|
Chapter 4
Environmental Consequences
____________________________________________________________________________________________________________
Introduction
The National Environmental Policy Act (NEPA)
requires that environmental assessments disclose the environmental impacts
of a proposed federal action, reasonable alternatives to that action, and
any adverse environmental effects that cannot be avoided if the proposed
action is implemented. This chapter presents analyses of potential
environmental impacts on natural, cultural, and social resources. The
analyses provide the basis for comparing the effects of the three
alternatives described in Chapter 2.
Methodologies
The methodologies used to conduct the
environmental impact analyses are presented in this section. Methodologies
are provided for project impacts as well as for cumulative impacts and
impairment to park resources. Methodologies and assumptions common to all
resource topic areas are presented first, followed by methodologies
specific to individual resource topic areas.
Each resource topic includes a
discussion of the project impacts and the duration, intensity, and type of
each impact. These impact criteria are defined below.
- Duration – whether the impact would occur in the
short term (temporary) or the long term (permanent).
- Intensity – whether the impact would be negligible,
minor, moderate, or major.
- Type – whether the impact would be beneficial or
adverse to the natural, cultural, or social environment.
Impacts are also considered in the
context of whether they would be limited to the local setting or regional
setting (see Chapter 3). In this analysis, local setting impacts would be
those that occur within the Lower Yosemite Fall area. Regional impacts
(i.e., those that would occur within Yosemite Valley), when viewed in
combination with direct impacts of this project, are considered cumulative
impacts.
Natural Resources
Wetlands
The National Park Service is committed
to the protection of wetlands. The wetland protection statutes that guide
the National Park Service include Executive Order 11990, Protection of
Wetlands; Director’s Order #77-1 (see Appendix A for further
discussion), Wetland Protection, and its accompanying Procedural Manual
#77-1; Clean Water Act Section 404; and the "no net loss" goal
outlined by the White House Office on Environmental Policy in 1993.
Executive Order 11990 requires that leadership be provided by involved
agencies to minimize the destruction, loss, or degradation of wetlands.
The National Park Service’s Director’s Order #77-1 and Procedural
Manual #77-1 provide specific procedures for carrying out the Executive
Order.
Wetlands in the Lower Yosemite Fall area
were delineated and mapped in the field during the spring of 2001 to two
standards: Cowardin wetlands and jurisdictional wetlands. Cowardin
wetlands are used as the basis for analysis under National Park Service
Wetland Protection Guidelines. Jurisdictional wetlands are used as a basis
for analysis under Section 404 of the Clean Water Act. Wetland data were
compared to each alternative to determine the area that would potentially
be effected by the proposed project alternative. For wetlands, the area of
potential effect is areas identified as having Cowardin and jurisdictional
wetlands.
Duration of Impact.
A short-term impact is defined as lasting less than 20 years following the
implementation of an alternative. A long-term impact is defined as lasting
longer than 20 years after implementation of an alternative.
Intensity of Impact. Three
primary measures were used to evaluate the intensity of impacts on
wetlands: the size and type of the wetland, the integrity of the wetland,
and the connectivity of the wetland to adjacent habitats. The greater the
size of a wetland and the strength of its linkages with neighboring
ecological communities, the more valuable a wetland is for the integrity
and maintenance of biotic and abiotic processes. The intensity of impacts
has been described as negligible, minor, moderate, or major. Negligible
impacts would be imperceptible or not detectable. Minor impacts would be
slightly detectable, localized within a small area, and would not affect
the overall viability of wetlands in the park. Moderate impacts would be
apparent and have the potential to become major impacts. Major impacts
would be substantial, highly noticeable, and could be permanent.
Type of Impact. Adverse
impacts are those that would degrade the size, integrity, or connectivity
of wetlands. Conversely, beneficial impacts would enlarge or enhance the
size, integrity, and connectivity of wetlands.
Geology, Geologic Hazards, and Soils
The impact analysis for geology,
geologic hazards, and soils focused on effects that geologic processes in
Yosemite National Park would have on visitors, personnel, and facilities
under each project alternative. Geologic processes can negatively affect
visitors, personnel, and facilities when events such as rockfalls,
earthquakes, and severe soil instability result in injury, death, or
damage to facilities. The assessment also focused on effects the project
alternatives would have on geologic processes—specifically, the
formation and conservation of soil resources. Actions prescribed for the
Lower Yosemite Fall Project could affect soil resources through
accelerated erosion, soil loss, or soil removal.
Geologic risks that affect public safety
are rarely predictable, and the extent to which they may affect people and
property cannot be quantified. Analysis of effects was qualitative, and
professional judgment has been applied to reach reasonable conclusions as
to the context, duration, intensity, and type of potential impacts (see
the Yosemite Valley Geologic Hazard Guideline in Appendix C of the Final
Yosemite Valley Plan/SEIS).
Duration of Impact. Rockfall
hazards would likely be long-term and permanent. The potential for
rockfall is ongoing, as this natural process continues to occur in
Yosemite Valley. Short-term impacts on soils would be those that could be
restored when project construction is completed and are considered as
those lasting 20 years or less. Long-term impacts would be considered as
those lasting over 20 years.
Intensity of Impact. The
intensity of an impact was based on its location within the Valley. The
intensity of the impact would be negligible if facilities of any kind are
located outside geologic hazard zones. The intensity of the impact would
be considered a minor risk if standard occupancy and miscellaneous
facilities are within the rockfall shadow zone. The intensity of the
impact would be moderate if essential, hazardous, and special occupancy
facilities are within the rockfall shadow zone, or standard occupancy and
miscellaneous facilities are within the talus slope zone. The intensity of
the impact would be considered major if essential, hazardous, and special
occupancy facilities are within the talus slope zone. For soils, impact
intensities are related to soil type, history of disturbance, and scale of
measurability.
Type of Impact. All
rockfall events are potentially hazardous. The type of impact is related
to risk, and it is difficult to estimate risk involving natural events. In
general, reducing risk is considered a beneficial impact. The type of
impact would be considered beneficial if there would be a decrease in both
the density of individuals and facilities from the talus slope zone; this
includes moving them into the rockfall shadow zone, a zone of lower risk.
It would also be considered beneficial if there would be a decrease in
both the density of individuals and facilities from the rockfall shadow
zone. Beneficial impacts to soils would be those that contribute to
protecting or restoring natural soil conditions, including abiotic and
biotic components, soils structure, and moisture. Adverse impacts would
result in degradation of chemical, physical, abiotic, or biotic soil
components.
Generally, maintaining facilities within
or moving facilities into a zone of higher risk or exposing people to
greater levels of risk was considered adverse. Specifically, the type of
impact would be considered adverse if (1) essential and hazardous
occupancy facilities remain in or are placed in the talus slope and
rockfall shadow zones; or (2) special occupancy facilities remain or are
placed in the talus slope zone.
Hydrology and Water Quality
This analysis focused on how the action
alternatives (Alternatives 2 and 3), relative to the No Action
Alternative, would affect hydrologic processes during project construction
and operation. The hydrology impact assessment evaluates how construction
activities, particularly on trails and bridges, would affect channel
morphology, flooding, and water quality. Hydrology impacts were evaluated
in terms of their context, duration, and intensity, and whether the
impacts were considered to be beneficial or adverse.
The analysis examined potential changes
to channel morphology (channel depth, position, and streamflow) as a
result of actions in the alternatives. The analysis identified potential
effects on water quality associated with construction operations, such as
the location of construction staging areas near the braided stream channel
and use of heavy equipment during construction.
Duration of Impact. Short-term
impacts occur during the alternative’s implementation and are usually
less than 2 years in duration (e.g., construction projects). Long-term
impacts remain after the alternative has been implemented and are usually
longer than 2 years in duration. Since the full implementation of an
alternative would take place over a number of years, this section
frequently assesses the duration of individual actions of the alternative
(e.g., removal of a bridge) instead of full implementation of the
alternative.
Intensity of Impact. Negligible
impacts would be imperceptible or not detectable. Minor impacts would be
slightly perceptible and localized, without the potential to expand if
left alone. Moderate impacts would be apparent and have the potential to
become larger. Major impacts would be substantial, highly noticeable, and
may be permanent.
Type of Impact. Adverse
impacts alter natural hydrologic conditions (e.g., impede flood flows,
cause unnatural erosion or deposition, etc.) or degrade water quality
(e.g., increase pollution or bacteria levels from recreational use).
Beneficial impacts are those that restore natural hydrologic conditions
(e.g., remove impediments to flood flows, stabilize riverbanks, etc.) or
improve water quality (e.g., reduce non-point source pollution).
Floodplains
The analysis qualitatively analyzed the
health and safety impacts to persons as well as potential property damage
that would be caused by minor changes in the floodplain of the Merced
River and its tributaries, as well as structures within the floodplain.
The source of these minor changes includes the following: trail
alignments, bridge rehabilitation and construction, restroom demolition
and construction, and replacement of the parking area with either a
seating area or a picnic area.
Duration of Impact. Short-term
impacts (e.g., construction) would be those that occur over a period of
less than 1 year. Long-term impacts would be those occurring for more than
1 year. All the impacts evaluated would be considered long term. The risk
posed to construction personnel working in the floodplain (short term) was
considered too small to warrant evaluation.
Intensity of Impact. Beneficial
and adverse impacts of individual actions in each alternative were
assigned intensities as they relate to effects on life/safety and property
in the floodplain.
Definitions of impact intensities are
provided in table 4-1.
|
Table 4-1
Floodplain Impact Intensity Definitions |
|
Intensity |
Evaluation of Factors |
|
Presence of People in Floodplain |
Ease of Flood Evacuation |
Number of Structures in Floodplain |
Flooding Damage to Property |
|
Negligible |
Daytime only
(few to none) |
Easy |
Few to none |
No damage likely |
|
Minor |
Daytime only
(may be numerous) |
Easy |
Few |
Slight damage possible |
|
Moderate |
Overnight |
Easy |
Medium |
Severe damage possible |
|
Major |
Overnight |
Difficult |
Numerous |
Severe damage likely |
Type of Impact. In
the context of evaluating impacts of each alternative by evaluating risk
to human life and property, removing structures from the 100-year
floodplain was considered a beneficial impact to human life or property.
Development of new Class I or Class II actions (non-exempted facilities)
in the 100-year floodplain was considered an adverse impact to human life
or property.
Vegetation
Two primary parameters were used to
evaluate the intensity of impacts on vegetation: (1) the size and
continuity of the plant community, and (2) the natural structure,
productivity, diversity (integrity), and rarity of the plant community.
Other not-so-visible impacts (such as
encroachment of wetland habitats by non-native species) would continue to
be managed by the National Park Service in conjunction with National Park
Service programs involved in the protection and long-term management of
the park’s vegetative resources.
Duration of Impact. Long-term
impacts have been defined as those that can be detected for longer than 20
years. Short-term impacts have been defined as those lasting less than 20
years.
Intensity of Impact. Negligible
impacts would have no measurable or perceptible changes in plant community
size, integrity, or continuity. Minor impacts would be measurable or
perceptible and localized within a relatively small area. This means the
overall viability of the plant community would not be affected. Moderate
impacts would cause a change in the plant community (e.g., size,
integrity, and continuity); however, the impact would remain localized.
The change would be measurable and perceptible, but could be reversed.
Major impacts would be substantial, highly noticeable, and could be
permanent in their effect on plant community size, integrity, continuity,
productivity, and structure.
Type of Impact. Impacts
were classified as adverse if they would reduce the size, continuity, or
integrity of a plant community. Conversely, impacts were classified as
beneficial if they would increase the size, continuity, or integrity of a
plant community.
Wildlife
The effects that the alternatives would
have on wildlife and their habitat are addressed by considering the
effects of alternatives on wildlife habitat as represented by general
vegetation types. A description of how vegetation impacts would affect
wildlife is provided.
Impacts on wildlife have been assessed
in terms of changes in the amount and distribution of wildlife habitat,
the size and connectivity of habitat, the integrity of the site (including
past disturbance), the potential for habituation of wildlife to humans,
and the relative importance of habitats.
Duration of Impact. Long-term
impacts are defined as those lasting 20 years or longer. Short-term
impacts would be expected to last for less than 20 years. All short-term
impacts to wildlife and habitat from implementation of an alternative
would relate to construction activities and their immediate effects on
wildlife. These impacts would end with cessation of construction activity,
or soon thereafter, and include the following:
- Noise, dust, and light emanating from construction
sites could affect the use of surrounding habitats by wildlife.
- Vegetation removed, trampled, or run-over during
temporary use of some habitat as areas for staging of machinery or
materials would affect wildlife until such areas could be restored
after the project.
- Diversion of water flows during construction would
result in unnatural drying or wetting of habitats adjacent to sites.
- Wildlife could be injured or killed by traffic or
machinery associated with construction.
- Pits and trenches could entrap wildlife, resulting in
their death. Spills of fuel, oil, hydraulic fluid, antifreeze, and
other toxic chemicals could affect wildlife, especially those in
aquatic environments.
- Construction personnel, at in-park residences or at
work sites, could provide human food to wildlife, resulting in
conditioning of wildlife and human/wildlife conflicts.
Subsequent impact analyses focused
primarily on long-term effects of implementation of the alternatives.
Intensity of Impact. Negligible
impacts are impacts that would not be measurable or perceptible. Minor
impacts would be measurable or perceptible and would be localized within a
relatively small area; however, the overall viability of the resource
would not be affected. Without further impacts, negative effects would be
reversed, and the resource would recover. Moderate impacts would be
sufficient to cause a change in the resource (e.g., abundance,
distribution, quantity, or quality); however, the impact would remain
localized. The change would be measurable and perceptible, but negative
effects could be reversed. Major impacts would be substantial, highly
noticeable, and could be permanent.
Type of Impact. Impacts
were classified as adverse if they would negatively affect the size,
continuity, or integrity of wildlife habitat. Conversely, impacts were
classified as beneficial if they would positively affect the size,
continuity, or integrity of wildlife habitat.
Special-Status Species
The National Park Service compiled a
list of potential special-status species with potential habitat in the
Lower Yosemite Fall area from three main sources: (1) a list of federal
endangered and threatened species that may be affected, provided by the
U.S. Fish and Wildlife Service, (2) species listed under the California
Endangered Species Act or considered rare or sensitive by the California
Department of Fish and Game, and (3) park rare plant species identified by
the National Park Service. Almost 60 special-status species on this
compiled list were evaluated for presence or potential habitat within the
Lower Yosemite Fall area (see Appendix B). All species except bald eagle,
American peregrine falcon, Wawona riffle beetle, harlequin duck, and
special-status bats were found to be absent in the Lower Yosemite Fall
area, and are not subject to further analysis in this chapter.
Wildlife
The impact evaluation for special-status
wildlife species for each alternative was based on the following: (1) the
possibility of a species or its preferred habitat types occurring in areas
that may be affected, (2) the direct loss of habitat or individuals, (3)
the partial loss of habitat from its modification, and (4) the species’
sensitivity to disturbance from human activities that may cause it to
abandon currently occupied habitat or deter it from occupying suitable
habitat.
Vegetation
Impacts have been evaluated considering
species’ sensitivity to impacts (based on rarity, resilience, size of
population, and extent of species throughout the park); location of
species in proximity to new disturbance; and mitigation measures applied
as appropriate for the species and the site.
Duration of Impact. The
expected duration of impacts is described as long-term or short-term.
Long-term impacts are defined as those that would last 20 years or longer,
and short-term impacts are those that would last less than 20 years.
Intensity of Impact. The
intensity and magnitude of impacts on special-status vegetation and
wildlife species are described as negligible, minor, moderate, or major.
Negligible impacts would be imperceptible or not detectable. Minor impacts
would be slightly detectable, localized within a relatively small area,
and not affect the overall viability of resources in the park; without
further impacts, adverse effects would be reversed, and the resource would
recover. Moderate impacts would be sufficient to cause a change in the
resource (e.g., abundance, distribution, quantity, or quality), but would
remain localized; they would be readily apparent. Major impacts would be
substantial, highly noticeable, and affect larger areas.
Type of Impact. Impacts
were classified as adverse if they would negatively affect individuals of
federally listed species or the species population size, or habitat size,
continuity, or integrity. Conversely, impacts were classified as
beneficial if they would positively affect individuals of federally listed
species or species population size, or the size, continuity, or integrity
of habitat.
Air Quality
The air quality impact assessment
evaluates how construction activities would affect air pollutant emissions
and concentrations. Air quality impacts were evaluated in terms of their
duration, intensity, and type, and whether the impacts were considered to
be beneficial or adverse.
The air quality impact assessment
involved the identification and qualitative description of the types of
activities associated with the Lower Yosemite Fall Project that could
affect air quality. A qualitative assessment was performed to evaluate the
potential for higher pollutant emissions or concentrations, taking into
account the frequency, magnitude, duration, location, and reversibility of
the potential impact. In addition, regional pollutant sources and
transport issues were evaluated in the context of regional cumulative
impacts.
Duration of Impact. For
this analysis, short-term impacts would be associated with construction
and demolition activities that are temporary in nature, while vehicle
emissions were quantified for a 15-year (2000-2015) time period and
assumed to continue beyond 2015.
Intensity of Impact. The
intensity of an impact was assessed based on whether the impact is judged
to be negligible, minor, moderate, or major relative to Alternative 1. For
this analysis, impacts that would increase or decrease air emissions or
pollutant concentrations by 5% or less would be negligible; by 5% to 20%
would be minor; by 21% to 50% would be moderate; by more than 50% would be
major.
Type of Impact. Impacts
were considered to be beneficial or adverse to air quality. Beneficial air
quality impacts would reduce emissions or lower pollutant concentrations,
while adverse impacts would increase emissions or raise pollutant
concentrations.
Noise
The noise impact assessment involved the
identification and description of the types of actions that could affect
the ambient noise environment, corresponding noise sources, relative
source strengths, and other characteristics. Based on the relative source
strengths, a qualitative assessment was performed to evaluate the
potential for a substantial increase in ambient noise levels. Assessments
were also performed where noise-sensitive uses are located or would expose
persons to excessive noise levels, taking into account the frequency,
magnitude, duration, location, and reversibility of the potential impact.
Duration of Impact. Long-term
impacts have a permanent effect on the ambient noise environment (visitor
and operational activity). Short-term impacts are temporary in duration
and would be associated with transitional types of impacts (construction
activity is usually a short-term impact).
Intensity of Impact. Negligible
impacts would not be detectable. Minor impacts would be slightly
detectable in proximity to the source, but would not be expected to have
an appreciable effect on ambient noise levels. Moderate impacts would be
clearly detectable and could have an appreciable effect on ambient noise
levels; moderate adverse impacts may include introduction of noise
associated with an activity or facility into an area with little or no
ambient noise. Major impacts would be clearly audible against ambient
noise levels, or would have a substantial, highly noticeable effect on
ambient noise levels.
Type of Impact. Beneficial
impacts are those impacts that would result in less noise, and adverse
impacts are those impacts that
would result in more noise.
Cultural Resources
This impact analysis methodology applies
to three basic types of cultural resources: archeological sites,
ethnographic resources, and cultural landscape resources (including
individually significant historic structures).
Cultural resource impacts in this
document are described in terminology consistent with the regulations of
the Council on Environmental Quality, and in compliance with the
requirements of both the National Environmental Policy Act and Section 106
of the National Historic Preservation Act.
The National Historic Preservation Act
requires determinations of no effect or effect, and where there would be
an effect, a determination as to whether that effect would be adverse or
not adverse. Archeological resources are typically considered eligible for
inclusion in the National Register of Historic Places because of the
information they have or may be likely to yield. Intensity of impacts to
archeological resources relates to the importance of the information they
contain and the extent of disturbance or degradation.
Council on Environmental Quality
regulations call for a discussion of the "appropriateness" of
mitigation, and Director’s Order 12 (Conservation Planning,
Environmental Impact Analysis and Decision-Making; see Appendix A for
further discussion) requires an analysis of the "effect" of
mitigation. The reduction in intensity that would result from mitigation
is an estimate of the effectiveness of mitigation under NEPA. It does not
suggest that the level of effect as determined by Section 106 would be
similarly reduced. Although adverse effects under Section 106 may be
mitigated, the effect would remain adverse.
Mitigation for NEPA purposes in this
environmental assessment is based on the park’s 1999 Programmatic
Agreement and includes avoidance of adverse effects or application of one
or more standard mitigation measures, described in stipulation VIII(A) of
this agreement. According to stipulation VII(C) of the 1999 Programmatic
Agreement, impacts to archeological resources are considered not adverse
for purposes of Section 106 of the National Historic Preservation Act if
data recovery is carried out in accordance with the 1999 research design.
Under the revised regulations of the Advisory Council on Historic
Preservation of May 18, 1999 (36 Code of Federal Regulations [CFR] 800,
Protection of Historic Properties, Final Rule and Notice), data recovery
is considered to be an adverse effect. However, according to Part
800.3(A)(2) of those revised regulations, provisions of programmatic
agreements in existence at the effective date of the new regulations
remain in effect. Therefore, archeological data recovery excavations are
not considered adverse effects.
Section 106 Summary. Under
regulations of the Advisory Council on Historic Preservation (36 CFR
800.9) addressing the criteria of effect and adverse effect, actions
proposed under the action alternatives would have the potential to
adversely affect significant historic properties. Ethnographic resources
would be disturbed or destroyed by construction occurring in traditional
plant-gathering areas, historic village sites, and/or places holding
special sacred and spiritual significance to American Indians. Historic
sites, structures, districts, and cultural landscape features would also
be adversely affected by undertakings entailing substantial facility
alteration or removal, or the introduction of modern non-contributing
development within or in proximity to historic districts and sensitive
landscape areas. To mitigate adverse effects, the park would utilize
compatible design principles, carry out Historic Architectural Building
Survey/Historic Architectural and Engineering Record documentation,
salvage historic materials, develop cooperative agreement provisions for
traditional plant gathering, or other suitable mitigation in accordance
with the Programmatic Agreement.
Many archeological resources having
varied potential to yield prehistoric and historic information would be
affected by ground-disturbing activities. To avoid adverse effects to
archeological resources, the park would carry out data recovery to
retrieve important information, in accordance with the Programmatic
Agreement.
The restoration of vegetation
contributing to historic settings and the cultural landscape, and the
removal of non-contributing structures and landscape elements also would
have no adverse effect on historic properties. Rehabilitation would be
carried out in accordance with the Secretary of the Interior’s
Standards and Guidelines for Archeology and Historic Preservation (USDOI
1983).
For project areas lacking sufficient
cultural resource data or design information to adequately assess effects,
the park would carry out inventories, evaluate identified resources for
national register significance, consult according to the stipulations of
the Programmatic Agreement, and recommend avoidance or appropriate
treatment/standard mitigation measures prior to construction disturbance.
Archeological Resources
Duration of Impact. Impacts
to archeological resources could be of short-term, long-term, or permanent
duration.
Type of Impact. Any
change in the physical attributes of an archeological site is irreparable
and considered adverse and of permanent duration. Adverse impacts to
archeological resources most often occur as a result of earthmoving
activities within an archeological site area, soil compaction or increased
erosion, unauthorized surface collection, or vandalism. Beneficial impacts
to archeological resources can occur when patterns of visitor use or
management action are changed in the vicinity of archeological resources
such that an ongoing impact, which would otherwise continue to degrade
archeological resources, is reduced or arrested.
Intensity of Impact. The
intensity of impact to an archeological resource would depend upon the
potential of the resource to yield important information, as well as the
extent of the physical disturbance or degradation. For example, major
earthmoving at an archeological site with low data potential might result
in a minor, adverse impact. Negligible impacts would be barely perceptible
and not measurable, and would usually be confined to archeological sites
with low data potential. Minor impacts would be perceptible and
measurable, and would remain localized and confined to archeological
site(s) with low to moderate data potential. Moderate impacts would be
sufficient to cause a noticeable change, and would generally involve one
or more archeological sites with moderate to high data potential. Major
impacts would result in substantial and highly noticeable changes,
involving archeological site(s) with high data potential.
Ethnographic Resources
Duration of Impact. Impacts
are considered short term if they represent a temporary change in
important vegetation or temporarily restrict access to an important
resource, and do not disrupt the cultural traditions associated with that
resource for a noticeable period of time. They are considered long term if
they involve a change in important vegetation or cultural feature, or
addition of a new facility or visitor use that would change the physical
character of or access to a resource for a noticeable period of time. This
period of time would vary by resource type and traditional practitioners.
These long-term changes would disrupt cultural tradition(s) associated
with the affected resource, but the disruption would not alter traditional
activities to the extent that the important cultural traditions associated
with the resource are lost. Permanent impacts to ethnographic resources
would involve irreversible changes in important resources such that the
ongoing cultural traditions associated with those resources are lost.
Type of Impact. Impacts
to ethnographic resources occur as a result of changes in the physical
characteristics, access to, or use of resources, such that the cultural
traditions associated with those resources are changed or lost. Beneficial
impacts can occur when intrusive facilities, or visitor or management
activities are removed from a traditional use area; when ecological
conditions are improved at a gathering area such that the traditionally
used resource is enhanced; or when access for American Indian people is
enhanced. Adverse impacts occur when physical changes to a traditionally
used resource or its setting degrade the resource itself, or degrade
access to or use of a resource.
