TIME |
ACTIVITY
(Colored text indicates current study position. |

|
Winter 2001 |
Gather resource information |

|
April 2001 |
First public meetings - scoping |

|
Spring 2001 |
Develop themes |

|
Summer 2001 |
Develop draft Feasibility Study |

|
Mid-Summer 2001 |
Second public meetings - review study recommendations |
|
Winter 2002 |
Produce Special Resource Study and Feasibility Study |
|
Spring 2002 |
Distribute draft study to the public |

|
Summer 2002 |
Production and distribution of final study |

|
Summer 2002 |
Secretary of Interior transmits draft recommendations to Congress |