1.3 Accident Prevention & Blasting Safety Plans - Electronic Process (SharePoint)

Contracting Officer's Representative (COR) or Construction Management Representative (CMR)

  • Review plans concurrently.
  • NOTE: Government accepts or rejects plan, but does not approve.

DSC Safety Officer/DSC Blasting Officer

  • Review plan and document comments on the CM-SPE form (on the NPS/DSC SharePoint Project website).
  • Send e-mail alert to the COR.

COR

  • Add your comments to the CM-SPE form.
  • Based on the comments, select the appropriate accept or reject box.
  • Sign the CM-SPE form.
  • Process all resubmittals and supplements using the same process described above.

Guidelines:

Templates:

  • 1.3C CM-22 DSC Contractor Accident/Property Damage Report Form
    (Do not use park forms.)

Document Control:

  • Accepted plans are retained in contract file, with copy to CMR.