Intensity of Impact. The
intensity of impacts to an ethnographic resource would depend on the
importance of the resource to an ongoing cultural tradition, as well as
the extent of physical damage or change. Negligible impacts would be
barely perceptible and not measurable, and would be confined to a small
area or single contributing element of a larger National Register district
(such as the ethnographic landscape in Yosemite Valley). Minor impacts
would be perceptible and measurable, and would remain localized and
confined to a single contributing element of a larger National Register
district. Moderate impacts would be sufficient to cause a change in a
significant characteristic of a National Register district or property,
and/or would generally involve a small group of contributing elements in a
larger National Register district. Major impacts would result in
substantial and highly noticeable changes in significant characteristics
of a National Register district or property, and/or would involve a large
group of contributing elements in a larger National Register district
and/or an individually significant property.
Cultural Landscape Resources, Including Individually
Significant Historic Sites and Structures
Duration of Impact. Impacts
to cultural landscape resources are considered short term if they involve
activities such as temporary removal of vegetation or other contributing
resources, road closures, or prescribed burns, where the impacts are
noticeable for a period of from 1 to 5 years. Other examples of short-term
impacts to historic structures include constructing scaffolding
surrounding a building during rehabilitation work, or minor deterioration
in historic fabric that is repairable as part of routine maintenance and
upkeep. Impacts are considered long term if they involve a reversible
change, lasting from 5 to 20 years, in a significant characteristic of a
historic structure or landscape. Permanent impacts to a historic structure
or landscape resources would include irreversible changes in significant
characteristics, such as removal of contributing resources; restoration of
natural systems and features; irreversible removal of historic fabric that
changes the historic character of a property; or demolition of a historic
structure.
Type of Impact. Impacts
to cultural landscape resources result from physical changes to
significant characteristics of a resource or its setting. Beneficial
impacts can occur as a result of restoration or rehabilitation of
resources, or removal of incompatible or noncontributing facilities.
Adverse impacts generally occur as a result of modifying a significant
characteristic of a historic structure or landscape resource; removal of a
significant structure or landscape resource; or addition of new,
incompatible facilities in proximity to a historic site or structure.
Intensity of Impact. Negligible
impacts would be barely perceptible and not measurable and would be
confined to small areas or a single contributing element of a larger
National Register district. Minor impacts would be perceptible and
measurable but remain localized and confined to a single contributing
element of a larger National Register district. Moderate impacts would be
sufficient to cause a change in a significant characteristic of an
individually significant historic structure, or would generally involve a
single or small group of contributing elements in a larger National
Register district. Major impacts would result from substantial and highly
noticeable changes in significant characteristics of an individually
significant historic structure, or would involve a large group of
contributing elements in a National Register district.
Social Resources
Scenic Resources
The overriding management purpose of any
national park, as defined by the National Park Service 1916 Organic Act,
is to conserve the scenery and natural and historic objects. Following
this direction, the National Park Service evaluated impacts on scenic
resources by examining the potential effects of the Lower Yosemite Fall
Project on the landscape character and/or features.
Impacts of the Lower Yosemite Fall
Project on visual resources were examined and assessed by comparing the
existing visual character of the landscape components and features and the
degree to which actions that may result from the Lower Yosemite Fall
Project would affect (i.e., contrast or conform with) these components and
features.
Potential impacts to scenic resources
consist of substantial changes that would alter (1) existing landscape
character, whether foreground, intermediate ground, or background, and
would be visible from viewing areas the National Park Service has
established as important or (2) access to historically important viewing
areas.
Duration of Impact. The
duration of the impacts considers whether the impact would be short-term
or long-term. A short-term impact would be short-lived or temporary due to
construction, restoration, or demolition activities, and a long-term
impact would be permanent and continual.
Intensity of Impact. The
magnitude of impacts to the scenery within the view from specific vantage
points and to specific scenic features is described as negligible, minor,
moderate, or major depending upon their comparison to scenic categories
presented in table 3-14 of the Yosemite Valley Plan (Vol. Ia,
Chapter 3, page 3-69), and as described below.
- Negligible impacts would be imperceptible or not
detectable.
- For the A Scenic category, minor impacts would be
slightly detectable or localized within a relatively small area. For
the B Scenic category, minor impacts would be slightly detectable,
localized within a relatively small area, or readily apparent.
- For the A Scenic category, moderate impacts would be
those that are readily apparent. For the B Scenic category, moderate
impacts would be substantial, highly noticeable, and/or result in
changing the character of the landscape.
- For the A Scenic category, major impacts would be
substantial, highly noticeable, and/or result in changing the
character of the landscape. For the B Scenic category, major impacts
would be substantial, highly noticeable, and/or result in changing the
character of the landscape by adding human-made features to a mostly
undisturbed area or by removing most human-made features from a
developed area.
Analysis of impacts to the Merced Wild
and Scenic River’s scenic Outstandingly Remarkable Values can be found
in Chapter 5 of this environmental assessment.
Type of Impact. All
actions proposed in each alternative were analyzed using a geographic
information system to evaluate the net change in each of the scenic
categories (A, B, and C). This approach assesses the acreage of scenic
categories A, B, and C that would be improved by the removal of
development and restoration to natural communities, or affected by new
development. Impacts were considered beneficial if they would decrease the
number of acres disturbed within A and B Scenic resource categories, and
considered adverse if actions within each alternative would increase the
number of human-caused visual intrusions in these categories. Impacts were
also considered beneficial if the quality of the visual experience would
be improved, and adverse if the visual quality would be degraded. No C
Scenic resources would be altered by any of the alternatives.
Visitor Experience
Impacts on visitor experience may occur
as a result of changes to road circulation, interpretation facilities,
trails, and other facilities and resources that contribute to the type and
quality of the visit to Yosemite National Park. Impacts may also occur
from direct actions, thereby altering the availability of a specific
experience or activity.
Visitor experience is also directly
affected by actions influencing natural resources such as air quality,
scenic resources, and cultural resources. Though impacts to these
resources are not repeated in the analysis of visitor experience,
enhancement or degradation of these resources also enhances or degrades
the quality of the visitor experience.
Impacts on visitor experience have been
assessed using professional judgment to develop a qualitative analysis of
the effects of actions to the Lower Yosemite Fall area. These conclusions
have been considered in combination with data on the proportion, when
known, of visitors who participate in different activities while in the
park. Anticipated changes in visitor participation would represent an
effect.
Duration of Impact. A
short-term impact on visitor experiences would be temporary in duration
because construction, restoration, or demolition activities would be
temporary. A long-term impact would have a permanent effect on the visitor
experience.
Intensity of Impact. The
intensity of impacts are defined as negligible, minor, moderate, and
major. Negligible impacts would result in little noticeable change in
visitor experience. Minor impacts would result in changes in desired
experiences but without appreciably limiting or enhancing critical
characteristics. (Critical characteristics are those elements of a
recreational activity that are most important to those who pursue it; for
example, it may be important to picnickers to be able to drive to a picnic
site.) Moderate impacts would change the desired experience appreciably,
(i.e., changes one or more critical characteristics, or appreciably
reduces/increases number of participants). Major impacts would eliminate
or greatly enhance multiple critical characteristics or greatly
reduce/increase participation.
Type of Impact. Impacts
were evaluated in terms of whether they would be beneficial or adverse to
visitor experience. Beneficial impacts would enhance visitor
participation, quality of visitor experience, and service level. Adverse
impacts would be effects that reduce visitor participation, quality of
visitor experience, and service level.
Park Operations and Facilities
For purposes of this analysis, an
alternative is assumed to have an impact (adverse or beneficial) on park
operations and facilities if it would:
- Result in direct changes to park operations,
facilities, or staffing requirements or policies associated with park
operations.
- Cause indirect effects on park operations,
facilities, or staffing, such as effects on utility and roadway
infrastructure, flooding, and impacts on provision of utilities,
especially potable water and sewer services.
Duration of Impact. Short-term
impacts would last only until all action items are completed. Long-term
impacts would have a permanent effect on operations.
Intensity of Impact. With
negligible impacts, there would not be a measurable difference in staffing
compared to existing requirements. With minor impacts, measurable
additions or reductions in staffing would be less than 15% of existing
requirements. With moderate impacts, additions or reductions in staffing
would be between 15% and 30% of existing requirements. With major impacts,
additions or reductions in staffing would exceed 30% of existing
requirements.
Type of Impact. Adverse
impacts represent an increase in staffing requirements. Beneficial impacts
represent a decrease in staffing requirements.
Recreation
Yosemite National Park offers a broad
spectrum of recreational opportunities. In addition, every visitor to
Yosemite brings unique expectations, and thus each has a unique
experience. The environmental assessment identifies, where possible, how
the opportunity for recreation would change as a result of the Lower
Yosemite Fall Project.
Duration of Impact. A
short-term impact on visitor experiences would be temporary in duration
and result from construction, restoration, or demolition activities. A
long-term impact would have a permanent effect on the visitor experience.
Intensity of Impact. The
intensity of impacts are defined as negligible, minor, moderate, and
major. Negligible impacts would result in little noticeable change in
recreational opportunities. Minor impacts would result in changes in
desired recreational opportunities but without appreciably limiting or
enhancing critical characteristics. (Critical characteristics are those
elements of a recreational activity that are most important to those who
pursue it; for example, it may be important to picnickers to be able to
drive to a picnic site.) Moderate impacts would change the desired
recreational opportunity appreciably (i.e., changes one or more critical
characteristics, or appreciably reduces/increases number of participants).
Major impacts would eliminate or greatly enhance multiple critical
characteristics or greatly reduce/increase participation.
Size of user groups was defined based on
a percentage of visitors who participate in a recreational activity in
Yosemite Valley:
- Small; less than 1% of visitors, unless Yosemite
Valley is a principal destination for this activity that cannot be
replaced at other destinations, which moves user group to moderate.
- Moderate; 1% to 5% of visitors
- Moderately large; 6% to 19% of visitors
- Large; 20% to 49% of visitors
- Majority; 50% to 74% of visitors
- Most; 75% or more of visitors to Yosemite Valley.
Type of Impact. Impacts
were evaluated in terms of whether they would be beneficial or adverse to
recreation. Beneficial impacts would enhance recreational participation,
quality or recreational opportunity. Adverse impacts would be effects that
reduce recreational participation, quality of recreational opportunity,
and service level.
Transportation
To evaluate the changes in traffic
volumes that would be generated by additional internal bus circulation,
internal bus circulation volumes were compared qualitatively with traffic
volumes under the No Action Alternative in the Yosemite Valley Plan (see
Vol. Ib, pages 4.0-39 and 4.0-40). Internal bus circulation volumes were
also compared to the level of service analysis for roadway segments and
intersections considered in the Yosemite Valley Plan (see Vol. Ib,
page 4.0-41).
Duration of Impact.
Short-term impacts would last less than 5 years and would be created
during the implementation phase of the alternative actions. A long-term
impact would be a permanent change in visitor circulation following the
implementation of an action.
Intensity of Impact. The
range of impact intensities for bus volumes on Valley roadways is listed
below:
- With a negligible impact, there would be no
measurable or perceptible change in the number of bus trips or bus
vehicle miles traveled on Valley roadways.
- With a minor impact, the change in the number of bus
trips or bus vehicle miles traveled on Valley roads would be less than
25%.
- With a moderate impact, the change in the number of
bus trips or bus vehicle miles traveled on Valley roads would be
between 26% and 75%.
- With a major impact, the change in the number of bus
trip or bus vehicles miles traveled on Valley roads would be greater
than 75%.
These ranges are higher than the ranges
of impact intensity defined for all vehicle miles of travel.
Type of Impact. Changes
in the number of bus trips or bus vehicle miles traveled cannot be
characterized as beneficial or
adverse from a transportation perspective.
Energy Consumption
Gasoline and diesel are the primary
fuels consumed by automobiles, trucks, and buses used in the Yosemite
Valley. A California Air Resources Board model (called BURDEN) was used to
estimate motor fuel consumption associated with proposed plans, employee
commuting patterns, and utilization of National Park Service and
concessioner vehicles that operate in the Valley. Annual fuel consumption
for heavy trucks, urban buses, and shuttle buses was derived from
vehicle-miles-traveled estimates and typical fuel economy values for these
vehicle types.
Duration of Impact. The
duration of the impact considers whether the impact would occur in the
short term or long term. Generally, short-term impacts are temporary in
nature, whereas long-term impacts would have a continuing effect on energy
consumption. For this analysis, vehicle emissions were quantified for the
15-year (2000-2015) time period and are assumed to continue beyond 2015.
Intensity of Impact. The
intensity of an impact was assigned based on whether the impact is judged
to be negligible, minor, moderate, or major relative to Alternative 1. For
this analysis, impacts that would increase or decrease energy consumption
by 5% or less annually would be negligible; by 5% to 20% annually would be
minor; by 21% to 50% annually would be moderate; and by more than 50%
annually would be major.
Type of Impact. Impacts
were considered to be either beneficial or adverse with respect to energy
consumption. Beneficial energy impacts would reduce energy consumption,
whereas adverse impacts would increase energy consumption.
Cumulative Impacts
A cumulative impact is described in
regulations developed by the Council on Environmental Quality, Regulation
1508. 7, as follows:
A "cumulative impact" is
the impact on the environment which results from the incremental
impact of the action when added to other past, present, and reasonably
foreseeable future actions regardless of what agency (Federal or
non-Federal) or person undertakes such other actions. Cumulative
impacts can result from individually minor but collectively
significant actions taking place over a period of time.
For the purpose of this environmental
assessment, a list of projects within Yosemite Valley was identified so
that potential cumulative impacts from the Lower Yosemite Fall Project could
be evaluated in the context of these other projects. Appendix C contains
the list of cumulative projects included in the cumulative impact
analysis. The other Yosemite Valley projects identified included past
actions, as well as any planning or development activity currently being
implemented or planned for implementation in the reasonably foreseeable
future.
These cumulative actions are evaluated
in the impact analysis in conjunction with potential impacts of each
proposed project alternative to evaluate whether there may be additive
effects on a particular natural, cultural, or social resource. Because
most of the other projects included in the cumulative analysis are in the
early planning stages, the evaluation of cumulative impacts was based on a
general description of each project considered.
Impairment
Pursuant to the 1916 Organic Act, the
National Park Service has a management responsibility "to conserve
the scenery and the natural and historic objects and the wildlife therein
and to provide for the enjoyment of the same in such manner and by such
means as will leave them unimpaired for the enjoyment of future
generations." Therefore, the National Park Service cannot take an
action that would "impair" park resources. The National Park
Service Management Policies (NPS 2001a) provides guidance on
addressing impairment.
Impairment is an impact that, in the
professional judgment of the responsible National Park Service manager,
would harm the integrity of park resources or values, including
opportunities that otherwise would be present for the enjoyment of those
resources or values. An impact would be less likely to constitute an
impairment to the extent that it is an unavoidable result from an action
necessary to preserve or restore the integrity of park resources or values
(NPS 2001a). An impact would be more likely to constitute impairment to
the extent that it affects a resource or value whose conservation is:
- Necessary to fulfill specific purposes identified in
the establishing legislation or proclamation of the park.
- Key to the natural or cultural integrity of the park
or to opportunities for enjoyment of the park.
- Identified as a goal in the park’s General
Management Plan or other relevant National Park Service planning
documents.
Impairment of park resources was
evaluated on the basis of the type and intensity of impact and in terms of
the types of resources affected. In general, beneficial impacts do not
constitute impairment. With respect to the intensity of impacts,
negligible and minor adverse impacts are not of sufficient magnitude to
constitute impairment. Moderate and major adverse impacts may constitute
impairment, but do not automatically do so. Rather, these impacts must be
analyzed with respect to the three bulleted criteria above.
The National Park Service Director’s
Order #12 (Conservation Planning, Environmental Impact Analysis, and
Decision-Making) requires that impairment be addressed in all
environmental assessments and draft and final environmental impact
statements, as well as in the decision documents (for example, Finding of
No Significant Impact or Record of Decision).
Analysis of Environmental Consequences
The analysis section includes direct and
indirect effects for each resource topic, an analysis of cumulative
impacts, and impairment of park resources for all alternatives.
Natural Resources
Wetlands
Alternative 1
Analysis – Local Setting
- Restroom Location. The
existing restroom would continue to be located in its current location,
which is not within or near any existing jurisdictional or Cowardin
wetlands.
- Parking Area.
The existing
parking area would continue in its current location, which is not near any
existing jurisdictional or Cowardin wetlands.
- Shuttle Bus Stop.
The shuttle
bus stop would continue in its current location, which is not located near
any existing jurisdictional or Cowardin wetlands. A new shuttle bus stop
would not be provided.
- Tour Bus Unloading, Loading, and Parking.
The
tour buses that park in the existing parking area would continue to not
impact existing jurisdictional or Cowardin wetlands.
- Trail Alignment.
Under
Alternative 1, human use and trampling in wetland areas where trails are
not well defined may continue to degrade existing jurisdictional or
Cowardin wetlands in the Lower Yosemite Fall area.
- Rehabilitation of Trails.
Under
Alternative 1, human use and trampling in wetland areas where trails are
not well defined may continue to degrade existing jurisdictional or
Cowardin wetlands in the Lower Yosemite Fall area.
- Rehabilitation, Relocation, and Installation of
Bridges.
All bridges in the Lower Yosemite
Fall area have abutments within creek channels classified as Cowardin
wetlands. In addition, the abutments of Bridge #5 are located in a
jurisdictional wetland. Hydrologic flows that support wetlands would
continue to be diverted and constricted by these bridge abutments.
- View Corridor Maintenance.
No trees or vegetation would be removed to maintain view corridors;
therefore, no jurisdictional or Cowardin wetlands would be affected.
- Removal of Human-Built Rock-Rubble Pile.
The
rock-rubble pile would continue in its present location; it would not
affect identified jurisdictional or Cowardin wetlands.
Overall, there would be a long-term,
minor, adverse impact on wetlands under Alternative 1 resulting from human
use and trampling in areas where trails are not well defined as well as
from bridge abutments (located within creek channels) that could alter
hydrologic flows that support wetlands.
Cumulative Impacts – Regional Setting
Throughout Yosemite Valley, a net gain
of approximately 118 acres of wetland would take place under the adopted Yosemite
Valley Plan. About 141 acres of wetlands would be restored, 12 acres
of new development in wetlands would take place, and 11 acres of
redevelopment in degraded wetlands could take place. Overall, regardless
of the continuing impacts to wetlands in the local setting, there would be
a long-term, major, beneficial impact on the size of wetlands in Yosemite
Valley.
Impairment
Wetland impacts resulting from
Alternative 1 would not be of sufficient magnitude to constitute
impairment.
Alternative 2
Analysis – Local Setting
- Restroom Relocation. Long-term,
negligible, beneficial impact. The new restroom would be located in
the southeast portion of the area currently occupied by the parking lot.
This area is not within or near any identified jurisdictional or Cowardin
wetlands.
- Parking Area Removal and Establishment of
Seating/Picnic Area.
Long-term, negligible,
beneficial impact. Project activities would not occur within or near
any identified jurisdictional or Cowardin wetlands.
- New Shuttle Bus Stop.
Long-term,
negligible, beneficial impact. The new shuttle bus stop would not be
placed within or near any identified jurisdictional or Cowardin wetlands.
- Interim Tour Bus Unloading, Loading, and Parking.
Short-term,
negligible, beneficial impact. Tour bus unloading, loading, and
parking would not occur within or near any identified jurisdictional or
Cowardin wetlands.
- Trail Alignment.
Long-term,
negligible, beneficial impact. None of the trail alignments would
occur within any identified jurisdictional or Cowardin wetlands.
- Rehabilitation of Trails.
Long-term,
minor, beneficial impact. Trail rehabilitation activities would not
occur within any identified Cowardin wetlands. These impacts would be
slightly detectable and localized throughout the local setting.
- Rehabilitation, Relocation, and Installation of
Bridges.
Long-term, minor, beneficial
impact. Proposed reconstruction of Bridge #5 would completely span the
identified jurisdictional wetland in this area. Negligible amounts of fill
would be placed within the Cowardin wetlands at Bridge #3 and Bridge #6
due to the placement of bridge piers. All bridge abutments would be
removed from the stream channel to upland areas. Overall, hydrologic flows
under the rehabilitated bridges would improve wetland conditions,
resulting in local, long-term, minor, beneficial impacts. The two piers at
the Yosemite Falls Bridge would be replaced in the same location and
result in no new wetland impact. Under Alternative 2, the hydrologic flows
and wetland conditions would be improved.
- View Corridor Maintenance.
Long-term,
negligible, adverse impact. Selected vegetation would be
removed in view corridors; however, wetland plant species would be avoided
to the extent possible.
- Removal of Human-Built Rock-Rubble Pile.
Long-term,
negligible, beneficial impact. The rock-rubble pile removal would be
preceded by studies on wetlands, hydrology, and cultural resources, and
appropriate public health and safety measures would be applied.
Overall, there would be a long-term,
minor, beneficial impact on wetlands due to the removal of bridge
abutments from creek channels.
Cumulative Impacts – Regional Setting
Cumulative impacts on wetlands are
described previously in this chapter for Alternative 1.
Alternative 2 would result in long-term, minor, beneficial impacts to
wetlands, which in combination with cumulative actions, would contribute
to a long-term, major, beneficial cumulative impact on the size and
condition of wetlands in the Yosemite Valley.
Impairment
Wetland impacts resulting from
Alternative 2 would not be of sufficient magnitude to constitute
impairment.
Alternative 3
Analysis – Local Setting
- Restroom Relocation. Long-term,
negligible, beneficial impact. The new restroom would be located in an
area adjacent to the trail leading from Northside Drive to Bridge #6. This
area is not within or near any identified Cowardin or jurisdictional
wetlands.
- Parking Area Removal and Establishment of an Informal
Seating Area.
Long-term, negligible,
beneficial impact. Project activities would not occur within or near
any identified Cowardin or jurisdictional wetlands.
- New Shuttle Bus Stop.
Long-term,
negligible, beneficial impact. The new shuttle bus stop would not be
placed within or near any identified Cowardin wetlands.
- Interim Tour Bus Unloading, Loading, and Parking.
Short-term,
negligible, beneficial impact. Tour bus unloading, loading, and
parking would not occur within or near any identified Cowardin or
jurisdictional wetlands.
- Trail Alignment.
Long-term,
negligible, beneficial impact. None of the trail alignments would
occur within any identified Cowardin or jurisdictional wetlands.
- Rehabilitation of Trails.
Long-term,
minor, beneficial impact. Trail rehabilitation activities would not
occur within any identified Cowardin or jurisdictional wetlands. These
impacts would be slightly detectable and localized throughout the local
setting.
- Rehabilitation, Relocation, and Installation of
Bridges.
Long-term, minor, beneficial
impact. Proposed reconstruction of Bridge #5 would completely span the
identified jurisdictional wetland in this area. Negligible amounts of fill
would be placed within the Cowardin wetlands at Bridge #3 and Bridge #6
due to the placement of bridge piers. All bridge abutments would be
removed from the stream channel to upland areas. Overall, hydrologic flows
under the rehabilitated bridges would improve wetlands conditions. The two
piers at the Yosemite Falls Bridge would be replaced in the same location,
and result in no new wetlands impacts.
- View Corridor Maintenance.
Long-term,
negligible, adverse impact. Selected vegetation would be
removed in view corridors; however, wetland plant species would be avoided
to the extent possible.
- Removal of Human-Built Rock-Rubble Pile.
Long-term,
negligible, beneficial impact. The rock-rubble pile would be removed
without the benefit of studies on wetlands, hydrology, and cultural
resources being performed and appropriate public health and safety
measures being applied.
Overall, there would be a long-term,
minor, beneficial impact on wetlands resulting from the removal of bridge
abutments from creek channels.
Cumulative Impact – Regional Setting
Additional cumulative impacts on
wetlands have been described previously in this chapter for
Alternative 1. In combination with Alternative 3, there would be a
long-term, major, beneficial cumulative impact on the size and condition
of wetlands in Yosemite Valley.
Impairment
Wetland impacts resulting from
Alternative 3 would not be of sufficient magnitude to constitute
impairment.
Geology, Geologic Hazards, and Soils
Alternative 1
Analysis – Local Setting
- Restroom Location. Long-term,
minor, adverse impact. The restroom would continue to be located in
its current location; the facility is classified as a Miscellaneous
Structure and is located within the rockfall shadow zone. (See the Final
Yosemite Valley Plan/SEIS, Vol. II, Appendix C, figure C-1 for
occupancy categories.) There would be no change in soil erosion at the
location of the restroom.
- Parking Area.
Long-term,
minor, adverse impact. The existing parking area would continue in its
current location. The facility is classified as "miscellaneous"
and is located within the rockfall shadow zone. There would be no change
in soil erosion in the area.
- Shuttle Bus Stop.
There would
be no change in rockfall hazards and soil erosion in the area as the
result of current shuttle bus stop operations for the Lower Yosemite Fall
area.
- Tour Bus Unloading, Loading, and Parking.
Long-term,
minor, adverse impact. Bus loading, unloading, and parking would
continue within the rockfall shadow zone. There would be no change in
rockfall hazards. There would be no soil erosion as a result of current
tour bus parking.
