Contracting Officer's Representative (COR) or Construction Management Representative (CMR)
- Review plans concurrently.
- NOTE: Government accepts or rejects plan, but does not approve.
DSC Safety Officer/DSC Blasting Officer
- Review plan and document comments on the CM-SPE form (on the NPS/DSC SharePoint Project website).
- Send e-mail alert to the COR.
COR
- Add your comments to the CM-SPE form.
- Based on the comments, select the appropriate accept or reject box.
- Sign the CM-SPE form.
- Process all resubmittals and supplements using the same process described above.
Guidelines:
Templates:
- 1.3C CM-22 DSC Contractor Accident/Property Damage Report Form
(Do not use park forms.)
Document Control:
- Accepted plans are retained in contract file, with copy to CMR.