, and the timber deck. Once this material was removed, the timber deck stringers and iron web braces could be dismantled. At this point a temporary bracing system was built to stabilize the trusses before construction work proceeded (see figure 5). This wooden system was extremely important--without it, the trusses might have twisted or overturned during the remaining disassembly work.
Figure 5. A temporary bracing system assured the protection of the bridge during disassembly. With the trusses stabilized, the deteriorated floorbeam hangers were removed. The floorbeams themselves were lifted, one at a time, by crane onto a flatbed truck, and transported to the shop. With the temporary bracing removed, the trusses were then attached to the crane and lifted in one piece, then placed on their sides on the truck (see figure 6). The plans had specified that the trusses be placed on the truck in an upright position, with protective bracing. But when the first truss was mistakenly laid on its side, the deteriorated lattice girder stiffener was severely bent. Fortunately, this lattice girder was slated for disposal before the damage occurred. The other truss was removed without damage.
Once at the shop, the bridge was completely
taken apart. All pins, beams, bars, nuts, and bolts were labeled
and inspected to determine their
structural condition (see figure 7). The parts were dismantled using
a variety of methods. Threaded parts were unscrewed; some rivets
had to be drilled out. Other parts were heated with a torch until they
expanded, then cooled; the resulting contraction allowed them to
be
removed. The bridge's pinned construction made disassembly easier,
as fewer pieces were actually riveted together.
The salvageable parts were placed in a Wheelbrator, a machine that removes rust through repeated vibration. The iron members were then sandblasted to remove paint and any remaining rust, then subjected to magnetic particle testing to determine which pieces had unseen damage or decay. The test was useful in determining wear in some of the parts, particularly the eyebars of the lower chord and the middle panel tension rods. In addition, some of the pins had worn by more than 1/4" over time. In order to reuse as much of the historic material as possible while ensuring sufficient structural integrity, it was decided to "build up" through welding those pieces that were worn down. In order to match the metallurgical composition of each part, a chemical test was undertaken. This testing allowed for an exact metallurgical match between the new built-up welds and the original metal of each part. Such a match reduced the possibility that a harmful physical or chemical reaction would take place between the weld and the wrought iron. Meanwhile, the endposts, lattice girder stiffeners, and vertical posts
were being fabricated from steel (see figure 8). The original end posts
had been constructed as a box section; one plate and two angle iron pieces
were riveted together to form
a column with one lattice side.
The final challenge lay in the floor beams. The new site was nine to ten feet narrower than the original site. To fit the new foundation, the bridge had to be reduced in width. This was done by cutting the ends of the floorbeams by four to five feet on each side. Fortunately, the cut was made near a vertical brace in the floorbeam, matching the original ends, which also terminated near a vertical brace. The lateral bracing attachment points were removed from the excess lengths and re-installed on the shorter floorbeams. New U-bolts of round stock (as opposed to the original square stock) were also fashioned. Once the built -up welds and fabrications were completed, the entire bridge was sprayed with an epoxy primer, followed by two coats of red iron oxide paint. Because none of the early paint remained, a compatible color was chosen in keeping with the bridge's historic character. The final problem was that the old bridge foundation at the new site was intended to support a shorter span. Since reducing the length of the span was not possible, a new foundation would need to be built for the relocated bridge. The old foundation of the bridge that once occupied the site was to be retained and preserved. First, cut granite blocks from the Providence River Relocation Project were obtained and transported to the new site. The new foundation was laid so that the bridge, as installed, would clear the old foundation by approximately one foot. When the new foundation was completed, the trusses were lifted by crane
to the site, installed in place, and secured with temporary wooden bracing
(see figure 9). The rest of the bridge (floor beams, hangers, stringers,
etc.) was then
|
Home | Search | E-mail | Technical Preservation Services | NPS History & Culture