- Trail Alignment.
Under
Alternative 1, trails would continue in their current alignments. This
current alignment may encourage off-trail use by visitors wanting to take
more direct routes or shortcuts to access viewing areas. As a result,
soils may continue to be disturbed and soil erosion may continue in
off-trail areas most heavily used by visitors. There would be no change in
rockfall hazards.
- Rehabilitation of Trails.
Under
Alternative 1, trails would continue in their current condition. Where
trails are deteriorated or undefined, off-trail use may result. Visitors
may continue to wander away from trails to access viewing areas. As a
result, soils may be disturbed and soil erosion may continue in off-trail
areas most heavily used by visitors. There would be no change in rockfall
hazards.
- Rehabilitation, Relocation, and Installation of
Bridges.
Under Alternative 1, all bridges in
the area would continue in their current condition. Without the
rehabilitation, relocation, and installation of certain bridges, human use
and trampling of off-trail areas may continue. Stream bank soil erosion
may continue in areas where bridges are not accessible for visitors to
cross creek channels (e.g., Bridge #6). There would be no change in
rockfall hazards.
- View Corridor Maintenance.
No
trees or vegetation would be removed to maintain view corridors;
therefore, no soils would be affected. There would be no change in
rockfall hazards.
- Removal of Human-Built Rock-Rubble Pile.
Because
the rock-rubble pile would not be removed, soils would not be affected.
There would be no change in rockfall hazards.
Overall, under Alternative 1 there would
be a long-term, negligible, adverse impact on soils from off-trail use
that could increase erosion. There would be a long-term, negligible,
adverse impact on geology or geologic hazards due to retention of the
restroom and the parking area within the rockfall shadow zone.
Cumulative Impacts – Regional Setting
Past facility development has occurred
in areas that are susceptible to damage from geohazards (rockfalls and
seismic events) and has contributed to the overall degradation of soil
resources in the park. These facilities include lodging, visitor centers,
campgrounds, and bridges, with associated roads and parking lots. In
addition, facilities required to support park infrastructure, including
employee housing, utility facilities, maintenance yards, and supply
storage areas, have been developed throughout the Valley.
Rockfall hazards would be reduced
through projects that relocate people and facilities away from rockfall
hazard zones, such as removal of units at Housekeeping Camp and Curry
Village located within the talus slope zone, as identified in the Yosemite
Valley Plan. However, other projects could expose additional visitors
to the risk of rockfalls, such as the Trail Reconstruction from Happy
Isles to Vernal Fall and Happy Isles Site Improvements. Most of the Lower
Yosemite Fall area is located in the rockfall shadow zone. The Yosemite
Falls Bridge is located in the talus slope zone. In addition, earthquakes
are unavoidable and unpredictable, and represent a potentially long-term,
adverse impact to public health and safety. Past, present, and reasonably
foreseeable future actions would result in local, long-term, minor,
beneficial cumulative impacts to public health and safety from geologic
hazards due to an overall reduction in the density of people and
facilities in the talus slope zone.
Certain development projects could
result in increased degradation of soil resources, such as expansion of
campgrounds and construction of lodging and employee housing in Yosemite
Valley, as identified in the Yosemite Valley Plan. However, other
projects related to habitat restoration, such as removal of roads through
Stoneman and Ahwahnee Meadows, and the Merced River at Eagle Creek
Ecological Restoration (Yosemite Valley), would have long-term, beneficial
effects on soils. Although these types of projects may have slight
site-specific, short-term, adverse effects (e.g., potential construction
erosion and soil loss), an objective of these projects is to restore and
manage natural resources and reduce soil degradation. For example, full
implementation of the Yosemite Valley Plan would restore
approximately 177 acres of soil, of which approximately 136 acres would be
high-value resource soils in Yosemite Valley. The cumulative projects
would result in local, long-term, minor, beneficial cumulative impacts to
soil resources.
Alternative 1 and the cumulative
projects would result in a local, long-term, minor, beneficial impact to
public safety in Yosemite Valley due to the overall reduction in the
density of facilities in the talus slope and rockfall shadow zones. The
local, long-term, minor, beneficial impacts to soil resources under the
cumulative projects would be somewhat diminished by the potential soil
erosion and bank destabilization under Alternative 1, resulting in a net
local, long-term, negligible, beneficial impact to soil resources.
Impairment
Geology, geologic hazards, and soil
impacts resulting from Alternative 1 would not be of sufficient magnitude
to constitute impairment.
Alternative 2
Analysis – Local Setting
- Restroom Relocation. Long-term,
negligible, beneficial impact. Soils-specific mitigation
measures that would be used during restroom demolition and construction of
the new restroom would largely offset adverse impacts to soils from these
activities. In addition, the new location of the restroom would be outside
the rockfall shadow zone.
- Parking Area Removal and Establishment of
Seating/Picnic Area.
Long-term, minor,
adverse impact. Soils-specific mitigation measures that would be used
during the removal of the parking area and the installation of seating
structures would prevent adverse impacts to soils from these activities.
There would be a minor risk from geologic hazards (rockfall) as a result
of activities under Alternative 2 because the picnic area and seating area
would be partly within the rockfall shadow zone.
- New Shuttle Bus Stop.
Long-term,
negligible, beneficial impact. Establishment of the new shuttle bus
stop would not require soil disturbance because it would be located in a
previously paved area. In addition, there would be no increased risk from
geologic hazards (rockfall) as a result of activities under Alternative 2.
- Interim Tour Bus Unloading, Loading, and Parking.
Short-term,
negligible, beneficial impact. Establishment of the interim tour bus
unloading, loading, and parking area would not result in soil disturbance
because it would be located in a previously paved area. There would be a
negligible, minor risk from geologic hazards (rockfall) as a result of
activities under Alternative 2 because the interim bus loading and
unloading and parking would not place facilities inside the rockfall
shadow zone.
- Trail Alignment.
Long-term,
minor, beneficial impact. The trail alignments to be constructed under
Alternative 2 would allow visitors better access to viewing areas while
staying on designated paths. As a result, disturbance and erosion of soils
in off-trail areas would be reduced. Soils-specific mitigation measures
that would be used for trail alignment would prevent adverse impacts to
soils from this activity. In addition, there would be no increased risk
from geologic hazards (rockfall) as a result of activities under
Alternative 2.
- Rehabilitation of Trails.
Long-term,
minor, beneficial impact. Under Alternative 2, trails would be paved
and widened to allow easier access to viewing areas. With better-defined
trails, human use and trampling of off-trail areas would be reduced,
thereby reducing soil disturbance and erosion. Construction and
rehabilitation of trails could bring visitors in proximity to contaminated
soils identified at the waste accumulation area within the vicinity of
Bridge #7 (to be constructed). Soils-specific and construction-specific
mitigation measures that would be used for trail rehabilitation would
prevent adverse impacts to soils and exposure to contaminated soils during
this activity. In addition, there would be no increased risk from geologic
hazards (rockfall and seismic shaking) as a result of activities under
Alternative 2.
- Rehabilitation, Relocation, and Installation of
Bridges.
Long-term, minor, beneficial
impact. Rehabilitation, relocation, and installation of the bridges
would help to discourage human use and trampling of off-trail areas.
Stream bank soil erosion would be reduced because all bridges in the area
would be accessible for visitors to cross creek channels. The construction
of Bridge #7 could bring visitors in proximity to contaminated soils
identified at the waste accumulation area. The soils-specific and
construction-specific mitigation measures that would be used for bridge
rehabilitation and construction would prevent adverse impacts to soils and
exposure to contaminated soils from these activities. There would be no
change in rockfall hazards under Alternative 2.
- View Corridor Maintenance.
Short-term,
negligible, adverse impact. Selected vegetation would be removed in
view corridors. The removal of trees and plants for vista maintenance
would represent a slight disturbance to soils in the area; however, these
impacts would be negligible. There would be no change in rockfall hazards
under Alternative 2.
- Removal of Human-Built Rock-Rubble Pile.
Short-term,
negligible, beneficial impact. The rock-rubble pile removal would be
preceded by studies of hydrology, cultural resources, and wetlands, and
appropriate public health and safety measures would be applied. There
would be a negligible impact to geology, geohazards, or soils.
Overall, there would be a long-term,
minor, beneficial impact on soils due to better defined trails that would
reduce heavy use in off-trail areas under Alternative 2. There would be a
long-term, minor, adverse impact on geology or geologic hazards due to
placement of the picnic area and seating area partially within the
rockfall shadow zone.
Cumulative Impacts – Regional Setting
The impacts of cumulative actions are
described under Alternative 1. In combination with
Alternative 2, there would be no change from Alternative 1 in the
cumulative effects on geology, geologic hazards, and soils within the
park. There would be a local, long-term, minor, beneficial cumulative
impact to public safety in Yosemite Valley due to the overall reduction in
the density of facilities in the talus slope and rockfall shadow zones.
There would be a local, long-term, negligible, beneficial cumulative
impact to soil resources.
Impairment
Geology, geologic hazards, and soils
impacts resulting from Alternative 2 would not be of sufficient magnitude
to constitute impairment.
Alternative 3
Analysis – Local Setting
- Restroom Relocation. Long-term,
negligible, beneficial impact. Soils-specific mitigation
measures that would be used during restroom demolition and construction of
the new restroom would prevent adverse impacts to soils from these
activities. In addition, the new location of the restroom would be outside
the rockfall shadow zone.
- Parking Area Removal and Establishment of an Informal
Seating Area.
Long-term, minor, adverse
impact. Soils-specific mitigation measures that would be used during
the removal of the parking area and the installation of seating structures
would largely offset adverse impacts to soils from these activities. There
would be a minor risk from geologic hazards (rockfall) as a result of
activities under Alternative 3 because the seating area would be
partially within the rockfall shadow zone.
- New Shuttle Bus Stop.
Long-term,
negligible, beneficial impact. Establishment of the new shuttle bus
stop would not require soil disturbance because it would be located in a
previously paved area. In addition, there would be no increased risk from
geologic hazards (rockfall) as a result of activities under
Alternative 3.
- Interim Tour Bus Unloading, Loading, and Parking.
Short-term,
negligible, beneficial impact. Establishment of the interim tour bus
unloading, loading, and parking area would not result in soil disturbance
because it would be located in a previously paved area. There would be a
negligible risk from geologic hazards (rockfall) as a result of activities
under Alternative 3, because a portion of the loading and unloading
and the interim bus parking would not place structures inside the rockfall
shadow zone.
- Trail Alignment.
Long-term,
minor, beneficial impact. The trail alignments to be constructed under
Alternative 3 would allow visitors better access to viewing areas
while staying on designated paths. As a result, disturbance and erosion of
soils in off-trail areas would be reduced. Soils-specific mitigation
measures that would be used for trail alignment would prevent adverse
impacts to soils from this activity. In addition, there would be no
increased risk from geologic hazards (rockfall) as a result of activities
under Alternative 3.
- Rehabilitation of Trails.
Long-term,
minor, beneficial impact. Under Alternative 3, trails would be
paved and widened to allow easier access to viewing areas. With
better-defined trails, human use and trampling of off-trail areas would be
reduced, thereby reducing soil disturbance and erosion. Construction
and rehabilitation of trails could bring visitors in proximity to
contaminated soils identified at the waste accumulation area within the
vicinity of Bridge #7 (to be constructed). Soils-specific and
construction-specific mitigation measures that would be used for trail
rehabilitation would prevent adverse impacts to soils and exposure to
contaminated soils during this activity. In addition, there would be no
increased risk from geologic hazards (rockfall) as a result of activities
under Alternative 3.
- Rehabilitation, Relocation, and Installation of
Bridges.
Long-term, minor, beneficial
impact. Rehabilitation, relocation, and installation of the bridges
would help to discourage human use and trampling of off-trail areas.
Stream bank soil erosion would be reduced because all bridges in the area
would be accessible for visitors to cross creek channels. The construction
of Bridge #7 could bring visitors in proximity to contaminated soils
identified at the waste accumulation area. The soils-specific and
construction-specific mitigation measures that would be used for bridge
rehabilitation and construction would prevent adverse impacts to soils,
and exposure to contaminated soils from these activities. There would be
no change in rockfall hazards or seismic shaking under Alternative 3.
- View Corridor Maintenance.
Short-term,
negligible, adverse impact. Selected vegetation would be removed in
view corridors. The removal of trees and plants for vista maintenance
would represent a slight disturbance to soils in the area; however, these
impacts would be negligible. There would be no change in rockfall hazards
under Alternative 3.
- Removal of Human-Built Rock-Rubble Pile.
Short-term,
negligible, beneficial impact. The rock-rubble pile would be removed
without the benefit of studies on hydrology, cultural resources, and
wetlands being performed and appropriate public health and safety
protection measures being applied. There would be a negligible impact to
geology, geohazards, or soils.
Overall, there would be a long-term,
minor, beneficial impact on soils due to more well-defined trails that
would reduce heavy use in off-trail areas under Alternative 3. There would
be a long-term, minor, adverse impact on geology or geologic hazards due
to placement of the seating area partially within the rockfall shadow
zone.
Cumulative Impacts – Regional Setting
The impacts of cumulative actions are
described under Alternative 1. In combination with
Alternative 3, there would be no change from Alternative 1 in the
cumulative effects on geology, geologic hazards, and soils within the
park. There would be a local, long-term, minor beneficial impact to public
safety in Yosemite Valley due to the overall reduction in the density of
facilities in the talus slope and rockfall shadow zones. There would be a
local, long-term, negligible, beneficial impact to soil resources.
Impairment
Geology, geologic hazards, and soil
impacts resulting from Alternative 3 would not be of sufficient magnitude
to constitute impairment.
Hydrology and Water Quality
Alternative 1
Analysis – Local Setting
- Restroom Location. The
existing restroom would continue to be located in its current location,
which is not within or near any creek channels; therefore, water quality
would not be affected.
- Parking Area.
Long-term,
minor, adverse impact. The existing parking area would continue to
represent a potential non-point source of pollution with the heavy use and
concentrated presence of vehicles in the area. (Non-point source pollution
occurs when water runs over land or through the ground, picks up
pollutants, and deposits them in surface waters or introduces them into
groundwater.) Surface runoff from the parking area could adversely affect
the water quality of nearby creeks.
- Shuttle Bus Stop.
Long-term,
minor, adverse impact. Shuttle buses would continue to stop at the
northeast corner of the existing parking area. Surface runoff from the
parking area would continue to (potentially) adversely affect the water
quality of Yosemite Creek.
- Tour Bus Unloading, Loading, and Parking.
Long-term,
minor, adverse impact. Tour buses would continue to park within the
existing parking area. Surface runoff from the parking area would continue
to (potentially) adversely affect the water quality of Yosemite Creek.
- Trail Alignment.
Long-term,
minor, adverse impact. Under Alternative 1, current trail alignments
would continue to encourage human use and trampling in creek channels.
This activity would continue to degrade hydrologic processes and water
quality of creeks in the area.
- Rehabilitation of Trails.
Long-term,
minor, adverse impact. Under Alternative 1, human use and trampling in
creek areas as the result of poorly defined trails may continue to degrade
hydrologic processes and water quality of creeks.
- Rehabilitation, Relocation, and Installation of
Bridges.
Long-term, minor, adverse impact. Under
Alternative 1, all bridges in the Lower Yosemite Fall area would continue
to constrict and alter water flows. This could contribute to accelerated
erosion on adjacent riverbanks associated with constricted flows.
- View Corridor Maintenance.
No
trees or vegetation would be removed to maintain view corridors;
therefore, no creeks would be affected.
- Removal of Human-Built Rock-Rubble Pile.
Long-term,
negligible, adverse impact. The rock-rubble pile removal would be
preceded by studies of hydrology, cultural resources, and wetlands, and
appropriate public health and safety measures would be applied.
Overall, there would be a long-term,
minor, adverse impact on hydrology and water quality under Alternative 1
due to surface runoff from the parking lot, which could introduce
pollutants into nearby creeks.
Cumulative Impacts – Regional Setting
The Merced River has been previously
affected by a variety of projects that have introduced obstructions into
the river channel, modified the floodplain, and adversely affected
hydrology. Examples of actions that have had adverse effects on the
hydrologic processes of the Merced River include lowering of the El
Captain moraine; placement of riprap; removal of large woody debris; and
construction of bridges, dikes, flood walls, impoundments, dams, and
buildings. Conversely, actions such as riverbank restoration projects,
removal of impoundments and bridges, and limiting visitor use to
particular areas help restore the natural river flow and reduce bank
erosion.
Reasonably foreseeable future projects
that would have beneficial impacts on hydrologic processes and water
quality include such restoration actions as those presented in the Yosemite
Valley Plan. Elements of the Yosemite Valley Plan include
removal of Sugar Pine Bridge, which constrains flows of the Merced River;
restoration to natural conditions of campgrounds located within the
floodplain; and removal of facilities from the 100-year floodplain.
Alternatively, adverse impacts could
occur by implementing projects called for in the Yosemite Valley Plan,
including construction of additional lodging, campsites, and a visitor
transit center in the Valley.
Overall, implementation of the Yosemite
Valley Plan would have a beneficial effect on river hydrologic
processes and water quality.
The Merced Wild and Scenic River
Comprehensive Management Plan (Merced River Plan) (NPS 2001b) protects
river-related resources through the application of seven management
elements. These elements are the River Protection Overlay, management
zoning, protection and enhancement of Outstandingly Remarkable Values,
Section 7 determination process under the Wild and Scenic Rivers Act,
classifications, boundary delineation, and implementation of a Visitor
Experience Resource Protection framework (refer to the Merced River Plan
for descriptions of these management elements).
Other future projects include the Happy
Isles Bridge Replacement Project, Repair of Flood Damaged Trails at Happy
Isles, Merced River at Eagle Creek Ecological Restoration (Yosemite
Valley), and the Replacement/Rehabilitation of the Yosemite Valley Main
Sewer Line. Cumulatively, these projects are anticipated to have
beneficial impacts on hydrologic processes and water quality of the Merced
River.
While some of the past, present, and
reasonably foreseeable future projects along the Merced River in Yosemite
Valley would ultimately remove constrictions to streamflows, enhance water
quality, rehabilitate eroded streambanks, and reduce degradation of stream
characteristics in the Merced River, others would result in adverse water
quality impacts and bank erosion. Thus, the cumulative projects would
result in a local, long-term, minor, beneficial impact to hydrologic
processes and water quality.
The past, present, and future projects
in Yosemite Valley, considered cumulatively with Alternative 1, would have
a local, long-term, minor beneficial effect on hydrologic processes and
water quality in Yosemite Valley.
Impairment
Hydrology and water quality impacts
resulting from Alternative 1 would not be of sufficient magnitude to
constitute impairment.
Alternative 2
Analysis – Local Setting
- Restroom Relocation. Long-term,
negligible, beneficial impact. Hydrology/water quality-specific
mitigation measures (including surface-runoff control) that would be used
during Alternative 2 restroom demolition and construction would
substantially minimize adverse impacts to Yosemite Creek during these
activities. Also, a portion of the area would be revegetated, thereby
restoring surface hydrology and improving water quality in the long term.
- Parking Area Removal and Establishment of
Seating/Picnic Area.
Long-term, minor,
beneficial impact. The parking area removal would remove a non-point
source of pollution from creeks in the area. The non-point pollution
source would be moved to other parking areas where water quality
protection measures meet regulations specified in the Clean Water Act.
(Note: More detailed mitigation measures are presented in Chapter 2,
Description of Proposed Action and Alternatives.) Hydrology/water
quality-specific mitigation measures under Alternative 2 (including
surface-runoff control) that would be used during parking lot removal and
seating/picnic area construction would prevent adverse impacts to creeks
during these activities.
- New Shuttle Bus Stop.
Long-term, negligible, beneficial impact. Under Alternative 2, the new
shuttle bus stop would be along Northside Drive at a location that is
already paved, and where vehicles already stop periodically. Surface
runoff would not be affected by any additional pollutant types or amount
from the new shuttle bus stop beyond that normally associated with runoff
from paved roadways.
- Interim Tour Bus Unloading, Loading, and Parking.
Short-term,
negligible, adverse impact. Under Alternative 2, the interim tour bus
unloading and loading zone would be along Northside Drive at a location
that is already paved, and where vehicles already stop periodically.
Surface runoff could be marginally affected by additional pollutants from
tour buses beyond that normally associated with runoff from paved
roadways.
- Trail Alignment.
Long-term, minor, beneficial impact. Under Alternative 2, trail
alignments would provide visitors with more defined access to viewing
areas, thereby discouraging the trampling of creek channels. Overall, this
would benefit the hydrologic processes and water quality of creeks in the
area. Hydrology/water quality-specific mitigation measures (including
surface-runoff control) that would be used during trail alignment would
prevent adverse impacts to creeks during these activities.
- Rehabilitation of Trails.
Long-term,
minor, beneficial impact. Under Alternative 2, trail rehabilitation
would provide visitors with more defined access to viewing areas, thereby
discouraging the trampling of creek channels. Overall, this would benefit
the hydrologic processes and water quality of creeks in the area.
Hydrology/water quality-specific mitigation measures (including
surface-runoff control) that would be used during trail rehabilitation
would prevent adverse impacts to creeks from these activities.
- Rehabilitation, Relocation, and Installation of
Bridges.
Long-term, moderate, beneficial
impact. Under Alternative 2, all bridges would be rehabilitated to
accommodate larger flows. Bridge abutments would be moved out of creek
channels and located further up on the banks. This would enlarge the
opening under each bridge, remove the current constricting abutments,
reduce bank erosion associated with the constricted openings, and
accommodate more water under the bridge. The piers at Bridges #3 and #6
would cause a slightly perceptible change to creek hydrology. Overall, the
bridges would be designed to improve hydrology and accommodate minor
shifts in the channel. There would be no change in hydrologic processes at
the Yosemite Falls Bridge as a result of its rehabilitation.
Hydrology/water quality-specific mitigation measures (including runoff
control) that would be used for bridge rehabilitation, relocation, and
installation would largely offset adverse impacts to water quality and
hydrology from these activities.
- View Corridor Maintenance.
Long-term, negligible, adverse impact. Selected vegetation would be
removed in view corridors. The removal of trees and plants for maintenance
of the Hutchings view corridor would have imperceptible effects to the
creek hydrology. Vista maintenance would be conducted with appropriate
mitigation measures to largely offset adverse impacts to hydrologic
processes and water quality.
- Removal of Human-Built Rock-Rubble Pile.
Long-term,
minor, beneficial impact. The rock-rubble pile removal would be
preceded by studies of hydrology, cultural resources, and wetlands, and
appropriate public health and safety measures would be applied. The
results of these studies would be used to maximize the potential for
hydrologic restoration without adversely affecting public health and
safety.
Overall, there would be a long-term,
moderate, beneficial impact on hydrology and water quality under
Alternative 2 due to the removal of the parking lot and removal of the
bridge abutments from creek channels to accommodate hydrologic flows.
Cumulative Impacts – Regional Setting
The cumulative impact analysis for
hydrology and water quality in Alternative 2 is the same as described
under Alternative 1 earlier in this chapter. The past, present, and future
projects in Yosemite Valley, considered cumulatively with Alternative 2,
would have a local, long-term, minor, beneficial impact on hydrologic
processes and water quality in Yosemite Valley.
Impairment
Hydrology and water quality impacts
resulting from Alternative 2 would not be of sufficient magnitude to
constitute impairment.
Alternative 3
Analysis – Local Setting
- Restroom Relocation. Long-term,
negligible, beneficial impact. Hydrology/water quality-specific
mitigation measures (including surface-runoff control) that would be used
during restroom demolition and construction would substantially minimize
adverse impacts to creeks during these activities. Also, a portion of the
area would be revegetated, thereby restoring surface hydrology and
improving water quality in the long term.
- Parking Area Removal and Establishment of an Informal
Seating Area.
Long-term, minor, beneficial
impact. The parking area removal would remove a non-point source of
pollution for creeks in the area. Hydrology/water quality-specific
mitigation measures (including surface-runoff control) that would be used
during parking lot removal and seating area construction (presented in
detail in Chapter 2, Description of the Proposed Action and Alternatives)
would prevent adverse impacts to creeks during these activities.
- New Shuttle Bus Stop.
Long-term, negligible, beneficial impact. The new shuttle bus stop
would be along Northside Drive at a location that is already paved, and
where vehicles already stop periodically. Surface runoff would not be
affected by any additional pollutant types or amount from the new shuttle
stop beyond that normally associated with runoff from paved roadways.
- Interim Tour Bus Unloading, Loading, and Parking.
Short-term,
negligible, adverse impact. The interim tour bus unloading and loading
zone would be along Northside Drive at a location that is already paved,
and where vehicles already stop periodically. Surface runoff could be
marginally affected by additional pollutants from tour buses beyond that
normally associated with runoff from paved roadways.
- Trail Alignment.
Long-term, minor, beneficial impact. Under Alternative 3, trail
alignments would provide visitors with more defined access to viewing
areas, thereby discouraging the trampling of creek channels. Overall, this
would benefit the hydrologic processes and water quality of creeks in the
area. Hydrology/water quality-specific mitigation measures (including
surface-runoff control) that would be used during trail alignment would
prevent adverse impacts to creeks during these activities.
