04-09-22 Telecon
September 22, 2004
IMS/SDE Web Mapping Workgroup Teleconference
This teleconference was broken into thee 1Hr sub-group meetings:
Interface
- Did Not Meeting
- Next telecon Not scheduled
Applications
In attendance: IMRO Paul Voris, GRLA Ulf Gafvert, VAFO Jim VanOstenbridge, NR Lisa Nelson, NCSU Bill Slocumb, WASO David Duran
- Not much input to needs form
- Ulf - How do we get better input?
- GRLA's needs are in-house and consistent data
- Bill - Echo consistent data (DOQ, DRG)
- House data and serve from National level
- David - We need to use a consistentdeveopment interface. That way we can share resources and migrate all developmental efforts to share by all
- IMS has 2 modes and three different programming environments
- 2 Modes
- Image service - server generates an image and send to client
- Streaming feature serviec - send data constrained by extrent to client which renders image
- 3 main programming environments
- Java - Fat need to download code to client each time
- HTML (JS) - thinner but again download to client
- JSP/ASP/CF - thinnest, server side processing
- there is a 4th Webservices - mostly for data serving
- Also need to take into consideration OGC (Open GIS Consortium) efforts
- todo's
- Ulf to take crack at new form questions
- David - Send out ESRI Webservices info
- Time table Send by Oct 1 new questions, return and summerize Oct 11, discuss at next telecon
- Next telecon Ocrtober 19, same time (2PM Eastern, Noon Mtn, 11AM Pacific)
Data
In attendance: IMRO Paul Voris, NR Lisa Nelson, Dean Tucker, REDW Dave Best, WASO David Duran
- Discusson with Dean as to the status and availability of NHD to 12 digit HUC level
- Cont discussion with NPS Hydro and ArcHydro efforts
- Talked about what the goals of the first phase is (start work on a NPS deveolped GeoDB and use an existing GeoDB to start working with Versioning, checkin/out and the like)
- Next telecon October 19, same time (3PM Eastern, 1PM Mtn, Noon Pacific)
|