• Image of bluebells in the spring

    Cuyahoga Valley

    National Park Ohio

There are park alerts in effect.
show Alerts »
  • Canal Visitor Center Closure

    Canal Visitor Center will be closed for construction, starting Monday, May 6, 2013. It will reopen with new exhibits in early 2014.

  • Riverview Road Closure

    Riverview Rd from the Cuyahoga Falls line north to the Peninsula line will be re-paved, beginning the week of April 22. Expect delays. Flaggers will direct traffic. Final resurfacing and striping will take place following the Memorial Day holiday.

  • Bald Eagle Closure in Effect

    RR tracks, and 30 foot right of way on either side, are closed to all foot traffic from the Rt. 82 Bridge at Station Rd, north to the RR tracks at. The Cuyahoga R. downstream of the Brecksville Dam to the Fitzwater Rd Bridge is closed to water activities.

Krejci Dump Site Cleanup and Restoration

Read Our Brochure: Krejci Dump: A Story of Transformation

Recent Updates:

August 29, 2012
Rigorous goals set for soil remediation and final restoration actions are scheduled to begin.The excavation and removal of approximately 371,000 tons of contaminated soils and debris has been completed. The comprehensive post-excavation soil sampling effort establishes that remediation goals for the 46-acre former dump site have been met. The final steps necessary to restore the Site may now begin, including final grading; re-vegetation using native meadow grasses, forbs and shrubs; and restoration of 3 acres of wetland and wet meadow habitats. The NPS expects this work to be largely completed before the end of 2012.

July 1, 2011
As of May 2011, preliminary soils data show that 176 of 185 quarter-acre grids on the Site had achieved all Site Remediation Goals. Four of the remaining nine grids (all on the West Site) continued to exceed cleanup levels for dioxins and have been the subject of additional excavation and sampling in June. The five remaining grids are still being used for haul roads and a staging area and will be excavated and tested once the other grids are clean.

NPS anticipates that EQIS will re-mobilize in late June to conduct additional excavation in any of the four West Site grids that continue to have dioxin-contaminated soil. If soil sampling results support the conclusion that the contaminated soil has been removed from these grids, then it is anticipated that EQIS will re-mobilize to remove haul roads and excavate and sample in the five remaining grids on the West Site that have been used for haul roads and staging.

EQIS is developing plans for grading and revegetating the East Site. Once those plans are approved by NPS and all sampling results have been confirmed, EQIS will survey and begin grading the East Site, most likely in the fall of 2011. Plans for West Site grading and revegetation will begin as soon as all West Site grids achieve the cleanup levels. East and West Site revegetation may be complete by the spring of 2012.

Click here to read the archived updates.

Reports:
Krejci Dump Site Cleanup and Restoration Public Notification Policy

Krejci Dump Cleanup History and Planning (NPS/BOR)

Krejci Dump Cleanup Process by EQIS (the project contractor)(July 20, 2005)

Krejci Dump Remedial Action Work Plan to Address Village of Boston Heights Issues

FAQ about the Krejci Dump Site Cleanup

Project Documents:
Initial Roadside Baseline Sampling
Second Round of Roadside Sampling
Third Round of Roadside Sampling
Summary of All Roadside Reports
Fact Sheet

For More Information:
Contact Christopher Davis at (330) 342-0764 ext. 5, or e-mail us.

 
 

Did You Know?

Image of Civilian Conservation Corps statue outside Happy Days Visitor Center.

During the Great Depression, the "boys of Company 567" of the Civilian Conservation Corps helped shape the landscape that would later become Cuyahoga Valley National Park by constructing buildings, playfields, and a lake, as well as planting over 100 acres of trees.