- Rehabilitation of Trails.
Long-term,
minor, beneficial impact. Under Alternative 3, trail
rehabilitation would provide visitors with more defined access to viewing
areas, thereby discouraging the trampling of creek channels. Overall, this
would benefit the hydrologic processes and water quality of creeks in the
area. Hydrology/water quality-specific mitigation measures (including
surface-runoff control) that would be used during trail rehabilitation
would prevent adverse impacts to creeks from these activities.
- Rehabilitation, Relocation, and Installation of
Bridges.
Long-term, moderate, beneficial
impact. Under Alternative 3, all bridges would be rehabilitated
to accommodate larger flows. Bridge abutments would be moved out of creek
channels and located further up on the banks. This would enlarge the
opening under each bridge, remove the current constricting abutments,
reduce bank erosion associated with the constricted openings, and
accommodate more water under the bridge. Overall, the bridges would be
designed to improve hydrology and accommodate minor shifts in the channel.
There would be no change in hydrologic processes at the Yosemite Falls
Bridge as a result of its rehabilitation. Hydrology/water quality-specific
mitigation measures (including runoff control) that would be used for
bridge rehabilitation, relocation, and installation would largely offset
adverse impacts to water quality and hydrology from these activities.
- View Corridor Maintenance.
Long-term, negligible, adverse impact. Selected vegetation would be
removed in view corridors. The removal of trees and plants for maintenance
of the Hutchings view corridor could potentially affect creeks. Vista
maintenance would be conducted with appropriate mitigation measures to
prevent adverse impacts to hydrologic processes and water quality.
- Removal of Human-Built Rock-Rubble Pile.
Long-term,
negligible, beneficial impact. The rock-rubble pile would be removed
without the benefit of studies on hydrology, cultural resources, and
wetlands being performed and appropriate public health and safety
protection measures being applied.
Overall, there would be a long-term,
moderate, beneficial impact on hydrology under Alternative 3 due to the
removal of the parking lot and removal of bridge abutments from creek
channels to accommodate hydrologic flows.
Cumulative Impacts – Regional Setting
The cumulative impact analysis for
hydrology and water quality in Alternative 3 is the same as described
under Alternative 1 earlier in this chapter. The past, present, and future
projects in Yosemite Valley, considered cumulatively with Alternative 3,
would have a local, long-term, minor, beneficial impact on hydrologic
processes and water quality in the Lower Yosemite Fall area.
Impairment
Hydrology and water quality impacts
resulting from Alternative 3 would not be of sufficient magnitude to
constitute impairment.
Floodplains
Alternative 1
Analysis – Local Setting
The current level of risk to human life
and property would continue as it is today, resulting in negligible
impact. Because there would be minor risk to human life and property and
no overnight accommodations in the Lower Yosemite Fall area, the following
actions would be exempted from the National Park Service’s Floodplain
Management Guideline (NPS 1993).
- Restroom Location.
Since
the restroom would continue to be located in its current location and
would not accommodate overnight occupants, there would continue to be no
risk to human life or property.
- Parking Area.
The existing
parking area would continue to not accommodate overnight visitors. There
would continue to be no risk to human life or property.
- Shuttle Bus Stop.
Since the
shuttle bus stop would continue in its current location and no overnight
accommodations would be constructed there, floodplain impacts would not
occur.
- Tour Bus Unloading, Loading, and Parking.
Since
tour bus operations would continue within the existing parking area, and
no construction would occur, floodplain impacts would not occur.
- Trail Alignment.
Long-term,
minor, adverse impact. Trails would remain in their current
alignments, and no new structures would be placed in the floodplain;
therefore, trail alignment would continue to have minor effects on the
floodplain because they would be a single structure used primarily in
the daytime.
- Rehabilitation of Trails.
Since the trails would continue in their current condition,
floodplain impacts would not occur.
- Rehabilitation, Relocation, and Installation of
Bridges.
Long-term, minor, adverse
impact. The bridges would continue in their current locations and
condition; therefore, these few structures would potentially receive
slight damage during a flood.
- View Corridor Maintenance.
Vegetation
would not be removed to enhance identified view corridors, and no new
development would occur in the floodplain.
- Removal of Human-Built Rock-Rubble Pile.
The
rock-rubble pile would continue at its current location, and no new
development would occur in the floodplain.
Overall, there would be long-term,
minor, adverse floodplain impacts relating to health and safety under
Alternative 1.
Cumulative Impacts – Regional Setting
Historically, the Merced River has been
affected by a variety of projects that have introduced obstructions into
the river channel and modified the floodplain. Alterations to hydrology
have occurred through development and use within the Merced River corridor
since Euro-American settlement. Examples of actions that have had adverse
effects on the hydrologic processes of the Merced River include placement
of riprap; removal of large woody debris; and construction of bridges,
dikes, flood walls, impoundments, dams, and buildings. Conversely, actions
such as riverbank restoration projects, removal of impoundments and
bridges, and limiting visitor use to particular areas help restore the
natural river flow and reduce bank erosion.
Reasonably foreseeable future projects
that would have beneficial impacts on hydrologic processes and the
floodplain include such restoration actions as those presented in the Yosemite
Valley Plan. Elements of the Yosemite Valley Plan include
removal of Sugar Pine Bridge, which constrains flows of the Merced River;
restoration to natural conditions of campgrounds located within the
floodplain; and removal of facilities from the 100-year floodplain.
Alternatively, adverse impacts could occur by implementation of the Yosemite
Valley Plan projects, including construction of additional lodging,
campsites, and a visitor transit center in the Valley. Overall,
implementation of the Yosemite Valley Plan would have a beneficial
effect on the floodplain.
Impairment
Floodplain impacts resulting from
Alternative 1 would not be of sufficient magnitude to constitute
impairment.
Alternative 2
Analysis – Local Setting
Under Alternative 2, the only facilities
that would be constructed in the Merced River floodplain in the Lower
Yosemite Fall area would be exempt from the National Park Service Floodplain
Management Guideline because they would not accommodate overnight
occupants and would not represent a risk to human life and property.
- Restroom Location.
Long-term,
minor, adverse impact. The new restroom would remain in the
floodplain, but it would not accommodate overnight occupants, nor would
it adversely affect human safety or property.
- Parking Area.
Long-term,
minor, adverse impact. Removal of the parking area and
installation of the seating area and picnic area and trails for day use
would be exempt from the National Park Service Floodplain Management
Guideline, although these new facilities would remain in the
floodplain.
- Shuttle Bus Stop.
Long-term,
negligible, beneficial impact. The new shuttle bus stop would
be exempt from the National Park Service Floodplain Management
Guideline because no overnight occupants of this facility would be
expected.
- Tour Bus Unloading, Loading, and Parking.
Long-term,
negligible, beneficial impact. No construction of facilities
related to tour bus unloading, loading, and parking would occur in the
floodplain; therefore, there would be no risk to public health and
safety.
- Trail Alignment.
Long-term,
negligible, beneficial impact. No structures related to trail
alignment would be constructed in the floodplain; therefore, health and
safety issues would not occur.
- Rehabilitation of Trails.
Long-term,
negligible, beneficial impact. No structures related to trail
rehabilitation would be constructed in the floodplain; therefore, health
and safety issues would not occur. A trail boardwalk would be elevated
above the creek bed, thus allowing creek hydrology to be restored. The
boardwalk would be within the floodplain; however, because it would be
used in the daytime only and would be a single structure, impacts would
be negligible.
- Rehabilitation, Relocation, and Installation of
Bridges.
Long-term, minor, beneficial
impact. The bridges to be constructed and rehabilitated would
be designed to reduce or eliminate impacts to human health or safety or
damage to property.
- View Corridor Maintenance.
Long-term,
negligible, beneficial impact. Vegetation maintenance
activities to maintain view corridors would not place new facilities
within the floodplain.
- Removal of Human-Built Rock-Rubble Pile.
Long-term,
minor, beneficial impact. Removal of the rock-rubble pile
would be preceded by studies to ensure that hazards to life and property
would not occur.
Overall, there would be long-term,
minor, adverse impacts to the floodplain under Alternative 2 due to
construction of the new restroom and picnic area and seating area in the
100-year floodplain.
Cumulative Impacts – Regional Setting
The cumulative impact analysis for
floodplains under Alternative 2 is the same as described under Alternative
1.
Impairment
Floodplain impacts resulting from
Alternative 2 would not be of sufficient magnitude to constitute
impairment.
Alternative 3
Analysis – Local Setting
Under Alternative 3, the only facilities
that would be constructed in the Merced River floodplain in the Lower
Yosemite Fall area would be exempt from National Park Service Floodplain
Management Guidelines because they would not accommodate overnight
occupants and would not represent a risk to human life and property.
- Restroom Location.
Long-term,
minor, adverse impact. The new restroom would remain in the
floodplain, but it would not accommodate overnight occupants, nor would
it adversely affect human safety or property.
- Parking Area.
Long-term,
minor, beneficial impact. Removal of the parking area and
installation of the seating area and trails for day use would be exempt
from the National Park Service Floodplain Management Guideline,
although these new facilities would remain in the floodplain.
- Shuttle Bus Stop.
Long-term,
negligible, beneficial impact. The new shuttle bus stop would
be exempt from the National Park Service Floodplain Management
Guideline because no overnight occupants of this facility would be
expected.
- Tour Bus Unloading, Loading, and Parking.
Long-term,
negligible, beneficial impact. No construction of facilities
related to tour bus unloading, loading, and parking would occur in the
floodplain.
- Trail Alignment.
Long-term,
negligible, beneficial impact. No structures related to trail
alignment would be constructed in the floodplain.
- Rehabilitation of Trails.
Long-term,
negligible, beneficial impact. No structures related to trail
rehabilitation would be constructed in the floodplain.
- Rehabilitation, Relocation, and Installation of
Bridges.
Long-term, minor, beneficial
impact. The bridges to be constructed and rehabilitated would
be designed to reduce or eliminate impacts to human health or safety or
damage to property.
- View Corridor Maintenance.
Long-term,
negligible, beneficial impact. Vegetation maintenance
activities to maintain view corridors would not place new facilities
within the floodplain.
- Removal of Human-Built Rock-Rubble Pile.
Long-term,
negligible, beneficial impact. Removal of the rock-rubble
pile would not be preceded by studies to ensure that hazards to life and
property would not occur.
Overall, there would be long-term,
minor, adverse impacts to the floodplain under Alternative 3 due to
the construction of the new restroom and seating area within the 100-year
floodplain.
Cumulative Impacts – Regional Setting
The cumulative impact analysis for
floodplains under Alternative 3 is the same as described under Alternative
1.
Impairment
Floodplain impacts resulting from
Alternative 3 would not be of sufficient magnitude to constitute
impairment.
Vegetation
Alternative 1
Analysis – Local Setting
- Restroom Location.
Long-term, minor, adverse impact. Under Alternative 1, trampling in
the area of the existing restroom would continue to prevent native
vegetative understory from being established in the area.
- Parking Area.
Under
Alternative 1, the existing parking area would remain. Vegetation
surrounding the parking area would continue to be affected by vehicle
emissions and human activity concentrated in the area.
- Shuttle Bus Stop.
Shuttle
buses would continue to stop within the parking area. There would be no
additional impact to vegetation from the current shuttle bus stop beyond
that created by the parking area.
- Tour Bus Unloading, Loading, and Parking.
Tour
buses would continue to park within the parking area. There would be no
additional impact to vegetation from the current shuttle bus stop beyond
that created by the parking area.
- Trail Alignment.
Long-term, minor, adverse impact. The alignment of certain trails
within the Lower Yosemite Fall area encourages use of off-trail areas to
access viewing areas by more direct routes. As a result, vegetation would
continue to be trampled in off-trail areas.
- Rehabilitation of Trails.
Long-term,
minor, adverse impact. Where trails are not currently well defined,
areas of vegetation would continue to be trampled by foot traffic.
- Rehabilitation, Relocation, and Installation of
Bridges.
Long-term, minor, adverse impact. Where
bridges are not accessible or are in poor condition, areas of vegetation
would continue to be trampled by foot traffic. In particular, riparian
vegetation along streambanks may be affected.
- View Corridor Maintenance.
Long-term, minor, beneficial impact. Trees and vegetation would not be
trimmed; they would continue to obscure view corridors.
- Removal of Human-Built Rock-Rubble Pile.
Long-term,
negligible, beneficial impact. The rock-rubble pile would continue at
its current location until studies of hydrology, cultural resources, and
wetlands are performed and appropriate mitigation measures applied.
Overall, long-term, minor, adverse
impacts to vegetation would continue under Alternative 1 from trampling
and heavy foot traffic near the restroom and other off-trail areas (as a
result of poorly defined trails and deteriorated bridges) and from heavy
exposure to vehicle emissions.
Cumulative Impacts – Regional Setting
Vegetation in Yosemite Valley has been
substantially altered by development and visitor activities. These changes
have negatively influenced the size, form, and function of vegetation
communities and the plants and wildlife that inhabit them. Cumulative
beneficial effects on vegetation would include restoration, rehabilitation
projects, and ecosystem management. Cumulative adverse effects would be
related to increased facilities and visitor demand.
Reasonably foreseeable future actions
within Yosemite Valley would have an overall net benefit to vegetation.
Full implementation of the Yosemite
Valley Plan would restore approximately 175 acres, of which
approximately 160 acres would be high-value resource vegetation in
Yosemite Valley. Such proposed actions include removal and restoration of
several campgrounds; removal of roads through Stoneman and Ahwahnee
Meadows; and natural vegetation restoration actions in several areas.
Although certain Yosemite Valley Plan projects have the potential
to adversely affect local vegetation, such as construction of new parking
and lodging facilities, and expansion of campgrounds in Yosemite Valley,
these projects would be designed to ensure the long-term protection of
sensitive vegetation communities consistent with the Merced River Plan and
the Vegetation Management Plan (NPS 1997b).
The Merced River Plan protects
river-related natural resources through the application of seven
management elements. These elements are the River Protection Overlay,
management zoning, protection and enhancement of Outstandingly Remarkable
Values, implementation of a Visitor Experience Resource Protection
framework, boundary delineation, classifications, and the Section 7 (of
the Wild and Scenic River Act) determination process.
Past, present, and reasonably
foreseeable future actions, in combination with Alternative 1, could have
a net long-term, moderate, beneficial effect on vegetation patterns.
Impairment
Vegetation impacts resulting from
Alternative 1 would not be of sufficient magnitude to constitute
impairment.
Alternative 2
Analysis – Local Setting
- Restroom Relocation. Long-term,
minor, beneficial impact. A small amount of mixed conifer/California
black oak vegetation (less than 800 square feet) would be re-established
in the area where the restroom would be removed. In addition, foot traffic
and associated trampling would be reduced around the perimeter of the
existing restroom. This would allow the currently degraded understory to
re-establish in the vicinity of the restroom. There would be no impact on
vegetation from the construction of the new restroom because it would be
constructed in the existing parking area in an area that does not support
vegetation. There would be a long-term, minor, beneficial impact on
vegetation as a result of the restroom relocation because there would be a
measurable beneficial impact on vegetation within a relatively small area.
- Parking Area Removal and Establishment of a
Seating/Picnic Area.
Long-term,
moderate, beneficial impact. About 1 acre of mixed conifer/California
black oak woodland would be re-established in the area where the current
parking area is located. This would be a long-term, moderate, beneficial
impact on vegetation because it would cause a beneficial change in the
size and continuity of the plant community; however, the impact would be
localized. Establishment of the seating area would have no impact on
vegetation because it would be within the existing parking area.
- New Shuttle Bus Stop.
Long-term, negligible, adverse impact. Tree and some vegetation
removal would be required for the establishment of a new shuttle bus stop;
however, the removal would be imperceptible from current conditions.
- Interim Tour Bus Unloading, Loading, and Parking.
Long-term,
negligible, beneficial impact. The planned interim tour bus unloading
and loading zone along Northside Drive is already paved. The establishment
of bus parking spaces near Camp 4, west of the Lower Yosemite Fall area
would not require the removal of trees or vegetation.
- Trail Alignment.
Long-term, negligible, beneficial impact. Trail rehabilitation would
help to reduce trampling of vegetation in off-trail areas. This would
allow plant communities to re-establish in heavily trampled areas and
result in a long-term, minor, beneficial impact. Trail widening and
hardening may require the removal of individual incense-cedar and
ponderosa pine trees (less than 30 trees with a diameter at breast height
between 6 and 20 inches). One mature big-leaf maple tree, a riparian
species, may be removed to enlarge the viewing area near the base of Lower
Yosemite Fall. There would be a long-term, negligible, beneficial impact
on vegetation as a result of trail alignment because the benefits of
reduced trampling in off-trail areas would be reduced by the need to
remove trees to widen trails and enlarge the viewing area.
- Rehabilitation of Trails.
Long-term,
negligible, beneficial impact. Trail rehabilitation would help to
reduce trampling of vegetation in off-trail areas. This would allow plant
communities to re-establish in heavily trampled areas and result in a
long-term, minor, beneficial impact. Trail widening and hardening may
require the removal of individual incense-cedar and ponderosa pine trees
(less than 30 trees with a diameter at breast height between 6 and 20
inches). One mature big-leaf maple tree, a riparian species, may be
removed to enlarge the viewing area near the base of Lower Yosemite Fall.
There would be a long-term, negligible, beneficial impact on vegetation as
a result of trail alignment because the benefits of reduced trampling in
off-trail areas would be reduced by the need to remove trees to widen
trails and enlarge the viewing area.
- Rehabilitation, Relocation, and Installation of
Bridges.
Long-term, negligible, beneficial
impact. Removal of abutments from stream channels would enhance
conditions that support riparian vegetation in the vicinity of the
bridges. Three mature riparian trees (white alder) may need to be removed
in the vicinity of Bridge #3 in order to move the abutments to upland
areas. In addition, several young incense-cedar and ponderosa pine trees
may need to be removed at Bridges #5 and #6 in order to move the abutments
to upland areas. There would be a long-term, negligible, beneficial impact
on vegetation because the benefits of enhanced riparian conditions in the
vicinity of the bridges would be reduced by the removal of mature riparian
trees at Bridge #3.
- View Corridor Maintenance.
Long-term,
negligible, adverse impact. Thinning of the trees and vegetation
removal within the two view corridors may result in removal of tree and
plant species of varying sizes and health status. However, thinning would
be selective and oak trees and riparian species would be retained to the
greatest extent possible.
- Removal of Human-Built Rock-Rubble Pile.
Long-term,
negligible, beneficial impact. The rock-rubble pile removal would be
preceded by studies of hydrology, cultural resources, and wetlands, and
appropriate public health and safety measures would be applied.
Overall, there would be a long-term,
moderate, beneficial impact on vegetation under Alternative 2 due to the
removal of the parking area, revegetation of most of the parking area,
relocation of the restroom, and alignment and rehabilitation of the
trails.
Cumulative Impacts – Regional Setting
Under Alternative 2, cumulative impacts
to vegetation in the Lower Yosemite Fall area would be the same as
described for Alternative 1.
Impairment
Vegetation impacts resulting from
Alternative 2 would not be of sufficient magnitude to constitute
impairment.
Alternative 3
Analysis – Local Setting
- Restroom Relocation. Long-term,
minor, beneficial impact. A small amount of mixed
conifer/California black oak vegetation (less than 800 square feet) would
be re-established in the area where the restroom would be removed. In
addition, foot traffic and associated trampling would be reduced around
the perimeter of the existing restroom. This would allow the currently
degraded understory to re-establish in the vicinity of the restroom. There
would be no impact on vegetation from the construction of the new restroom
because it would be constructed in the existing parking area in an area
that does not support vegetation. There would be a long-term, minor,
beneficial impact on vegetation as a result of the restroom relocation
because there would be a measurable beneficial impact on vegetation within
a relatively small area.
- Parking Area Removal and Establishment of an Informal
Seating Area.
Long-term, moderate,
beneficial impact. About 1 acre of mixed conifer/California black oak
woodland would be re-established in the area where the current parking
area is located. This would be a long-term, moderate, beneficial impact on
vegetation because it would cause a beneficial change in the size and
continuity of the plant community; however, the impact would be localized.
Establishment of the seating area would have no impact on vegetation
because it would be within the existing parking area.
- New Shuttle Bus Stop.
Long-term, negligible, adverse impact. Tree and some vegetation
removal would be required for the establishment of a new shuttle bus stop;
however, the removal would be imperceptible.
- Interim Tour Bus Unloading, Loading, and Parking.
Long-term,
negligible, beneficial impact. The planned interim tour bus unloading
and loading zone along Northside Drive is already paved. The establishment
of bus parking spaces near Camp 4, west of the Lower Yosemite Fall area,
would not require the removal of trees or vegetation.
- Trail Alignment.
Long-term, negligible, beneficial impact. Trail rehabilitation would
help to reduce trampling of vegetation in off-trail areas. This would
allow plant communities to re-establish in heavily trampled areas and
result in a long-term, minor, beneficial impact. Trail widening and
hardening may require the removal of individual incense-cedar and
ponderosa pine trees (less than 30 trees with a diameter at breast height
between 6 and 20 inches). One mature big-leaf maple tree, a riparian
species, may be removed to enlarge the viewing area near the base of Lower
Yosemite Fall. There would be a long-term, negligible, beneficial impact
on vegetation as a result of trail alignment because the benefits of
reduced trampling in off-trail areas would be reduced by the need to
remove trees to widen trails and enlarge the viewing area.
- Rehabilitation of Trails.
Long-term,
negligible, beneficial impact. Trail rehabilitation would help to
reduce trampling of vegetation in off-trail areas. This would allow plant
communities to re-establish in heavily trampled areas and result in a
long-term, minor, beneficial impact. Trail widening and hardening may
require the removal of individual incense-cedar and ponderosa pine trees
(less than 30 trees with a diameter at breast height between 6 and 20
inches). One mature big-leaf maple tree, a riparian species, may be
removed to enlarge the viewing area near the base of Lower Yosemite Fall.
There would be a long-term, negligible, beneficial impact on vegetation as
a result of trail alignment because the benefits of reduced trampling in
off-trail areas would be reduced by the need to remove trees to widen
trails and enlarge the viewing area.
- Rehabilitation, Relocation, and Installation of
Bridges.
Long-term, negligible, beneficial
impact. Removal of abutments from stream channels would enhance
conditions that support riparian vegetation in the vicinity of the
bridges. Three mature riparian trees (white alder) may need to be removed
in the vicinity of Bridge #3 in order to move the abutments to upland
areas. In addition, several young incense-cedar and ponderosa pine trees
may need to be removed at Bridges #5 and #6 in order to move the abutments
to upland areas. There would be a long-term, negligible, beneficial impact
on vegetation because the benefits of enhanced riparian conditions in the
vicinity of the bridges would be reduced by the removal of mature riparian
trees at Bridge #3.
- View Corridor Maintenance.
Long-term,
negligible, adverse impact. Thinning of the trees and vegetation
removal within the two view corridors may result in removal of tree and
plant species of varying sizes and health status. However, thinning would
be selective, and oak trees and riparian species would be retained to the
greatest extent possible.
- Removal of Human-Built Rock-Rubble Pile.
Long-term,
negligible, beneficial impact. The rock-rubble pile would be removed
without the benefit of studies on hydrology, cultural resources, and
wetlands being performed and appropriate public health and safety
protection measures being applied.
Overall, there would be a long-term,
moderate, beneficial impact on vegetation under Alternative 3 due to the
removal of the parking area, revegetation of most of the parking area, and
rehabilitation and realignment of trails.
Cumulative Impacts – Regional Setting
Under Alternative 3, cumulative impacts
to vegetation in the Lower Yosemite Fall area would be the same as
described for Alternative 1.
Impairment
Vegetation impacts resulting from
Alternative 3 would not be of sufficient magnitude to constitute
impairment.
Wildlife
Alternative 1
Analysis – Local Setting
Alternative 1 would result in no further
impacts on wildlife species or habitat in the Lower Yosemite Fall area
beyond existing conditions. Existing habitat would not be further
disturbed.
- Restroom Location.
Because
the restroom would continue to be located in its current location and a
new restroom would not be constructed, no further disturbance of
wildlife would occur.
- Parking Area.
Because the
parking area would continue in its current location, further disturbance
of wildlife would continue to be avoided.
- Shuttle Bus Stop.
Because
the shuttle bus stop would continue in its current location and a new
shuttle bus stop would not be constructed, further disturbance of
wildlife would continue to be avoided.
- Tour Bus Unloading, Loading, and Parking.
Because
tour bus operations would continue within the existing parking area, and
no construction would occur, further disturbance of wildlife would
continue to be avoided.
- Trail Alignment.
Because
the trails would remain in their current alignments, further disturbance
of wildlife would continue to be avoided.
- Rehabilitation of Trails.
Because
the trails would remain in their current condition, further disturbance
of wildlife would continue to be avoided.
- Rehabilitation, Relocation, and Installation of
Bridges.
Because the bridges would remain in
their current locations and condition, further disturbance of wildlife
would continue to be avoided.
- View Corridor Maintenance.
Because
vegetation would not be removed to enhance identified view corridors,
further disturbance of wildlife would continue to be avoided.
- Removal of Human-Built Rock-Rubble Pile.
Because
the rock-rubble pile would remain in its current location, further
disturbance of wildlife would continue to be avoided.
Overall, there would be long-term,
negligible, adverse impacts to wildlife under Alternative 1 because
the existing facilities are impacting wildlife habitat continuity;
however, these impacts would be negligible because they would not worsen
over time and would not be measurable or perceptible.
Cumulative Impacts – Regional Setting
Reasonably foreseeable future actions
within Yosemite Valley are considered to have an overall net benefit to
wildlife. For example, the Merced River Plan protects river-related
natural resources through the application of management elements,
including the River Protection Overlay, management zoning, protection and
enhancement of Outstandingly Remarkable Values, and implementation of a
Visitor Experience Resource Protection framework. Full implementation of
the Yosemite Valley Plan would increase the size, continuity, and
integrity of wildlife habitats in Yosemite Valley. Although certain Yosemite
Valley Plan projects, such as improving El Portal Road from the El
Portal/Big Oak Flat Road intersection to Pohono Bridge and expansion of
campgrounds in Yosemite Valley, have the potential to adversely affect
local wildlife, these projects must be designed to ensure the long-term
protection of sensitive vegetation communities consistent with the Merced
River Plan and the Vegetation Management Plan (NPS 1997b). In
addition, implementation of the Visitor Experience and Resource Protection
framework (included in both the Merced River Plan and Yosemite Valley
Plan) will help reduce adverse effects of visitor use on wildlife
habitat and patterns.
Wildlife communities have been
manipulated almost since the inception of the park. Regional wildlife has
been historically affected by logging, fire suppression, rangeland
clearing, grazing, mining, draining, damming, diversions, and the
introduction of non-native species. Park rangers trapped fur-bearing
mammals until 1925; mountain lions were considered dangerous predators and
controlled through the 1920s; and black bears were artificially fed as a
tourist attraction until 1940. Natural wildland fires, with their
generally beneficial effects on wildlife habitat, were routinely
suppressed until 1972. Past and ongoing activities include recreational
use and construction of bridges, diversion walls, roads, pipelines,
riprap, buildings, campgrounds, and other recreational features.
Past, present, and reasonably
foreseeable future actions, in combination with Alternative 1, would have
a net local, long-term, minor to moderate, beneficial effect on wildlife
patterns.
Impairment
Wildlife impacts resulting from
Alternative 1 would not be of sufficient magnitude to constitute
impairment.
Alternative 2
Analysis – Local Setting
- Restroom Relocation. Long-term,
negligible, adverse impact. The relocation of the restroom
would not have any measurable effect on the existing wildlife species or
habitat. The planned location of the new restroom is already disturbed by
existing structures and human activity.
- Parking Area Removal and Establishment of a
Seating/Picnic Area.
Long-term,
negligible, adverse impact. Removal of the parking lot and
establishment of a seating area and picnic area would not have any
measurable adverse effect on existing wildlife habitat. The current
location of the existing parking area is already disturbed by existing
structures and human activity. The presence of picnic tables would
introduce a new area for exposure of wildlife to human food. However,
wildlife-specific mitigation measures, such as signs to deter visitors
from feeding wildlife, bear-proof garbage cans, and regular trash
collection, would largely offset impacts to wildlife.
- New Shuttle Bus Stop.
Long-term, negligible, adverse impact. Establishment of a new shuttle
bus stop would not have any measurable effect on existing wildlife species
or habitat because the location of the new shuttle bus stop is already
disturbed by pavement and human activity.
- Interim Tour Bus Unloading, Loading, and Parking.
Short-term,
negligible, adverse impact. Establishment of new interim tour bus
unloading, loading, and parking locations would not have any measurable
effect on existing wildlife species or habitat because the locations are
already disturbed by pavement and human activity.
- Trail Alignment.
Long-term, negligible, adverse impact. Tree removal due to changes in
trail alignments would eliminate some snags and other mature trees that
provide habitat for birds, bats, and other small mammals. Currently, the
lower forest layers are marginal wildlife habitat because of their
proximity to human uses; therefore, the impact to lower canopy wildlife
users would be negligible. Higher layers of the canopy, however, are less
affected by human uses; therefore, the loss of some mature trees would
have a greater impact on wildlife species or habitat. Wildlife-specific
mitigation measures would be used to minimize adverse impacts to wildlife
species or habitat.
- Rehabilitation of Trails.
Long-term,
negligible, adverse impact. Tree removal due to trail rehabilitation
would eliminate some snags and other mature trees that provide habitat for
birds, bats, and other small mammals. Currently, the lower forest layers
are marginal wildlife habitat because of their proximity to human uses;
therefore, the impact to lower canopy wildlife users would be negligible.
Higher layers of the canopy, however, are less affected by human uses;
therefore, the loss of some mature trees would have a greater impact on
wildlife species or habitat. Wildlife-specific mitigation measures would
be used to minimize adverse impacts to wildlife species or habitat.
- Rehabilitation, Relocation, and Installation of
Bridges.
Long-term, negligible, adverse
impact. Tree removal due to bridge rehabilitation and construction
would eliminate some snags and other mature trees that provide habitat for
birds, bats, and other small mammals. Currently, the lower forest layers
are marginal wildlife habitat due to their proximity to human uses;
therefore, the impact to lower canopy wildlife users would be negligible.
Higher layers of the canopy, however, are less affected by human uses;
therefore, the loss of some mature trees would have a greater impact on
wildlife species or habitat. Wildlife-specific mitigation measures would
be used to minimize adverse impacts to wildlife species or habitat.
- View Corridor Maintenance.
Long-term,
negligible, adverse impact. Tree thinning to maintain the view
corridors would eliminate some snags and other mature trees that provide
habitat for birds, bats, and other small mammals. Currently, the lower
forest layers are marginal wildlife habitat due to their proximity to
human uses; therefore, the impact to lower canopy wildlife users would be
negligible. Higher layers of the canopy, however, are less affected by
human uses; therefore, the loss of some mature trees would have a greater
impact on wildlife species or habitat. Wildlife-specific mitigation
measures would be used to minimize adverse impacts to wildlife species or
habitat.
- Removal of Human-Built Rock-Rubble Pile.
Long-term,
negligible, beneficial impact. The rock-rubble pile removal would
preceded by studies of hydrology, cultural resources, and wetlands, and
appropriate public health and safety measures would be applied.
Overall, there would be a long-term,
negligible, adverse cumulative impact on wildlife species or habitat under
Alternative 2 resulting from tree removal associated with trail alignment
and rehabilitation, bridge rehabilitation and construction, and view
corridor maintenance.
Cumulative Impacts – Regional Setting
The cumulative impact analysis for
wildlife under Alternative 2 is the same as described earlier for
Alternative 1. Cumulative actions would have a local, long-term, minor to
moderate, beneficial cumulative effect on wildlife species or habitat
within Yosemite Valley.
Impairment
Wildlife impacts resulting from
Alternative 2 would not be of sufficient magnitude to constitute
impairment.
Alternative 3
Analysis – Local Setting
- Restroom Relocation. Long-term,
negligible, adverse impact. The relocation of the restroom
would not have any measurable effect on the existing wildlife habitat. The
planned location of the new restroom is already disturbed by existing
structures and human activity.
- Parking Area Removal and Establishment of an Informal
Seating Area.
Long-term, negligible,
adverse impact. Removal of the parking lot and establishment of the
seating area would not have any measurable adverse effect on existing
wildlife habitat. The current location of the existing parking lot is
already disturbed by existing structures and human activity. The presence
of picnic tables in the seating area would introduce a new area for
exposure of wildlife to human food. However, wildlife-specific mitigation
measures such as signs to deter visitors from feeding wildlife would
prevent adverse impacts to wildlife species or habitat.
- New Shuttle Bus Stop.
Long-term, negligible, adverse impact. Establishment of a new shuttle
bus stop would not have any measurable effect on existing wildlife habitat
because the location of the new shuttle bus stop is already disturbed by
pavement and human activity.
- Interim Tour Bus Unloading, Loading, and Parking.
Short-term,
negligible, adverse impact. Establishment of a new interim tour bus
unloading, loading, and parking locations would not have any measurable
effect on existing wildlife species or habitat, because the locations are
already disturbed by pavement and human activity.
- Trail Alignment.
Long-term, negligible, adverse impact. Tree removal resulting from
trail realignments would eliminate some snags and other mature trees that
provide habitat for birds, bats, and other small mammals. Currently, the
lower forest layers are marginal wildlife habitat due to their proximity
to human uses; therefore, the impact to lower canopy wildlife users would
be negligible. Higher layers of the canopy, however, are less affected by
human uses; therefore, the loss of some mature trees would have a greater
impact on wildlife species or habitat. Wildlife-specific mitigation
measures would be used to minimize adverse impacts to wildlife species or
habitat.
- Rehabilitation of Trails.
Long-term,
negligible, adverse impact. Tree removal due to trail rehabilitation
would eliminate some snags and other mature trees that provide habitat for
birds, bats, and other small mammals. Currently, the lower forest layers
are marginal wildlife habitat due to their proximity to human uses;
therefore, the impact to lower canopy wildlife users would be negligible.
Higher layers of the canopy, however, are less affected by human uses;
therefore, the loss of some mature trees would have a greater impact on
wildlife species or habitat. Wildlife-specific mitigation measures would
be used to minimize adverse impacts to wildlife species or habitat.
- Rehabilitation, Relocation, and Installation of
Bridges.
Long-term, negligible, adverse
impact. Tree removal due to bridge rehabilitation and construction
would eliminate some snags and other mature trees that provide habitat for
birds, bats, and other small mammals. Currently, the lower forest layers
are marginal wildlife habitat due to their proximity to human uses;
therefore, the impact to lower canopy wildlife users would be negligible.
Higher layers of the canopy, however, are less affected by human uses;
therefore, the loss of some mature trees would have a greater impact on
wildlife species or habitat. Wildlife-specific mitigation measures would
be used to minimize adverse impacts to wildlife species or habitat.
- View Corridor Maintenance.
Long-term,
negligible, adverse impact. Tree thinning to maintain the view
corridors would eliminate some snags and other mature trees that provide
habitat for birds, bats, and other small mammals. Currently, the lower
forest layers are marginal wildlife habitat due to their proximity to
human uses; therefore, the impact to lower canopy wildlife users would be
negligible. Higher layers of the canopy, however, are less affected by
human uses; therefore, the loss of some mature trees would have a greater
impact on wildlife species or habitat. Wildlife-specific mitigation
measures would be used to minimize adverse impacts to wildlife species or
habitat.
- Removal of Human-Built Rock-Rubble Pile.
Long-term,
negligible, beneficial impact. The rock-rubble pile would be removed
without the benefit of studies of hydrology, cultural resources, and
wetlands being performed and appropriate public health and safety measures
being applied.
Overall, there would be a long-term,
negligible, adverse impact on wildlife species or habitat under
Alternative 3 due to tree removal associated with trail alignment and
rehabilitation, bridge rehabilitation and construction, and view corridor
maintenance.
Cumulative Impacts – Regional Setting
The cumulative impact analysis for
wildlife under Alternative 3 is the same as presented earlier for
Alternative 1. Cumulative actions would have a local, long-term, minor to
moderate, beneficial cumulative effect on wildlife within Yosemite Valley.
Impairment
Wildlife impacts resulting from
Alternative 3 would not be of sufficient magnitude to constitute
impairment.
Special-Status Species
Alternative 1
Analysis – Local Setting
All Alternative 1 Elements.
Fourteen special-status species may be present in the Lower Yosemite Fall
area (including ten bat species). Additional species were considered in
the evaluation for this project but were found to be absent in the Lower
Yosemite Fall area (see Appendix B and the Methodology section in this
chapter). The impacts of all Alternative 1 elements were evaluated for the
following species:
- Bald Eagle (Federal Threatened Species, California
Endangered Species) and Harlequin Duck (Federal Species of Concern,
California Species of Special Concern).
The
bald eagle and harlequin duck are not known to nest in Yosemite Valley
and have not been observed in the Lower Yosemite Fall area in recent
years. The area of effect would be limited and the presence of these
species in the area is unlikely.
- American Peregrine Falcon (California Endangered
Species).
The American peregrine falcon may
forage in the Lower Yosemite Fall area but it does not nest in the area.
Important habitat features would be retained, and a large area of
suitable unaffected habitat would remain in the Lower Yosemite Fall
area.
- Wawona Riffle Beetle (Federal Species of Concern).
Under
Alternative 1, bridge rehabilitation and removal of bridge abutments,
which could enhance potential habitat for the Wawona riffle beetle by
improving natural river flow dynamics, would not be undertaken.
Likewise, pier construction, which could remove a small amount of
potential habitat for the Wawona riffle beetle, would not be undertaken.
- Special-Status Bat Species.
The
pallid bat, small-footed myotis bat, long-eared myotis bat, long-legged
myotis bat, and greater mastiff bat roost and forage in forested areas.
The Townsend’s big-eared bat, spotted bat, fringed myotis bat, and
Yuma myotis bat forage in forested areas. Special-status
species-specific mitigation measures would be used to minimize impacts
to bat species. Bridge rehabilitation, trail relocation, and restroom
relocation activities would not be undertaken and, therefore, these
actions would not affect bats and roosting sites. Important habitat
features would be retained, and a large area of suitable, unaffected
habitat would remain in the Lower Yosemite Fall area.
Overall, there would be long-term,
negligible, adverse impacts to special-status species or their habitat
under Alternative 1.
Cumulative Impacts – Regional Setting
Reasonably foreseeable future actions
within Yosemite Valley are considered to have an overall net benefit to
special-status species. For example, the Merced River Plan protects
river-related natural resources through the application of seven
management elements. Those elements are the River Protection Overlay,
management zoning, protection and enhancement of Outstandingly Remarkable
Values, implementation of a Visitor Experience Resource Protection
framework, classifications, delineation of boundaries, and the Section 7
determination process. Full implementation of the Yosemite Valley Plan
would increase the size, continuity, and integrity of habitats (especially
meadow, riparian, California black oak, and upland habitats) for
special-status species in Yosemite Valley.
Although certain projects set forth in
the Yosemite Valley Plan, such as construction of new lodging and
parking facilities, and expansion of campgrounds in Yosemite Valley, have
the potential to adversely affect local special-status species, these
projects must be designed to ensure the long-term protection of
special-status species consistent with the Merced River Plan and the
Endangered Species Act. In addition, implementation of the Visitor
Experience and Resource Protection framework (included in both the Merced
River Plan and Yosemite Valley Plan) would help reduce adverse
effects of visitor use on special-status species.
Cumulative actions would have a local,
long-term, moderate, beneficial cumulative effect on special-status
species within Yosemite Valley.
Impairment
Special-status species impacts resulting
from Alternative 1 would not be of sufficient magnitude to constitute
impairment.
Alternative 2
Analysis – Local Setting
All Alternative 2 Elements.
Fourteen special-status species may be present in the Lower Yosemite Fall
area (including ten bat species). Additional species were considered in
the evaluation for this project, but were found to be absent in the Lower
Yosemite Fall area (see Appendix B and the Methodology section in this
chapter). The impacts of all Alternative 2 elements were evaluated for the
following species:
- Bald Eagle (Federal Threatened Species, California
Endangered Species) and Harlequin Duck (Federal Species of Concern,
California Species of Special Concern).
Long-term,
negligible, beneficial impact. The bald eagle and harlequin duck are
not known to nest in Yosemite Valley and have not been observed in the
Lower Yosemite Fall area in recent years. The area of effect would be
limited and the presence of these species in the area is unlikely.
- American Peregrine Falcon (California Endangered
Species).
Long-term, negligible,
beneficial impact. The American peregrine falcon may forage in the
Lower Yosemite Fall area but it does not nest in the area. Important
habitat features would be retained, and a large area of suitable
unaffected habitat would remain in the Lower Yosemite Fall area.
- Wawona Riffle Beetle (Federal Species of Concern).
Long-term, minor, beneficial impact. Bridge rehabilitation and
removal of bridge abutments could enhance potential habitat for the
Wawona riffle beetle by improving natural river flow dynamics. This
would be a long-term, moderate, beneficial impact. However, pier
construction could remove a small amount of potential habitat for the
Wawona riffle beetle. The adverse impact from removal of potential
habitat would offset the beneficial impact to a minor level.
- Special-Status Bat Species.
Short-term,
negligible, adverse impact. The pallid bat, the small-footed myotis
bat, the long-eared myotis bat, long-legged myotis bat, and the greater
mastiff bat roost and forage in forested areas. The Townsend’s
big-eared bat, spotted bat, fringed myotis bat, and Yuma myotis bat
forage in forested areas. Selected thinning in the view corridors could
remove potential roost sites and foraging habitat for bats.
Special-status species-specific mitigation measures would be used to
minimize impacts to bat species. Bridge rehabilitation, trail
relocation, and restroom relocation activities would not be expected to
affect bats and roosting sites. Important habitat features would be
retained, and a large area of suitable, unaffected habitat would remain
in the project area.
Overall, there would be long-term,
minor, beneficial impacts under Alternative 2 to the Wawona riffle beetle
from improved river flow dynamics.
Cumulative Impacts – Regional Setting
Cumulative impacts on special-status
species are described under Alternative 1. Cumulative actions, in
particular actions prescribed in the Merced River Plan and the Yosemite
Valley Plan, would have a local, long-term, moderate, beneficial
effect on special-status species in Yosemite Valley.
Impairment
Special-status species impacts resulting
from Alternative 2 would not be of sufficient magnitude to constitute
impairment.
Alternative 3
Analysis – Local Setting
All Alternative 3 Elements. Fourteen
special-status species may be present in the Lower Yosemite Fall area
(including ten bat species). Additional species were considered in the
evaluation for this project, but were found to be absent in the Lower
Yosemite Fall area (see Appendix B and Methodology, this chapter). The
impacts of all Alternative 3 elements were evaluated for the following
species:
- Bald Eagle (Federal Threatened Species, California
Endangered Species) and Harlequin Duck (Federal Species of Concern,
California Species of Special Concern).
Long-term,
negligible, beneficial impact. The bald eagle and harlequin duck are
not known to nest in Yosemite Valley and have not been observed in the
Lower Yosemite Fall area in recent years. The affected area would be
limited, and the presence of these species in the area is unlikely.
- American Peregrine Falcon (California Endangered
Species).
Long-term, negligible,
beneficial impact. The American peregrine falcon may forage in the
Lower Yosemite Fall area, but it does not nest in the area. Important
habitat features would be retained, and a large area of suitable
unaffected habitat would remain in the Lower Yosemite Fall area.
- Wawona Riffle Beetle (Federal Species of Concern).
Long-term,
minor, beneficial impact. Bridge rehabilitation and removal of
bridge abutments could enhance potential habitat for the Wawona riffle
beetle by improving natural river flow dynamics. This would be a
long-term, moderate, beneficial impact. However, pier construction could
remove a small amount of potential habitat for the Wawona riffle beetle.
The adverse impact from removal of potential habitat would offset the
beneficial impact to a minor level.
- Special-Status Bat Species.
Short-term,
negligible, adverse impact. The pallid bat, small-footed myotis bat,
long-eared myotis bat, long-legged myotis bat, and greater mastiff bat
roost and forage in forested areas. The Townsend’s big-eared bat,
spotted bat, fringed myotis bat, and Yuma myotis bat forage in forested
areas. Selected thinning in the view corridors could remove potential
roost sites and foraging habitat for bats. Special-status
species-specific mitigation measures would be used to minimize impacts
to bat species. Bridge rehabilitation, trail relocation, and restroom
relocation activities are not expected to affect bats and roosting
sites. Important habitat features would be retained, and a large area of
suitable, unaffected habitat would remain in the Lower Yosemite Fall
area.
Overall, there would be long-term,
minor, beneficial impacts under Alternative 3 to the Wawona riffle beetle
from improved river flow dynamics.
Cumulative Impacts – Regional Setting
Cumulative impacts on special-status
species are described under Alternative 1. Cumulative actions, in
particular actions prescribed in the Merced River Plan and the Yosemite
Valley Plan, would have a local, long-term, moderate, beneficial
effect on special-status species in Yosemite Valley.
Impairment
Because impacts to special-status
species would be negligible under Alternative 3, this alternative would
not result in impairment of park resources.
Air Quality
Alternative 1
Analysis – Local Setting
- Restroom Location. The
existing restroom would continue to have no effect on air quality in the
Lower Yosemite Fall area.
- Parking Area.
Long-term,
negligible, adverse impact. Private automobiles and commercial buses
would continue to access and park in the parking area. Emissions from
these buses and automobiles would continue to adversely affect air quality
in the area although, as older vehicles are replaced with newer, cleaner
vehicles, emissions would decrease. The existing parking area would not be
removed; therefore, there would be no emissions from motorized
construction equipment. No additional cars or buses would be attracted to
the Lower Yosemite Fall area.
- Shuttle Bus Stop.
There would
be no additional impacts from the emissions of shuttle buses that
currently park in the parking lot beyond those from private automobiles.
Shuttle buses are not allowed to idle in the parking area for long periods
of time.
- Tour Bus Unloading, Loading, and Parking.
There
would be no additional impacts from the emissions of tour buses that
currently park in the parking area. Tour buses are not allowed to idle in
the parking area for long periods of time.
- Trail Alignment.
The existing
trail alignments would continue to have no effect on air quality in the
area.
- Rehabilitation of Trails.
The
existing condition of trails would continue to have no effect on air
quality in the area.
- Rehabilitation, Relocation, and Installation of
Bridges.
The existing condition of the bridges
would continue to have no effect on air quality in the area.
- View Corridor Maintenance.
No
trees or vegetation would be removed to maintain view corridors. The lack
of vista maintenance in the area would not affect air quality.
- Removal of Human-Built Rock-Rubble Pile.
The
rock-rubble pile would continue in its current location.
Overall, there would be a long-term,
negligible, adverse impact to air quality under Alternative 1 due to the
concentration of vehicle emissions in the existing parking area.
Cumulative Impacts – Regional Setting
Although cumulative growth in the region
would tend to adversely affect air quality, implementation of ongoing
state and federal mobile-source control programs would ameliorate this
effect to a degree. Considered with the adverse impacts associated with
regional air quality influences, the cumulative projects in combination
with Alternative 1 would have a local, long-term, moderate, beneficial
effect on air quality in Yosemite Valley.
Impairment
Air quality impacts resulting from
Alternative 1 would not be of sufficient magnitude to constitute
impairment.
Alternative 2
Analysis – Local Setting
- Restroom Relocation. Short-term,
negligible, adverse impact. Air-quality-specific mitigation
measures (e.g., dust abatement) would be used during restroom demolition
and construction to largely offset adverse impacts to air quality from
these activities.
- Parking Area Removal and Establishment of
Seating/Picnic Area.
Long-term, negligible,
adverse impact. Under Alternative 2, the parking area would be
relocated and day tour buses would be redirected to an area near Camp 4
west of Yosemite Lodge. Cars would ultimately be directed to a 550-space
parking area in Yosemite Village. Localized air quality impacts associated
with these vehicles would shift from the Lower Yosemite Fall area to these
new locations. However, air quality impacts would be largely offset
because there would be no change in the number of tour buses.
Air-quality-specific mitigation measures (e.g., dust abatement) would be
used during parking removal and seating area construction to prevent
adverse impacts to air quality from these activities.
- New Shuttle Bus
Stop.
Long-term, negligible, adverse
impact. Under Alternative 2, shuttle buses would stop for a short time
to load and unload passengers at a new location along Northside Drive.
However, no additional impact to air quality would result from shuttle
buses stopping at this location because Northside Drive is already a major
thoroughfare for vehicles and buses and the number of shuttle buses would
be the same as under Alternative 1. Shuttle buses would not be
allowed to idle for long periods of time.
- Interim Tour Bus Unloading, Loading, and Parking.
Short-term,
negligible, adverse impact. Under Alternative 2, tour buses would be
temporarily parked at an area near Camp 4 west of Yosemite Lodge.
Localized air quality impacts associated with these vehicles would shift
from the Lower Yosemite Fall area to this new location. However, there
would be a negligible impact to air quality from tour buses because there
would be less than 200 additional vehicle miles traveled per day by the
buses, the road is already a major thoroughfare for vehicles and buses,
and tour buses would not be allowed to idle for long periods of time.
- Trail Alignment.
Short-term,
negligible, adverse impact. Air-quality-specific mitigation measures
(e.g., dust abatement) would be used during trail alignment activities to
largely offset adverse impacts to air quality.
- Rehabilitation of Trails.
Short-term,
negligible, adverse impact. Air-quality-specific mitigation measures
(e.g., dust abatement) would be used during trail rehabilitation
activities to largely offset adverse impacts to air quality.
- Rehabilitation, Relocation, and Installation of
Bridges.
Short-term, negligible, adverse
impact. Air-quality-specific mitigation measures (e.g., dust
abatement) would be used during bridge rehabilitation and construction to
largely offset adverse impacts to air quality from these activities.
- View Corridor Maintenance.
Long-term,
negligible, adverse impact. Tree and vegetation removal for vista
maintenance would not have a measurable effect on air quality in the area.
- Removal of Human-Built Rock-Rubble Pile.
Long-term,
negligible, adverse impact. The rock-rubble pile removal would be
preceded by studies of hydrology, cultural resources, and wetlands, and
appropriate public health and safety measures would be applied.
Overall, there would be a long-term,
minor, adverse impact on air quality under Alternative 2 because
vehicle emissions would remain unchanged but shift from the Lower Yosemite
Fall area to other areas in Yosemite Valley.
Cumulative Impacts – Regional Setting
Although cumulative growth in the region
would tend to adversely affect air quality, implementation of ongoing
state and federal mobile-source control programs would ameliorate this
effect to a degree. With respect to particulate matter, conditions in the
Valley would be determined by both regional sources and local sources, and
could be beneficial or adverse. Considered with the adverse impacts
associated with regional air quality influences, the cumulative projects
would have a local, long-term, moderate, beneficial effect on air quality
in Yosemite Valley.
Alternative 2 and the cumulative
projects would result in local, long-term, moderate, beneficial impacts on
air quality.
Impairment
Air quality impacts resulting from
Alternative 2 would not be of sufficient magnitude to constitute
impairment.
Alternative 3
Analysis – Local Setting
- Restroom Relocation. Short-term,
negligible, adverse impact. Air-quality-specific mitigation
measures (e.g., dust abatement) would be used during restroom demolition
and construction to largely offset adverse impacts to air quality from
these activities.
- Parking Area Removal and Establishment of
Seating/Picnic Area.
Long-term, negligible,
adverse impact. Under Alternative 3, the parking area would be
relocated and day tour buses would be redirected to an area near Camp 4
west of Yosemite Lodge. Cars would ultimately be directed to a 550-space
parking area in Yosemite Village. Localized air quality impacts associated
with these vehicles would shift from the Lower Yosemite Fall area to these
new locations. However, air quality impacts would be largely offset
because there would be no change in the number of tour buses.
Air-quality-specific mitigation measures (e.g., dust abatement) would be
used during parking removal and seating area construction to largely
offset adverse impacts to air quality from these activities.
- New Shuttle Bus Stop.
Long-term,
negligible, adverse impact. Under Alternative 3, shuttle buses would
stop for a short time to load and unload passengers at a new location
along Northside Drive. No additional impact to air quality would result
from shuttle buses stopping at this location because Northside Drive is
already a major thoroughfare for vehicles and buses and the number of
shuttle buses would be the same as for Alternative 1. Shuttle buses would
not be allowed to idle for long periods of time.
- Interim Tour Bus Unloading, Loading, and Parking.
Short-term,
negligible, adverse impact. Under Alternative 3, tour buses would be
temporarily parked at an area near Camp 4 west of Yosemite Lodge.
Localized air quality impacts associated with these vehicles would shift
from the Lower Yosemite Fall area to this new location. However, there
would be a negligible impact to air quality from tour buses because there
would be less than 200 additional vehicle miles traveled per day by the
buses, the road is already a major thoroughfare for vehicles and buses,
and tour buses would not be allowed to idle for long periods of time.
- Trail Alignment.
Short-term,
negligible, adverse impact. Air-quality-specific mitigation measures
(e.g., dust abatement) would be used during trail alignment activities to
largely offset adverse impacts to air quality.
- Rehabilitation of Trails.
Short-term,
negligible, adverse impact. Air-quality-specific mitigation measures
(e.g., dust abatement) would be used during trail rehabilitation
activities to largely offset adverse impacts to air quality.
- Rehabilitation, Relocation, and Installation of
Bridges.
Short-term, negligible, adverse
impact. Air-quality-specific mitigation measures (e.g., dust
abatement) would be used during bridge rehabilitation and construction to
largely offset adverse impacts to air quality from these activities.
- View Corridor Maintenance.
Long-term,
negligible, adverse impact. Tree and vegetation removal for vista
maintenance would not have a measurable effect on air quality in the area.
- Removal of Human-Built Rock-Rubble Pile.
Long-term,
negligible, adverse impact. Removal of the rock-rubble pile would not
affect air quality. The rock-rubble pile would be removed without the
benefit of studies on hydrology, cultural resources, and wetlands being
performed and appropriate public health and safety protection measures
being applied.
Overall, there would be a long-term,
minor, adverse impact on air quality under Alternative 3 because
vehicle emissions would remain unchanged but shift from the Lower Yosemite
Fall area to other areas in Yosemite Valley.
Cumulative Impacts – Regional Setting
Although cumulative growth in the region
will tend to adversely affect air quality, implementation of ongoing state
and federal mobile-source control programs would ameliorate this effect to
a degree. With respect to particulate matter, conditions in the Valley
would be determined by both regional sources and local sources, and could
be beneficial or adverse. Considered with the adverse impacts associated
with regional air quality influences, the cumulative projects would have a
local, long-term, moderate, beneficial effect on air quality in Yosemite
Valley.
Alternative 3 and the cumulative
projects would result in local, long-term, moderate, beneficial impacts on
air quality.
Impairment
Air quality impacts resulting from
Alternative 3 would not be of sufficient magnitude to constitute
impairment.
Noise
Alternative 1
Analysis – Local Setting
- Restroom Location. The
existing restroom would not be removed. The limited number of fixtures at
the current restroom would continue to contribute to the amount of time
visitors may congregate and wait in the area to use restroom services.
Human activity in the area would continue to contribute to noise levels in
the area.
- Parking Area.
Private
automobiles would continue to access and park in the parking area.
Visitors would continue to congregate and create noise at the south
approach to the western trail. Vehicle noise and human activity would
continue to contribute to noise levels in the area.
- Shuttle Bus Stop.
Shuttle
buses would continue to stop in the parking area, with visitors
congregating at the south approach to the western trail. Vehicle noise and
human activity would continue to contribute to noise levels in the area.
- Tour Bus Unloading, Loading, and Parking.
Private
automobiles would continue to access and park in the parking area, with
visitors congregating at the south approach to the western trail. Vehicle
noise and human activity would continue to contribute to noise levels in
the area.
- Trail Alignment.
The current
alignment of trails in the area would continue to have no effect on noise
levels.
- Rehabilitation of Trails.
The
current condition of trails in the area would continue to have no effect
on noise levels.
- Rehabilitation, Relocation, and Installation of
Bridges.
The current condition of bridges in
the area would continue to have no effect on noise levels.
- View Corridor Maintenance.
No
trees or vegetation would be removed; therefore, there would continue to
be no noise generated from vista maintenance activities.
- Removal of Human-Built Rock-Rubble Pile.
Removal
of the rock-rubble pile would continue not to affect noise levels.
Overall, there would be a long-term,
minor, adverse impact on noise levels under Alternative 1 as a result of
vehicles accessing and parking in the parking area.
Cumulative Impacts – Regional Setting
Reasonably foreseeable future actions
proposed for Yosemite Valley could have beneficial or adverse impacts on
noise. For example, the National Park Service’s Shuttle Bus Replacement
Project could have a net beneficial effect on the ambient noise
environment by improving the attractiveness of alternative modes of
transportation, thereby reducing private automobile trips. Although the
Shuttle Bus Replacement Project would have localized, short-term, adverse
noise effects, the general goal of the project is to relieve congestion
and provide for alternative means of transportation within Yosemite
Valley. To the extent that transportation-related projects would replace
automobile trips in the Valley with bus trips, the anticipated beneficial
effect would depend upon ridership levels (and the corresponding number of
automobile trips that would be avoided) and the technology selected for
the buses. Overall, general sound levels associated with traffic along
most roadways in the Valley would be reduced, thus representing a
long-term, beneficial impact.
Other reasonably foreseeable future
National Park Service projects not anticipated to have a net adverse or
beneficial effect on the ambient noise environment (except for short-term,
localized impacts during construction) include the
Replacement/Rehabilitation of Yosemite Valley Main Sewer Line, Merced
River at Eagle Creek Ecological Restoration (Yosemite Valley), Trail
Reconstruction from Happy Isles to Vernal Fall, Repair Flood Damaged Trail
Bridges at Happy Isles, and Happy Isles Site Improvements.
Impairment
Noise impacts resulting from Alternative
1 would not be of sufficient magnitude to constitute impairment.
Alternative 2
Analysis – Local Setting
- Restroom Relocation.
Long-term, minor, adverse impact. Removal of the existing restroom
would reduce the amount of noise at the southern approach to the western
trail, but this noise source would be relocated elsewhere. Noise-specific
mitigation measures used during restroom demolition and construction would
largely offset short-term, adverse impacts to noise levels from these
activities.
- Parking Area Removal and Establishment of
Seating/Picnic Area.
Long-term, minor,
adverse impact. Under Alternative 2, the parking area would be removed
and cars and buses would be redirected to the Yosemite Lodge parking area
(overnight buses and cars) and an area near Camp 4 west of Yosemite Lodge
(day tour buses). The noise generated from these vehicles would be
eliminated from the Lower Yosemite Fall area, but would be relocated to
the replacement parking area at Yosemite Village. The seating area would
provide a quiet setting for visitors to enjoy views of Yosemite Falls.
Noise-specific mitigation measures used during parking area removal and
seating/picnic area construction would largely offset adverse impacts to
noise levels from these activities.
- New Shuttle Bus Stop.
Long-term, minor, beneficial impact. The replacement of the current
shuttle bus stop with a new stop along Northside Drive would further
reduce the amount of vehicle and human activity noise at the south
approach of the western trail. Shuttle buses stopping at the new location
would not have a measurable effect on noise levels along Northside Drive
because this road already experiences noise from current traffic levels.
- Interim Tour Bus Unloading, Loading, and Parking.
Short-term,
minor, adverse impact. Under Alternative 2, tour buses that currently
unload and board passengers in the parking area would be redirected to the
interim dropoff and pickup zone along Northside Drive (for loading and
unloading passengers) and to an area near Camp 4 west of Yosemite Lodge
(for interim parking). The noise generated from these vehicles would be
eliminated from the Lower Yosemite Fall area, but would temporarily
increase noise levels in the Camp 4 area during certain times of the day
(i.e., mid-day). The addition of the tour bus unloading and loading zone
would not have a measurable effect on noise levels along Northside Drive
because this road already experiences noise from current traffic levels.
- Trail Alignment.
Short-term,
negligible, adverse impact. Noise-specific mitigation measures used
during trail alignment would largely offset adverse impacts to noise
levels from this activity.
- Rehabilitation of Trails.
Short-term,
negligible, adverse impact. Noise-specific mitigation measures used
during trail rehabilitation would largely offset adverse impacts to noise
levels from these activities.
- Rehabilitation, Relocation, and Installation of
Bridges.
Short-term, negligible, adverse
impact. Noise-specific mitigation measures used during bridge
rehabilitation and construction would largely offset adverse impacts to
noise levels from these activities.
- View Corridor Maintenance.
Long-term,
negligible, adverse impact. Tree and vegetation removal for vista
maintenance would not have a measurable effect on noise levels in the
area.
- Removal of Human-Built Rock-Rubble Pile.
Short-term,
negligible, adverse impact. The rock-rubble pile removal would be
preceded by studies of hydrology, cultural resources, and wetlands, and
appropriate public health and safety measures would be applied.
Noise-specific mitigation measures used during removal of the rock-rubble
pile would largely offset adverse impacts to noise levels from this
activity.
Overall, there would be long-term,
minor, adverse impacts on noise levels in the Lower Yosemite Fall area
under Alternative 2 due to the removal of the parking area and associated
cars and buses, but some of these impacts would be shifted to other areas
in the Valley.
Cumulative Impacts – Regional Setting
The cumulative impacts analysis under
Alternative 2 is the same as presented earlier for Alternative 1.
Impairment
Noise impacts resulting from Alternative
2 would not be of sufficient magnitude to constitute impairment.
Alternative 3
Analysis – Local Setting
- Restroom Relocation.
Long-term, negligible, adverse impact. Removal of the existing
restroom would reduce the amount of noise from human activity at the
southern approach to the western trail, but this noise would be shifted
elsewhere. However, placement of the new restroom near the trail leading
from Northside Drive to Bridge #6 would increase noise levels in this
area. The adverse impact from noise generated at the new restroom location
would mitigate the long-term, minor, beneficial impact from noise
reduction in the existing restroom area to a negligible level.
Noise-specific mitigation measures used during restroom demolition and
construction would largely offset short-term, adverse impacts to noise
levels from these activities.
- Parking Area Removal and Establishment of an Informal
Seating Area.
Long-term, minor, adverse
impact. Under Alternative 3, the parking area would be removed
and cars and buses would be redirected to the Yosemite Lodge parking area
(overnight buses and cars) and an area near Camp 4 west of Yosemite Lodge
(day tour buses). The noise generated from these vehicles would be
eliminated from the Lower Yosemite Fall area but relocated to the
replacement parking area in Yosemite Village. The seating area would
provide a quiet setting for visitors to enjoy views of Yosemite Falls.
Noise-specific mitigation measures used during parking lot removal and
seating area construction would largely offset adverse impacts to noise
levels from these activities.
- New Shuttle Bus Stop.
Long-term, minor, beneficial impact. The replacement of the current
shuttle bus stop with a new one along Northside Drive would further reduce
the amount of vehicle and human activity noise at the south approach to
the western trail. Shuttle buses stopping at the new location would not
have a measurable effect on noise levels along Northside Drive because
this road already experiences noise from current traffic levels.
- Interim Tour Bus Unloading, Loading, and Parking.
Short-term,
minor, adverse impact. Under Alternative 3, tour buses that
currently unload and board passengers in the parking area would be
redirected to the interim dropoff and pickup zone along Northside Drive
(for loading and unloading passengers) and to an area near Camp 4 west of
Yosemite Lodge (for parking). The noise generated from these vehicles
would be eliminated from this area but would temporarily increase noise
levels near Camp 4. The addition of the tour bus unloading and loading
zone would not have a measurable effect on noise levels along Northside
Drive because this road already experiences noise from current traffic
levels.
- Trail Alignment.
Short-term,
negligible, adverse impact. Noise-specific mitigation measures used
during trail alignment activities would largely offset adverse impacts to
noise levels.
- Rehabilitation of Trails.
Short-term,
negligible, adverse impact. Noise-specific mitigation measures used
during trail rehabilitation would largely offset adverse impacts to noise
levels.
- Rehabilitation, Relocation, and Installation of
Bridges.
Long-term, negligible, adverse
impact. Noise-specific mitigation measures used during bridge
rehabilitation and construction would largely offset adverse impacts to
noise levels from these activities.
- View Corridor Maintenance.
Long-term,
negligible, adverse impact. Tree and vegetation removal for vista
maintenance would not have a measurable effect on noise levels in the
area.
- Removal of Human-Built Rock-Rubble Pile.
Short-term,
negligible, adverse impact. The rock-rubble pile would be removed
without the benefit of studies on hydrology, cultural resources, and
wetlands being performed and appropriate public health and safety
protection measures being applied. Noise-specific mitigation measures used
during removal of the rock-rubble pile would largely offset adverse
impacts to noise levels from this activity.
Overall, there would be a long-term,
minor, adverse impact on noise levels in the Lower Yosemite Fall area
under Alternative 3 resulting from the removal of the parking area and
associated cars and buses, but some of these impacts would be shifted to
other areas.
Cumulative Impacts
The cumulative impacts analysis for
Alternative 3 is the same as presented for Alternative 1.
Impairment
Noise impacts resulting from Alternative
3 would not be of sufficient magnitude to constitute impairment.
Cultural Resources
Archeological Resources
Alternative 1
Analysis – Local Setting
- Restroom Location. Long-term,
minor, adverse impact. Although the restroom would remain in
its current location, it would continue to present a long-term, minor,
adverse impact to archeological site CA-Mrp-240/303/H.
- Parking Area.
Long-term,
minor, adverse impact. Although the parking area would remain
in its current location, it would continue to present a long-term, minor,
adverse impact to archeological site CA-Mrp-240/303/H.
- Shuttle Bus Stop.
Long-term,
minor, adverse impact. Although the shuttle bus stop would
remain in its current location, it would continue to present a long-term,
minor, adverse impact to archeological site CA-Mrp-240/303/H.
- Tour Bus Unloading, Loading, and Parking.
Long-term,
minor, adverse impact. Although tour bus operations would
remain within the existing parking area, they would continue to present a
long-term, minor, adverse impact to archeological site CA-Mrp-240/303/H.
- Trail Alignment.
Long-term,
minor, adverse impact. The trails would remain in their current
alignments, presenting a long-term, minor, adverse impact to the Hutchings
sawmill and Camp Lost Arrow site.
- Rehabilitation of Trails.
Since
the trails would remain in their current condition, including normal
maintenance and repair, no disturbance of archeological resources would
occur.
- Rehabilitation, Relocation, and Installation of
Bridges.
Since the bridges would remain in
their current locations and condition, including normal maintenance and
repair (including Bridge #6, which is currently collapsed and would
therefore be rebuilt), no disturbance of archeological resources would
occur.
- View Corridor Maintenance.
Since
vegetation would not be removed to enhance identified view corridors, no
disturbance of archeological resources would occur.
- Removal of Human-Built Rock-Rubble Pile.
Since
the rock-rubble pile would remain in its current location, no disturbance
of archeological resources would occur.
Overall, there would be long-term,
minor, adverse impacts to archeological resources under Alternative 1 due
to the existing restroom location, parking area location, and trail
alignments.
Cumulative Impacts – Regional Setting
Reasonably foreseeable future actions
proposed in the region that could have an adverse cumulative effect on
archeological resources in Yosemite Valley include development-related
projects, such as implementing the Yosemite Valley Plan, the
Replacement/Rehabilitation of Yosemite Valley Main Sewer Line, and the
Merced River at Eagle Creek Ecological Restoration. The extensive grading
and ground disturbance likely required for these projects could disturb
individual archeological resources. Each of these projects is near the
main stem of the Merced River, which is an archeologically sensitive area.
Implementation of the Yosemite Valley Plan would have a local,
long-term, minor, adverse cumulative effect on cultural resources in
Yosemite Valley resulting from possible disturbance associated with
earth-moving, construction, and demolition projects. The National Park
Service would follow guidelines of the 1999 Programmatic Agreement and
avoid adverse effects to archeological resources to the greatest extent
feasible. In combination with Alternative 1, the other projects
within and in the vicinity of the Lower Yosemite Fall area would have no
further cumulative impact on archeological resources beyond those analyzed
in the Yosemite Valley Plan.
Impairment
Archeological resource impacts resulting
from Alternative 1 would not be of sufficient magnitude to constitute
impairment.
Alternative 2
Analysis – Local Setting
- Restroom Relocation. Long-term,
minor, adverse impact. Long-term, moderate, adverse impacts to
archeological site CA-Mrp-240/303/H would occur through the grading and
removal of intact cultural deposits. This impact would be reduced to the
extent possible through archeological data recovery excavations and
site-specific construction monitoring. Thus, the adverse impact to this
site would be reduced in intensity from moderate to minor.
- Parking Area Removal and Establishment of
Seating/Picnic Area.
Long-term, negligible,
adverse impact. Long-term, minor, adverse impacts to archeological
site CA-Mrp-240/303/H would occur through the careful grading and
potential removal of cultural deposits. These impacts would be reduced to
the extent possible through archeological data recovery excavations and
site-specific construction monitoring. Thus, the adverse impacts to this
site would be reduced in intensity from minor to negligible.
- New Shuttle Bus Stop.
Long-term,
minor, adverse impact. Long-term, moderate, adverse impacts to
archeological site CA-Mrp-749 would occur through the grading and removal
of intact cultural deposits. These impacts would be reduced to the extent
possible through archeological data recovery excavations and site-specific
construction monitoring. Thus, the adverse impacts to this site would be
reduced in intensity from moderate to minor.
- Interim Tour Bus Unloading, Loading, and Parking.
Negligible
impact. Because no ground disturbing activities would be required with
this action, archeological deposits would not be disturbed.
- Trail Alignment.
Long-term,
minor, adverse impact. Long-term, moderate, adverse impacts to
archeological sites CA-Mrp-240/303/H, CA-Mrp-749, YC-5, YC-12, and the
Rock Ring could occur through the grading and removal of intact cultural
deposits. These impacts would be reduced to the extent possible through
avoidance, archeological data recovery excavations, and site-specific
construction protection and monitoring. Thus, the adverse impacts to these
sites would be reduced in intensity from moderate to minor.
- Rehabilitation of Trails.
Long-term,
minor, adverse impact. Long-term, moderate, adverse impacts to
archeological sites CA-Mrp-240/303/H, CA-Mrp-749, YC-5, and YC-12 could
occur through the grading and removal of intact cultural deposits. These
impacts would be reduced to the extent possible through archeological data
recovery excavations and site-specific construction monitoring. Thus, the
adverse impacts to these sites would be reduced in intensity from moderate
to minor.
- Rehabilitation, Relocation, and Installation of
Bridges.
Long-term, minor, adverse impact.
Long-term, moderate, adverse impact to archeological site YC-5 would occur
through the grading and removal of intact cultural deposits. This impact
would be reduced to the extent possible through archeological data
recovery excavations and site-specific construction monitoring. Thus, the
adverse impacts to this site would be reduced in intensity from moderate
to minor.
- View Corridor Maintenance.
Negligible
impact. As view corridor maintenance would not occur within the
boundaries of archaeological sites, cultural deposits would not be
disturbed.
- Removal of Human-Built Rock-Rubble Pile.
Negligible
impact. The rock-rubble pile is not situated within the confines of a
known archeological resource. As such, the removal of the pile would not
disturb archaeological deposits.
Overall, there would be local,
long-term, minor, adverse impacts to archeological resources under
Alternative 2 due to the restroom location, new shuttle bus stop location,
trail alignments, and bridge rehabilitation.
Cumulative Impacts – Regional Setting
The effects of
cumulative actions on archeological resources have been described
previously for Alternative 1. The cumulative projects within and in
the vicinity of the Lower Yosemite Fall area would result in a local,
long-term, minor, adverse impact on archeological resources as a result of
the potential disturbance of such resources. In combination with
Alternative 2, these impacts would be increased to a moderate level
of intensity.
Impairment
Archeological resource impacts resulting
from Alternative 2 would not be of sufficient magnitude to constitute
impairment.
Alternative 3
Analysis – Local Setting
- Restroom Relocation. Long-term,
minor, adverse impact. Long-term, moderate, adverse impacts to
archeological sites CA-Mrp-240/303/H and CA-Mrp-749 would occur through
the grading and removal of intact cultural deposits. These impacts would
be reduced to the extent possible through archeological data recovery
excavations and site-specific construction monitoring. Therefore, the
adverse impacts to these sites would be reduced in intensity from moderate
to minor.
- Parking Area Removal and Establishment of an Informal
Seating Area.
Long-term, minor, adverse
impact. Long-term, moderate, adverse impacts to archeological site
CA-Mrp-240/303/H would occur through the grading and removal of intact
cultural deposits. These impacts would be reduced to the extent possible
through capping the site with dirt, archeological data recovery
excavations, and site-specific construction monitoring. Thus, the adverse
impacts to this site would be reduced in intensity from moderate to minor.
- New Shuttle Bus Stop.
Long-term,
minor, adverse impact. Long-term, moderate, adverse impacts to
archeological site CA-Mrp-749 would occur through the grading and removal
of intact cultural deposits. These impacts would be reduced to the extent
possible through archeological data recovery excavations and site-specific
construction monitoring. Thus, the adverse impacts to this site would be
reduced in intensity from moderate to minor.
- Interim Tour Bus Unloading, Loading, and Parking.
Negligible
impact. As no ground disturbing activities are required with this
project component, archeological deposits would not be disturbed.
- Trail Alignment.
Long-term,
minor, adverse impact. Long-term, moderate, adverse impacts to
archeological sites CA-Mrp-240/303/H, CA-Mrp-749, YC-5, YC-12, and the
Rock Ring could occur through the grading and removal of intact cultural
deposits. In addition, the eastern trail would go over the millrace
feature on site YC-5 (Hutchings sawmill site). These impacts would be
reduced to the extent possible through archeological data recovery
excavations and site-specific construction monitoring. Thus, the adverse
impacts to these sites would be reduced in intensity from moderate to
minor.
- Rehabilitation of Trails.
Long-term,
minor, adverse impact. Long-term, moderate, adverse impacts to
archeological sites CA-Mrp-240/303/H, CA-Mrp-749, YC-5, and YC-12 could
occur through the grading and removal of intact cultural deposits. These
impacts would be reduced to the extent possible through archeological data
recovery excavations and site-specific construction monitoring. Thus, the
adverse impacts to these sites would be reduced in intensity from moderate
to minor.
- Rehabilitation, Relocation, and Installation of
Bridges.
Long-term, minor, adverse impact.
Long-term, moderate, adverse impacts to archeological site YC-5 would
occur through the grading and removal of intact cultural deposits. These
impacts would be reduced to the extent possible through archeological data
recovery excavations and site-specific construction monitoring. Thus, the
adverse impacts to this site would be reduced in intensity from moderate
to minor.
- View Corridor Maintenance.
Negligible
impact. Because view corridor maintenance would not occur within the
boundaries of archaeological sites, cultural deposits would not be
disturbed.
- Removal of Human-Built Rock-Rubble Pile.
Negligible
impact. The rubble-pile is not situated within the confines of a known
archeological resource. As such, the removal of the pile would not disturb
archaeological deposits.
Overall there would be local, long-term,
minor, adverse impacts to archeological resources under Alternative 3 from
the restroom location, parking area removal, new shuttle bus stop, trail
alignments, and bridge rehabilitation.
Cumulative Impacts – Regional Setting
The effects of cumulative actions on
archeological resources have been described previously for
Alternative 1. The cumulative projects within and in the vicinity of
the Lower Yosemite Fall area would result in a local, long-term,
negligible to minor, adverse impact on archeological resources as a result
of the potential disturbance of such resources. In combination with
Alternative 3, these impacts would be increased to a moderate level
of intensity.
Impairment
Archeological resource impacts resulting
from Alternative 3 would not be of sufficient magnitude to constitute
impairment.
Ethnographic Resources
Alternative 1
Analysis – Local Setting
- Restroom Location. Long-term,
minor, adverse impact. Although the restroom would remain in its
current location, it would continue to present a long-term, minor, adverse
impact on the Koom-I-ne and bedrock milling feature resources.
- Parking Area.
Long-term,
minor, adverse impact. Although the parking area would remain in its
current location, it would continue to present a long-term, minor, adverse
impact to the Koom-I-ne and bedrock milling feature resources.
- Shuttle Bus Stop.
Long-term,
minor, adverse impact. Although the shuttle bus stop would remain in
its current location, it would continue to present a long-term, minor,
adverse impact to the Koom-I-ne and bedrock milling feature
resources.
- Tour Bus Unloading, Loading, and Parking.
Long-term,
minor, adverse impact. Although tour bus operations would remain
within the existing parking area, and no construction would occur, they
would continue to present a long-term, minor, adverse impact to the Koom-I-ne
and bedrock milling feature resources.
- Trail Alignment.
Long-term,
minor, adverse impact. Since the trails would remain in their current
alignments, the existing designated trails, network of undesignated trails
(social trails), and the existing Valley Loop trail would continue to
cause disturbance of ethnographic resources.
- Rehabilitation of Trails.
Long-term,
minor, adverse impact. Since the trails would remain in their current
condition except for normal maintenance and repair, disturbance of
ethnographic resources would occur due to construction; however, because
trails through ethnographic resources would remain in their current
condition, no barriers would prevent additional disturbance to these
resources.
- Rehabilitation, Relocation, and Installation of
Bridges.
Since the bridges would remain in
their current locations and condition (except for normal maintenance and
repair such as rebuilding Bridge #6, which recently collapsed), no
disturbance of ethnographic resources would occur.
- View Corridor Maintenance.
Since
vegetation would not be removed to enhance identified view corridors, no
disturbance of ethnographic resources would occur.
- Removal of Human-Built Rock-Rubble Pile.
Since
the rock-rubble pile would remain in its current location, no disturbance
of ethnographic resources would occur.
Overall, there would be long-term,
minor, adverse impacts to ethnographic resources under Alternative 1 from
the locations of the existing restroom, parking area, and shuttle bus
stop.
Cumulative Impacts – Regional Setting
Ethnographic resources and their
traditional cultural associations have been lost or damaged in Yosemite
Valley through past development, visitor use, natural events, and
widespread disruption of cultural traditions. Nevertheless, Yosemite
National Park retains many sites and resources of significance to local
and culturally associated American Indians.
In general, the ethnographic resources
within the main stem of the Merced River are the result of thousands of
years of human occupation. Development of facilities within Yosemite
Valley has disturbed or destroyed numerous ethnographic resources and
compromised the integrity of numerous other such resources, which has had
an adverse cumulative effect on ethnographic resources.
Reasonably foreseeable future actions
proposed in the Yosemite Valley Plan within the local area and the
region could have a beneficial cumulative impact on ethnographic resources
at the Lower Yosemite Fall area (see the Final Yosemite Valley Plan/SEIS,
Vol. Ib, Chapter 4, page 4.2-143).
Another example of a reasonably
foreseeable future project that could beneficially affect ethnographic
resources in Yosemite Valley is the Merced River at Eagle Creek Ecological
Restoration project. This project could restore native plant habitat,
which would be a long-term, beneficial impact on ethnographic resources.
The intensity of this impact would depend on the extent to which gathering
sites were restored and access to traditional use areas was continued.
Other projects in Yosemite Valley would result in a local, long-term,
minor, adverse cumulative impact on ethnographic resources as a result of
the disturbance of such resources. Alternative 1 would not contribute
to this impact.
Impairment
Ethnographic resource impacts resulting
from Alternative 1 would not be of sufficient magnitude to constitute
impairment.
Alternative 2
Analysis – Local Setting
- Restroom Relocation. Long-term,
minor, adverse impact. The relocation of the restroom within
the boundaries of the former Koom-I-ne village site would
result in a local, long-term, minor, adverse impact to this resource.
- Parking Area Removal and Establishment of
Seating/Picnic Area.
Long-term, minor,
beneficial impact. The removal of the parking area, which would lessen
the degree of development within the boundaries of the former Koom-I-ne
village site, would result in a local, long-term, minor, beneficial impact
to this resource.
- New Shuttle Bus Stop.
Long-term,
minor, adverse impact. The placement of the facility within a grove of
California black oaks would result in a long-term, minor, adverse impact
to this traditional gathering area. Increased visitor use would also
result in a long-term, minor, adverse impact.
- Interim Tour Bus Unloading, Loading, and Parking.
Short-term,
minor, adverse impact. The temporary parking of buses adjacent to the
Indian Cultural Center, a traditional use area, could result in a
short-term, minor, adverse impact to this resource by increasing the
degree of non-traditional activities in the area. Buses will park
elsewhere prior to establishment of the Indian Cultural Center.
- Trail Alignment.
Long-term,
moderate, adverse impact. The
trail alignment would
impact ethnographic resources such as the former Koom-I-ne village
site, the helli mushroom-gathering area, California black oaks, and
bracken fern. However, these impacts could be reduced by further
consultation with culturally associated American Indian tribes to develop
appropriate mitigating strategies (e.g., trail design elements that
encourage visitors to stay on defined trails, thus minimizing trampling of
vegetation). Such strategies could include identification of and
assistance in providing access to alternative resource-gathering areas,
continuing to provide access to traditional use or spiritual areas, and
screening new development from traditional use areas.
- Rehabilitation of Trails.
Long-term,
moderate, adverse impact. The rehabilitation of trails would
impact ethnographic resources such as the former Koom-I-ne village
site, the helli mushroom-gathering area, California black oaks, and
bracken fern. However, these impacts would be reduced by further
consultation with culturally associated American Indian tribes to develop
appropriate mitigating strategies. Such strategies would include
identification of and assistance in providing access to alternative
resource-gathering areas, continuing to provide access to traditional use
or spiritual areas, and screening new development from traditional use
areas.
- Rehabilitation, Relocation, and Installation of
Bridges.
Long-term, minor, adverse impact.
Ground-disturbing activities, as well as the establishment/relocation of
facilities within traditional gathering areas (mushrooms, bracken fern,
California black oaks), would result in long-term, minor, adverse impacts
to these ethnographic resources.
- View Corridor Maintenance.
Negligible
impact. Because view corridor maintenance would not occur within the
boundaries of an ethnographic resource, ethnographic resources would not
be impacted.
- Removal of Human-Built Rock-Rubble Pile.
Negligible
impact. Because the rubble pile is not situated within the boundaries
of an ethnographic resource, ethnographic resources would not be impacted.
Overall, there would be local,
long-term, moderate, adverse impacts to ethnographic resources under
Alternative 2 due to trail realignments and trail and bridge
rehabilitation efforts.
Cumulative Impacts – Regional Setting
The cumulative effects of actions on
ethnographic resources are described previously for Alternative 1.
The cumulative projects within and in the vicinity of the Lower Yosemite
Fall area would result in a local, long-term, minor to negligible, adverse
impact on ethnographic resources as a result of the potential disturbance
of such resources. In combination with Alternative 2, these impacts
would be increased to a moderate level of intensity.
Impairment
Ethnographic resource impacts resulting
from Alternative 2 would not be of sufficient magnitude to constitute
impairment.
Alternative 3
Analysis – Local Setting
- Restroom Relocation. Long-term,
moderate, adverse impact. The placement of the restroom within
the boundaries of a traditional gathering area (mushrooms) would
result in a local, long-term, moderate, adverse impact to this resource.
- Parking Area Removal and Establishment of an Informal
Seating Area.
Long-term, minor, beneficial
impact. The removal of the parking area from within the boundaries of
the former Koom-I-ne village site would result in a local,
long-term, minor, beneficial impact to this resource.
- New Shuttle Bus Stop.
Long-term,
minor, adverse impact. The placement of the facility within a grove of
California black oaks could result in a long-term, minor, adverse impact
to this traditional gathering area. Increased visitor use could also
result in a long-term, minor, adverse impact.
- Interim Tour Bus Unloading, Loading, and Parking.
Short-term,
minor, adverse impact. The temporary parking of buses adjacent to the
Indian Cultural Center, a traditional use area, could result in a
short-term, minor, adverse impact to this resource.
- Trail Alignment.
Long-term,
moderate, adverse impact. The trail alignment may impact
ethnographic resources such as the former Koom-I-ne village site,
the helli mushroom-gathering area, California black oaks, and
bracken fern. However, these impacts could be reduced by further
consultation with culturally associated American Indian tribes to develop
appropriate mitigating strategies (e.g., trail design elements that
encourage visitors to stay on defined trails, thus minimizing trampling of
vegetation). Such strategies could include identification of and
assistance in providing access to alternative resource-gathering areas,
continuing to provide access to traditional use or spiritual areas, and
screening new development from traditional use areas.
- Rehabilitation of Trails.
Long-term,
moderate, adverse impact. The rehabilitation of trails may
impact ethnographic resources such as the former Koom-I-ne village
site, the helli mushroom-gathering area, California black oaks, and
bracken fern. However, these impacts could be reduced by further
consultation with culturally associated American Indian tribes to develop
appropriate mitigating strategies. Such strategies could include
identification of and assistance in providing access to alternative
resource-gathering areas, continuing to provide access to traditional use
or spiritual areas, and screening new development from traditional use
areas.
- Rehabilitation, Relocation, and Installation of
Bridges.
Long-term, minor, adverse impact.
Ground-disturbing activities, as well as the establishment/relocation of
facilities within traditional gathering areas (mushrooms, bracken fern,
California black oaks), may result in long-term, minor, adverse impacts to
these ethnographic resources.
- View Corridor Maintenance.
Negligible
impact. Because view corridor maintenance would not occur within the
boundaries of an ethnographic resource, ethnographic resources would not
be impacted.
- Removal of Human-Built Rock-Rubble Pile.
Negligible
impact. Because the rubble pile is not situated within the boundaries
of an ethnographic resource, ethnographic resources would not be impacted.
Overall, there would be local,
long-term, moderate, adverse impacts to ethnographic resources due to
trail realignments and rehabilitation of trails and bridges under
Alternative 3.
Cumulative Impacts – Regional Setting
The cumulative effects of actions on
ethnographic resources are described previously for Alternative 1.
The cumulative projects within and in the vicinity of the Lower Yosemite
Fall area would result in a local, long-term, minor to negligible, adverse
impact on ethnographic resources as a result of the potential disturbance
of such resources. In combination with Alternative 3, these impacts
would be increased to a moderate level of intensity.
Impairment
Ethnographic resource impacts resulting
from Alternative 3 would not be of sufficient magnitude to constitute
impairment.
Cultural Landscape Resources
Alternative 1
Analysis – Local Setting
- Parking Area. Because the
parking area would remain in its current location, no disturbance of
cultural landscape resources would occur.
- Shuttle Bus Stop.
Because the
shuttle bus stop would remain in its current location and a new shuttle
bus stop would not be constructed, no disturbance of cultural landscape
resources would occur.
- Tour Bus Unloading, Loading, and Parking.
Because
tour bus operations would remain within the existing parking area, and no
construction would occur, no disturbance of cultural landscape resources
would occur.
- Trail Alignment.
The Lost
Arrow Trail and Valley Loop Trail, both of which are contributing elements
of the Yosemite Valley cultural landscape, would remain in their current
alignments and not be affected.
- Rehabilitation of Trails.
Because
the trails would remain in their current condition, no disturbance of
cultural landscape resources would occur.
- Rehabilitation, Relocation, and Installation of
Bridges.
Because the bridges would remain in
their current locations and condition, no disturbance of cultural
landscape resources would occur.
- View Corridor Maintenance.
Long-term,
moderate, adverse impact. Vegetation would continue to grow within the
identified view corridors, thereby obscuring views to Yosemite Falls, a
significant characteristic of a landscape resource.
- Removal of Human-Built Rock-Rubble Pile.
Because
the rock-rubble pile would remain in its current location, no disturbance
of cultural landscape resources would occur.
Overall, there would be a long-term,
moderate, adverse impact to cultural landscape resources in the Lower
Yosemite Fall area under Alternative 1 because view corridor
maintenance would not occur.
Cumulative Impacts – Regional Setting
Many cultural landscape resources
have been lost or damaged in Yosemite Valley through past development,
visitor use, and natural events, resulting in adverse cumulative impacts
to the cultural landscape. Disappearing structures and sites areas include
homestead cabins, barns, road and trail segments, bridges, mining
complexes, railroad and logging facilities, historic tourist facilities,
blazes, and campsites. These resources are reminders of the Valley’s
ranching, grazing, lumbering, and mining history and early tourism.
Reasonably foreseeable future actions
proposed in the region that could affect the remaining cultural landscape
resources include Yosemite Valley campground rehabilitation projects.
Implementation of projects called for in the Yosemite Valley Plan
would result in the removal, relocation, or modification of historic
buildings and structures, and the introduction of modern facilities and
development within historic districts and contributing portions of the
cultural landscape. The Yosemite Valley Plan would also restore
native vegetation communities to patterns more in keeping with the
cultural landscape and historic setting of the Valley. Overall,
implementation of the Yosemite Valley Plan would adversely affect
the cultural landscape. Alternative 1, combined with other projects
in Yosemite Valley, would result in a local, long-term, negligible,
adverse cumulative impact on cultural landscape resources.
Impairment
Cultural landscape resource impacts
resulting from Alternative 1 would not be of sufficient magnitude to
constitute impairment.
Alternative 2
Analysis – Local Setting
- Restroom Relocation. Negligible
impact. The placement of the restroom within the proposed
location would not significantly alter the historic setting of any of the
five identified cultural landscape resources.
- Parking Area Removal and Establishment of
Seating/Picnic Area.
Negligible impact. The
placement of the seating/picnic area would not significantly alter the
historic setting of the seven cultural landscape resources identified
within the Lower Yosemite Fall area.
- New Shuttle Bus Stop.
Negligible
impact. The placement of the shuttle bus stop would not
significantly alter the historic setting of the seven identified cultural
landscape resources.
- Interim Tour Bus Unloading, Loading, and Parking.
Short-term,
negligible, adverse impact. The placement of the interim tour
bus operations would temporarily add an incompatible use (bus parking) in
front of Camp 4, but the impact would be barely perceptible.
- Trail Alignment.
Long-term,
minor, adverse impact. Modifications to the trail alignments would
impact the following cultural landscape resources by altering their
historic alignments: Hutchings Orchard, Hutchings sawmill/Camp Lost Arrow
site, Lost Arrow Trail, Auto Road, and Valley Loop Trail. These impacts
would be perceptible and measurable but would remain localized and
confined to a single contributing element of a larger pending National
Register district.
- Rehabilitation of Trails.
Long-term,
moderate, adverse impacts. Rehabilitation of the trails would impact
the following cultural landscape resources by altering their historic
setting: Hutchings Orchard, Hutchings sawmill/Camp Lost Arrow site, Lost
Arrow Trail, Auto Road, and Valley Loop Trail.
- Rehabilitation, Relocation, and Installation of
Bridges.
Long-term, moderate, adverse
impacts. Rehabilitation of the bridges be perceptible and measurable
but would remain localized and confined to a single contributing element
of a larger pending National Register district. The following cultural
landscape resources would be affected by altering their historical
alignments and setting: Hutchings Orchard, Hutchings sawmill/Camp Lost
Arrow site, and Lost Arrow Trail.
- View Corridor Maintenance.
Long-term,
moderate, beneficial impact. Regular removal of vegetation that
obscures views to Yosemite Falls would significantly restore views of this
cultural landscape feature.
- Removal of Human-Built Rock-Rubble Pile.
Negligible
impact. Neither removal nor retention of the rock-rubble pile
would significantly alter the historic setting of the seven identified
cultural landscape resources.
Overall, there would be local,
long-term, moderate, adverse impacts to cultural landscape resources under
Alternative 2 due to trail realignments and bridge rehabilitation.
Cumulative Impacts – Regional Setting
The effects of cumulative actions on
cultural landscape resources have been described previously for
Alternative 1. Combined with the cumulative projects in Yosemite Valley,
Alternative 2 would result in a local, long-term, minor, adverse impact on
cultural landscape resources.
Impairment
Cultural landscape resource impacts
resulting from Alternative 2 would not be of sufficient magnitude to
constitute impairment.
Alternative 3
Analysis – Local Setting
- Restroom Relocation. Negligible
impact. The placement of the restroom within the proposed
location would not significantly alter the historic setting of any of the
seven identified cultural landscape resources.
- Parking Area Removal and Establishment of an Informal
Seating Area.
Negligible impact. The
placement of the seating/picnic area would not significantly alter the
historic setting of the seven cultural landscape resources.
- New Shuttle Bus Stop.
Negligible
impact. The placement of the shuttle bus stop would not
significantly alter the historic setting of the seven identified cultural
landscape resources.
- Interim Tour Bus Unloading, Loading, and Parking.
Short-term,
negligible, adverse impact. The placement of the interim tour
bus operations would temporarily add an incompatible use (bus parking) in
front of Camp 4, but the impact would be barely perceptible.
- Trail Alignment.
Long-term,
minor, adverse impact. Modifications to the trail alignments would
impact the following cultural landscape resources by altering their
historical alignments: Hutchings Orchard, Hutchings sawmill/Camp Lost
Arrow site (under this alternative, the majority of the sawmill site,
including the millrace, would be disturbed), Lost Arrow Trail, Auto Road,
and Valley Loop Trail.
- Rehabilitation of Trails.
Long-term,
moderate, adverse impact. Rehabilitation of the trails would impact
the following cultural landscape resources by altering their historic
setting: Hutchings Orchard, Hutchings sawmill/Camp Lost Arrow site (under
this alternative, the majority of the sawmill site, including the
millrace, would be disturbed), Lost Arrow Trail, Auto Road, and Valley
Loop Trail.
- Rehabilitation, Relocation, and Installation of
Bridges.
Long-term, moderate, adverse
impact. Rehabilitation of the bridges would impact the following
cultural landscape resources by altering their historic setting: Hutchings
Orchard, the millrace feature of the Hutchings sawmill site, and Lost
Arrow Trail.
- View Corridor Maintenance.
Long-term,
minor, beneficial impact. Periodic vegetation removal (less
frequently that would occur under Alternative 2) would also restore views
to Yosemite Falls, although the effect would be less noticeable than it
would be under Alternative 2.
- Removal of Human-Built Rock-Rubble Pile.
Negligible
impact. Neither removal nor retention of the rock-rubble pile
would significantly alter the historic setting of the seven identified
cultural landscape resources.
Overall, there would be local,
long-term, moderate, adverse impacts to cultural landscape resources under
Alternative 3 as a result of trail realignments, and bridge and trail
rehabilitation efforts.
Cumulative Impacts – Regional Setting
The effects of cumulative actions on
cultural landscape resources have been described previously for
Alternative 1. Combined with the cumulative projects in Yosemite Valley,
Alternative 3 would result in a local, long-term, minor, adverse impact on
cultural landscape resources.
Impairment
Cultural landscape resource impacts
resulting from Alternative 3 would not be of sufficient magnitude to
constitute impairment.
Social Resources
Scenic Resources
Alternative 1
Analysis – Local Setting
- Restroom Location. Long-term,
moderate, adverse impact. The existing restroom in the Lower Yosemite
Fall area would continue to intrude on the view of Yosemite Falls along
the Western Trail view corridor.
- Parking Area.
The existing
parking area would remain in its current location and condition, but would
not obscure the view of Yosemite Falls.
- Shuttle Bus Stop.
The shuttle
bus stop in the existing parking area would continue in its current
location but would not obscure the view of Yosemite Falls.
- Tour Bus Unloading, Loading, and Parking.
Long-term,
moderate, adverse impact. The tour buses that park in the current
parking lot would continue to obstruct the view along the Western Trail
view corridor.
- Trail Alignment.
No trail
alignments would be changed. Currently trail alignments do not obscure the
view corridors.
- Rehabilitation of Trails.
The
current condition of the trails does not detract from the view corridors
in the Lower Yosemite Fall area because no structures are present.
- Rehabilitation, Relocation, and Installation of
Bridges.
None of the existing bridges obscure
views of Yosemite Falls.
- View Corridor Maintenance.
Long-term,
moderate, adverse impact. The two historic view corridors through the
Lower Yosemite Fall area would not be maintained through vegetation
management. Vegetation would continue to grow in these view corridors,
thus obscuring historic views. This situation will worsen over time.
- Removal of Human-Built Rock-Rubble Pile.
Although
the existing rock-rubble pile would remain, it does not intrude into any
identified view corridor.
Overall, there would be a long-term,
moderate, adverse impact to scenic resources under Alternative 1 because
view corridor maintenance would not occur.
Cumulative Impacts – Regional Setting
Scenic resources have been affected by
numerous past actions since the inception of Yosemite National Park.
Primary among these is the alteration of natural communities resulting
from Euro-American settlement in the park. For example, agricultural
activities and the development of tourism resulted in the drying out of
the Valley by breaching the glacial moraine and controlling naturally
occurring fires, which affected vegetation patterns in the Lower Yosemite
Fall area. Broad-leaved trees along the streambanks were displaced by the
comparatively dense stands of conifers that exist today. These events have
resulted in a local, long-term, adverse effect on scenic resources,
because the conifers now block views of visually important landscape
features that were visible throughout the Valley before the vegetation
patterns were changed.
Reasonably foreseeable future actions
that would have a net beneficial cumulative effect on scenic resources
include those that improve the general health of ecosystems viewable from
or within the Lower Yosemite Fall area. Development-related projects could
have an adverse effect on scenic resources if they obscure views to A
Scenic resources as presented in the Yosemite Valley Plan (see the Final
Yosemite Valley Plan/SEIS, Vol. IB, page 4.0-21 for a description of
scenic resource categories), with the exception of the redevelopment of
Yosemite Lodge as called for in the Yosemite Valley Plan.
Other projects within and in the
vicinity of the Lower Yosemite Fall area would result in a local,
long-term, major, beneficial cumulative impacts on scenic resources in
Yosemite Valley because of the overall emphasis on maintaining view
corridors and restoring disturbed or developed land to natural conditions
within Yosemite Valley. However, the intensity of this impact would be
reduced to moderate because of the long-term, minor, adverse impact of
having the existing restroom within the Western Trail view corridor of the
Lower Yosemite Fall area. Alternative 1, combined with other projects in
Yosemite Valley, would not result in any additional cumulative impacts to
scenic resources in the Valley beyond the impacts evaluated above.
Impairment
Scenic resource impacts resulting from
Alternative 1 would not be of sufficient magnitude to constitute
impairment.
Alternative 2
Analysis – Local Setting
- Restroom Relocation. Long-term,
minor, beneficial, impact. Demolition of the current restroom under
Alternative 2 would remove an intrusion from the foreground of the
Western Trail view corridor. This intrusion would be minor because it
would be localized within a relatively small area. The new restroom would
be placed outside the Western Trail view corridor.
- Parking Area Removal and Establishment of
Seating/Picnic Area.
Long-term, minor,
beneficial impact. No structures would be placed within any identified
view corridor, and the cars and buses would be removed from the Western
Trail view corridor.
- New Shuttle Bus Stop.
Long-term,
negligible, adverse impact. The new shuttle bus stop would not be
placed within any identified view corridor.
- Interim Tour Bus Unloading, Loading, and Parking.
Short-term,
negligible, adverse impact. Although the buses would unload and board
passengers adjacent to the Hutchings view corridor, they would pass
through it upon departure. Passing through the view corridor would be
imperceptible when compared with Alternative 1.
- Trail Alignment.
Long-term,
negligible, adverse impact. No structures would be placed in the view
corridors.
- Rehabilitation of Trails.
Long-term,
negligible, adverse impact. Even when rehabilitated, trail
rehabilitation would not result in placement of structures within the view
corridors.
- Rehabilitation, Relocation, and Installation of
Bridges.
Long-term, negligible, adverse
impact. Even when rehabilitated, the bridges would not result in
placement of structures within the view corridors.
- View Corridor Maintenance.
Long-term,
moderate, beneficial impact. Selective tree-thinning and vegetation
removal in both the Hutchings view corridor and the Western Trail view
corridor would greatly enhance the current condition of the view towards
Yosemite Falls, which is categorized as an A Scenic resource by the Yosemite
Valley Plan.
- Removal of Human-Built Rock-Rubble Pile.
Long-term,
negligible, adverse impact. The existing rock-rubble pile does not
intrude into any identified view corridor.
Overall, there would be local,
long-term, moderate, beneficial impacts to scenic resources under
Alternative 2 due to the maintenance of important view corridors.
Cumulative Impacts – Regional Setting
The effects of cumulative actions on
scenic resources are described previously in this chapter for
Alternative 1. In combination with Alternative 2, the cumulative
projects within and in the vicinity of the Lower Yosemite Fall corridor
would result in a local, long-term, major, beneficial cumulative impact on
scenic resources in Yosemite Valley.
Impairment
Scenic resource impacts resulting from
Alternative 2 would not be of sufficient magnitude to constitute
impairment.
Alternative 3
Analysis – Local Setting
- Restroom Relocation. Long-term,
minor, beneficial, impact. Demolition of the current restroom under
Alternative 3 would remove an intrusion from the foreground of the
Western Trail view corridor. This intrusion would be minor because it
would be localized within a relatively small area. The new restroom would
be placed outside both the Western Trail and Hutchings view corridors.
- Parking Area Removal and Establishment of an Informal
Seating Area.
Long-term, minor, beneficial
impact. No structures would be placed within any identified view
corridor, and the cars and buses would be removed from the Western Trail
view corridor.
- New Shuttle Bus Stop.
Long-term,
negligible, adverse impact. The new shuttle bus stop would not be
placed within any identified view corridor.
- Interim Tour Bus Unloading, Loading, and Parking.
Short-term,
negligible, adverse impact. Although buses would unload and board
passengers adjacent to the Hutchings view corridor, they would pass
through it upon departure. Passing through the view corridor would be
imperceptible when compared with Alternative 1.
- Trail Alignment.
Long-term,
negligible, adverse impact. No trails would impact or change the view
corridors.
- Rehabilitation of Trails.
Long-term,
negligible, adverse impact. Even when rehabilitated, the trails would
not impact or change the view corridors.
- Rehabilitation, Relocation, and Installation of
Bridges.
Long-term, negligible, adverse
impact. Even when rehabilitated, the bridges would not result in
placement of structures within the view corridors.
- View Corridor Maintenance.
Long-term,
minor, beneficial impact. The two historic view corridors through the
Lower Yosemite Fall area would be maintained sporadically through
vegetation management. Efforts to maintain the views would be localized
and slightly detectable.
- Removal of Human-Built Rock-Rubble Pile.
Long-term,
negligible, adverse impact. The existing rock-rubble pile does not
intrude into any identified view corridor.
Overall, there would be a long-term,
minor, beneficial impact to scenic resources under Alternative 3 due
to the sporadic maintenance of view corridors.
Cumulative Impacts – Regional Setting
The effects of cumulative actions on
scenic resources have been described previously in this section for
Alternative 1. In combination with Alternative 3, the cumulative
projects within and in the vicinity of the Lower Yosemite Fall corridor
would result in a local, long-term, major, beneficial cumulative impact on
scenic resources in Yosemite Valley.
Impairment
Scenic resource impacts resulting from
Alternative 3 would not be of sufficient magnitude to constitute
impairment.
Visitor Experience
Alternative 1
Analysis – Local Setting
- Restroom Location. Long-term,
moderate, adverse impact. The limited number of restroom fixtures, its
inaccessibility to physically impaired visitors, and the state of
deterioration at the restroom would continue to substantially degrade the
visitor experience at the Lower Yosemite Fall area.
- Parking Area.
Long-term,
minor, adverse impact. Keeping the parking area in its current
location continues to provide convenience for the limited number of
vehicles that can park in the area. Overall, the parking area is so small
it does not meet the current demand. Many visitors drive to the parking
area only to find it is full, thus requiring them to drive elsewhere in
search of parking. This causes frustration and some confusion for
visitors.
- Shuttle Bus Stop.
Long-term,
minor, adverse impact. In its current location, the shuttle bus stop
is not clearly visible to visitors, nor is it obvious from the trails.
These conditions would continue.
- Tour Bus Unloading, Loading, and Parking.
Long-term,
minor, adverse impact. Since tour bus loading, unloading, and parking
would continue to occur in the existing parking area, the noise, visual
intrusion, and confusion would continue.
- Trail Alignment.
Long-term,
minor, adverse impact. Without rehabilitation and realignment, the
poorly defined eastern trail would continue to hinder visitor
accessibility to the base of Lower Yosemite Fall. The lack of
well-delineated and signed trails would continue to create confusion for
visitors.
- Rehabilitation of Trails.
Long-term,
minor, adverse impact. Without rehabilitation and realignment, the
eastern trail would continue to hinder visitor accessibility to the base
of Lower Yosemite Fall.
- Rehabilitation, Relocation, and Installation of
Bridges.
Long-term, minor, adverse impact. Without
rehabilitation and realignment, some bridges would continue to hinder
visitor accessibility to the base of Lower Yosemite Fall. The
intermittently crowded conditions caused by the limited amount of viewing
area space at Yosemite Falls Bridge may also adversely impact visitor
experience at the Lower Yosemite Fall area.
- View Corridor Maintenance.
Long-term,
moderate, adverse impact. Since the principal visitor use of the Lower
Yosemite Fall area is viewing Yosemite Falls, visitor experience is
hindered by the lack of maintenance of the two view corridors in the area.
Vegetation would continue to grow in these view corridors, thus
obscuring historic views.
- Removal of Human-Built Rock-Rubble Pile.
Long-term,
negligible, adverse impact. The existing rock-rubble pile would cause
little noticeable change to the quality of visitor experience and/or
service level at the Lower Yosemite Fall area.
Overall, there would be long-term,
moderate, adverse impacts to visitor experience due to the lack of
restroom relocation, trail alignment, rehabilitation of trails,
rehabilitation of bridges, and view corridor maintenance under Alternative
1.
Cumulative Impacts – Regional Setting
Implementation of the Yosemite Valley
Plan would enhance the quality of the visitor experience in Yosemite
Valley by reducing automobile congestion, limiting crowding, and expanding
orientation and interpretation services. It also calls for traffic
management systems and options for the size and placement of parking
areas, both within and outside of Yosemite Valley. Parking areas outside
the Valley could be used to intercept day visitors and shift those
visitors to Valley-bound shuttle buses.
Reasonably foreseeable future actions
that would have a beneficial cumulative effect on visitor use and
experience are those that could increase the number of facilities
accessible to the visitors, as well as enhance the condition of these
facilities to add to visitor enjoyment of the park.
Impairment
Visitor experience impacts resulting
from Alternative 1 would not be of sufficient magnitude to constitute
impairment.
Alternative 2
Analysis – Local Setting
- Restroom Relocation. Long-term,
moderate, beneficial impact. The new restroom to be constructed
under Alternative 2 would have an adequate number of toilet fixtures.
This would be an increase from the seven toilet fixtures available in the
existing restroom, would provide visitors greater restroom access with a
shorter waiting period for use, and would meet federal accessibility
standards.
- Parking Area Removal and Establishment of
Seating/Picnic Area.
Long-term, moderate,
beneficial impact. Removal of the parking area would help to enhance
the quiet setting for enjoyment of the Lower Yosemite Fall area by
eliminating noise and pollution from cars and buses. This would enhance
visitor use and experience as well as public safety. Visitor services and
facilities such as a small picnic and seating area, bicycle racks, and a
drinking fountain would further enhance the visitor experience.
- New Shuttle Bus Stop.
Long-term,
minor, beneficial impact. The new location of the shuttle bus stop
would provide a higher level of visitor access to the Lower Yosemite Fall
area because it would be located in a somewhat less congested area along
Northside Drive.
- Interim Tour Bus Unloading, Loading, and Parking.
Short-term,
minor, adverse impact. With the removal of the parking area, tour
buses would load and unload visitors along Northside Drive, a short
distance from the current location. This would not cause an appreciable
limit on critical characteristics of the visitor experience. The tour
buses would then be parked further west along Northside Drive. Buses
parked for the interim on Northside Drive west of Yosemite Lodge would be
visible and audible during mid-day to visitors at Camp 4. Because buses
would be parked during the middle of the day, when visitors are likely to
be elsewhere in the park, the impact on visitors using Camp 4 would be
minimal.
- Trail Alignment.
Long-term,
moderate, beneficial impact. Realignment of the trails would
allow for easier wayfinding and greater access to the trail system for
visitors with disabilities. The eastern trail would also be more clearly
delineated and meet accessibility guidelines. Improved educational
exhibits along the trails would serve to enhance the enjoyment of the
Lower Yosemite Fall area by providing visitors more information about the
area.
- Rehabilitation of Trails.
Long-term,
moderate, beneficial impact. Rehabilitation of the trails would allow
for easier wayfinding and greater access to the trail system for visitors
with disabilities, thereby appreciably changing the desired experience for
these visitors. The eastern trail would also be more clearly delineated
and meet accessibility guidelines. Improved educational exhibits along the
trails would serve to enhance the enjoyment of the Lower Yosemite Fall
area by providing visitors more information about the area. Expansion of
the viewing area at the base of Lower Yosemite Fall would help to
alleviate crowding conditions during peak times of visitation.
- Rehabilitation, Relocation, and Installation of
Bridges.
Long-term, moderate, beneficial
impact. In all cases, the bridges would meet federal accessibility
standards, which none currently meet. Currently, one bridge is closed
because of partial collapse and several are in a state of disrepair. The
rehabilitated bridges would be safer for visitors. Improved educational
exhibits along the trails would serve to enhance the enjoyment of the
Lower Yosemite Fall area by providing visitors with more information about
the area. At Yosemite Falls Bridge at the base of Lower Yosemite Fall, the
width of the bridge deck would be increased, thus allowing more visitors
to enjoy the view from the bridge. Greater visitor access and dispersion
of people at the base of Lower Yosemite Fall would further enhance visitor
experience. In summary, all of these actions would appreciably change the
desired experience for visitors.
- View Corridor Maintenance.
Long-term,
moderate, beneficial impact. Since the principal visitor use of the
Lower Yosemite Fall area is viewing Yosemite Falls, visitor experience
would be enhanced by the comprehensive maintenance of the two view
corridors in the area. Selective tree-thinning and vegetation removal in
both the Hutchings and Western Trail view corridors would greatly enhance
the current condition of these view corridors.
- Removal of Human-Built Rock-Rubble Pile.
Long-term,
negligible, adverse impact. The existing rock-rubble pile would
cause little noticeable change to the quality of visitor experience and/or
service level at the Lower Yosemite Fall area.
Overall, there would be a long-term,
moderate, beneficial impact to the visitor experience under Alternative 2
because of the rehabilitation of trails and bridges and maintenance of
view corridors.
Cumulative Impacts – Regional Setting
The effects of cumulative actions on
visitor experience are described previously for Alternative 1.
Actions under Alternative 2 would contribute to the local, long-term,
major, beneficial cumulative impact on visitor use and experience in the
Lower Yosemite Fall area.
Impairment
Visitor experience impacts resulting
from Alternative 2 would not be of sufficient magnitude to constitute
impairment.
Alternative 3
Analysis – Local Setting
- Restroom Relocation. Long-term,
moderate, beneficial impact. The new restroom to be constructed
under Alternative 2 would have an adequate number of toilet fixtures.
This would be an increase from the seven toilet fixtures available in the
existing restroom, would provide visitors greater access to a restroom
with a shorter waiting period for use, and would meet federal
accessibility standards.
- Parking Area Removal and Establishment of an Informal
Seating Area.
Long-term, moderate,
beneficial impact. Removal of the parking area would help to enhance
the quiet setting for enjoyment of the Yosemite Falls area by eliminating
noise and pollution from cars and buses. This would enhance visitor use
and experience, as well as public safety. Visitor services and facilities
such as a new informal seating area, bicycle racks, and a drinking
fountain would further enhance the visitor experience.
- New Shuttle Bus Stop.
Long-term,
minor, beneficial impact. The new location of the shuttle bus stop
would provide a slightly higher level of visitor access to the Lower
Yosemite Fall area because it would be located in a somewhat less
congested area along Northside Drive.
- Interim Tour Bus Unloading, Loading, and Parking.
Short-term,
minor, adverse impact. With the removal of the parking area, tour
buses would board and unload visitors along Northside Drive, a short
distance from their current location. This would not cause an appreciable
change in critical characteristics of the visitor experience. The tour
buses would then be parked further west along Northside Drive. Buses
parked for the interim on Northside Drive west of Yosemite Lodge would be
visible and audible during mid-day to visitors at Camp 4. Because buses
would be parked during the middle of the day, when visitors are likely to
be elsewhere in the park, the impact on visitors using Camp 4 would be
minimal.
- Trail Alignment.
Long-term,
moderate, beneficial impact. Realignment of the trails would
allow for easier wayfinding and greater access to the trail system for
visitors with disabilities, thereby appreciably changing the desired
experience for those visitors. The eastern trail would also be more
clearly delineated and meet accessibility guidelines. Improved educational
exhibits along the trails would serve to enhance the enjoyment of the
Lower Yosemite Fall area by providing visitors with more information about
the area.
- Rehabilitation of Trails.
Long-term,
moderate, beneficial impact. Rehabilitation of the trails would allow
for easier wayfinding and greater access to the trail system for visitors
with disabilities, thereby appreciably changing the desired experience for
those visitors. The eastern trail would also be more clearly delineated,
and would meet accessibility guidelines. Improved educational exhibits
along the trails would serve to enhance the enjoyment of the Lower
Yosemite Fall area by providing visitors more information about the area.
Expansion of the viewing area at the base of Lower Yosemite Fall would
help to alleviate crowding conditions during peak times of visitation.
- Rehabilitation, Relocation, and Installation of
Bridges.
Long-term, moderate, beneficial
impact. In all cases, the bridges would meet federal accessibility
standards, which none currently meet. Currently, one bridge is closed
because of partial collapse and several are in a state of disrepair. The
rehabilitated bridges would be safer for visitors. Improved educational
exhibits along the trails would serve to enhance the enjoyment of the
Lower Yosemite Fall area by providing visitors with more information about
the area. At Yosemite Falls Bridge at the base of Lower Yosemite Fall, the
width of the bridge deck would be increased, thus allowing more visitors
to enjoy the view from the bridge. Greater visitor access and dispersion
of people at the base of Lower Yosemite Fall would further enhance visitor
experience. In summary, all of these actions would appreciably change the
desired experience for visitors
- View Corridor Maintenance.
Long-term,
minor, beneficial impact. Since the principal visitor use of the Lower
Yosemite Fall area is viewing Yosemite Falls, visitor experience would be
enhanced by sporadic maintenance of the two view corridors in the area.
Intermittent tree-thinning and vegetation removal in both the Hutchings
and the Western Trail view corridors would greatly enhance the current
condition of these view corridors.
- Removal of Human-Built Rock-Rubble Pile.
Long-term,
negligible, adverse impact. The existing rock-rubble pile would
cause little noticeable change to the quality of visitor experience and/or
service level at the Lower Yosemite Fall area.
Overall, there would be a long-term,
moderate, beneficial impact to the visitor experience at the Lower
Yosemite Fall area under Alternative 3 due to the rehabilitation of trails
and bridges and restroom relocation.
Cumulative Impacts – Regional Setting
The effects of cumulative actions on
visitor experience are described previously for Alternative 1.
Actions under Alternative 3 would contribute to the local, long-term,
major, beneficial cumulative impact on visitor use and experience in the
Lower Yosemite Fall area.
Impairment
Visitor experience impacts resulting
from Alternative 3 would not be of sufficient magnitude to constitute
impairment.
Park Operations and Facilities
Alternative 1
Analysis – Local Setting
- Restroom Location. Long-term,
minor, adverse impact. The existing restroom would continue to require
frequent upkeep and maintenance because of its age and current state of
disrepair.
- Parking Area.
Retaining the
parking area in its current location would continue to have no effect on
the demand for park operations services and facilities.
- Shuttle Bus Stop.
Retaining
the shuttle bus stop in its current location would continue to have no
effect on the demand for park operations services and facilities.
- Tour Bus Unloading, Loading, and Parking.
Continuing
the current tour bus operations in the existing parking area would not
affect the demand for park operations and facilities.
- Trail Alignment.
The current
trail alignments would continue to have no effect on the demand for park
operations services and facilities.
- Rehabilitation of Trails.
Long-term,
minor, adverse impact. The existing trails would continue to require
frequent upkeep and maintenance because of their age and current state of
disrepair.
- Rehabilitation, Relocation, and Installation of
Bridges.
Long-term, minor, adverse impact. The
existing bridges would continue to require frequent upkeep and maintenance
because of their age and current state of disrepair.
- View Corridor Maintenance.
No
maintenance of view corridors would be undertaken.
- Removal of Human-Built Rock-Rubble Pile.
The
rock-rubble pile would be retained, and would not change park operations.
Overall, there would be long-term,
minor, adverse impacts to park operations and facilities under Alternative
1 resulting from maintenance of existing restroom, bridges, and trails.
Cumulative Impacts – Regional Setting
The extent to which past, present, or
reasonably foreseeable future projects could have a cumulative impact on
park operations and facilities, when combined with Alternative 1, is
determined largely by whether such projects would affect park facilities
or the demand for park operations services and facilities. Projects that
affect park facilities themselves or the demand for facilities management,
resource management, and maintenance of utility systems services in
particular would have the potential for cumulative effects with the Lower
Yosemite Fall area.
Park operations and facilities have been
affected by numerous past National Park Service management decisions and
projects since the inception of the park. Reasonably foreseeable future
projects include Repair of Flood Damaged Trail Bridges at Happy Isles,
Happy Isles Site Improvements, Merced River Plan, and implementation of
portions of the Yosemite Valley Plan. Overall, there has been
negligible impact from past actions on park operations and facilities.
Reasonably foreseeable future actions
that would have a beneficial cumulative effect on park operations and
facilities are those that could reduce the number or amount of facilities
within the park, or reduce long-term maintenance activities. An example is
the Replacement/Rehabilitation of the Yosemite Valley Main Sewer Line.
Although this project would have short-term, adverse impacts associated
with planning, construction, replacement, and rehabilitation, its overall
effect would be to reduce long-term maintenance. Therefore, this project
would have a long-term, beneficial cumulative impact on park operations
and facilities.
Examples of reasonably foreseeable
future projects that would have an adverse effect on park operations and
facilities are actions called for in the Merced River Plan and the
Yosemite Valley Plan. Implementation of these plans would
substantially increase demand on park operations and facilities in the
short term during planning, repair, rehabilitation,
construction/demolition, and replacement of facilities (e.g., removal of
the road through Stoneman Meadow, construction of new campsites, and
restoration of large areas of Yosemite Valley to natural conditions).
Implementation of these plans is expected to have local, short- and
long-term, moderate to major, adverse impacts on park operations and
facilities. However, in combination with Alternative 1, these
cumulative impacts could be increased to long-term and major because of
the ongoing maintenance requirements presented by the existing condition
of the restroom, trails, and bridges in the Lower Yosemite Fall area.
Impairment
Park operations and facilities impacts
resulting from Alternative 1 would not be of sufficient magnitude to
constitute impairment.
Alternative 2
Analysis – Local Setting
- Restroom Relocation. Long-term,
moderate, beneficial impact. Service and emergency vehicles would have
direct access to the new restroom location from Northside Drive, and only
limited service vehicle travel on pedestrian trails would be required to
service the restroom. Construction of the new restroom under Alternative 2
would decrease the frequency of maintenance required for facilities and
structures in the Lower Yosemite Fall area.
- Parking Area Removal and Establishment of
Seating/Picnic Area.
Long-term, negligible,
beneficial impact. Construction of the new picnic and seating area
would not require measurable staffing level increases to perform required
maintenance for facilities and structures in the Lower Yosemite Fall area.
- New Shuttle Bus Stop.
Long-term, negligible, beneficial impact. Construction of the new
shuttle bus stop would not require measurable staffing level increases to
perform required maintenance for facilities and structures in the Lower
Yosemite Fall area.
- Interim Tour Bus Unloading, Loading, and Parking.
Short-term,
minor, adverse impact. There may be indirect effects on park staffing
to ensure that bus operations (loading, unloading, and parking) do not
delay traffic on Northside Drive.
- Trail Alignment.
Long-term,
negligible, beneficial impact. Realignment of trails into upland areas
would decrease the frequency of maintenance required for trails in the
Lower Yosemite Fall area.
- Rehabilitation of Trails.
Long-term,
moderate, beneficial impact. Realignment of trails into upland areas
would decrease the frequency of maintenance required for trails in the
Lower Yosemite Fall area.
- Rehabilitation, Relocation, and Installation of
Bridges.
Long-term, moderate, beneficial
impact. Rehabilitation of bridges and relocating bridge abutments to
upland areas would decrease the frequency of maintenance required for
bridges in the Lower Yosemite Fall area.
- View Corridor Maintenance.
Long-term,
minor, adverse impact. National Park Service staff would be
required to selectively trim and cut vegetation within view corridors to
ensure that historic views remain unobstructed. Such trimming would be
conducted in accordance with the park’s Vegetation Management Plan.
- Removal of Human-Built Rock-Rubble Pile
.
Long-term, negligible, adverse impact. Removal of the
rock-rubble pile would be preceded by technical studies to ensure that it
would not cause direct or indirect impacts on park operation.
Overall, there would be long-term,
moderate, beneficial impacts to park operations and facilities under
Alternative 2 as a result of the decreased frequency of maintenance for
new facilities (restroom, bridges, and trails).
Cumulative Impacts – Regional Setting
The effects of cumulative actions on
park operations and facilities are described previously for
Alternative 1. Alternative 2 might diminish local, long-term,
major, adverse cumulative impacts on park operations and maintenance in
the Yosemite Valley area to moderate adverse impacts due to the reduced
need for maintenance of Lower Yosemite Fall area facilities, trails, and
bridges.
Impairment
Park operations and facilities impacts
resulting from Alternative 2 would not be of sufficient magnitude to
constitute impairment.
Alternative 3
Analysis – Local Setting
- Restroom Relocation. Long-term,
moderate, beneficial impacts. Service and emergency vehicles would
have direct access to the new restroom location from Northside Drive, and
only limited service vehicle travel on pedestrian trails would be required
to service the restroom. Construction of the new restroom under
Alternative 3 would decrease the frequency of maintenance required for
facilities and structures in the Lower Yosemite Fall area.
- Parking Area Removal and Establishment of Informal
Seating Area.
Long-term, negligible,
beneficial impacts. Construction of the new seating area would not
require measurable staffing level increases to perform required
maintenance for facilities and structures in the Lower Yosemite Fall area.
- New Shuttle Bus Stop.
Long-term,
negligible, beneficial impacts. Construction of the new shuttle bus
stop would not require measurable staffing level increases to perform
required maintenance for facilities and structures in the Lower Yosemite
Fall area.
- Interim Tour Bus Unloading, Loading, and Parking.
Short-term,
minor, adverse impacts. There may be indirect effects on park staffing
to ensure that bus operations (loading, unloading, and parking) do not
delay traffic on Northside Drive.
- Trail Alignment.
Long-term,
negligible, beneficial impacts. Construction of new trails would
decrease the frequency of maintenance required for trails in the Lower
Yosemite Fall area.
- Rehabilitation of Trails.
Long-term,
moderate, beneficial impacts. Construction of new trails would
decrease the frequency of maintenance required for trails in the Lower
Yosemite Fall area.
- Rehabilitation, Relocation, and Installation of
Bridges.
Long-term, moderate, beneficial
impacts. Construction of new trails would decrease the frequency of
maintenance required for bridges in the Lower Yosemite Fall area.
- View Corridor Maintenance.
Long-term,
minor, adverse impact. National Park Service Staff would be
required to selectively trim and cut vegetation within view corridors to
ensure that historic views remain unobstructed. Such trimming would be
conducted in accordance with the park’s Vegetation Management Plan.
- Removal of Human-Built Rock-Rubble Pile.
Long-term,
negligible, adverse impact. Removal of the rock-rubble pile
would not cause direct or indirect impacts on park operation.
Overall, there would be long-term,
moderate, beneficial impacts to park operations and facilities under
Alternative 3 due to the decreased frequency of maintenance of new
facilities (restroom, trails, and bridges).
Cumulative Impacts – Regional Setting
The effects of cumulative actions on
park operations and facilities have been described previously for
Alternative 1. Alternative 3 might diminish local, long-term,
major, adverse cumulative impacts on park operations and maintenance in
the Lower Yosemite Fall area to moderate, adverse impacts due to the
reduced need for maintenance of Lower Yosemite Fall area facilities,
trails, and bridges.
Impairment
Park operations and facilities impacts
resulting from Alternative 3 would not be of sufficient magnitude to
constitute impairment.
Recreation
Alternative 1
Analysis – Local Setting
- Restroom Location. Continuing
the restroom in its current location would not inhibit recreational
opportunities in the Lower Yosemite Fall area.
- Parking Area.
Continuing the
parking area in its current location would not inhibit recreational
opportunities in the Lower Yosemite Fall area.
- Shuttle Bus Stop.
Continuing
the shuttle bus stop in its current location would not inhibit
recreational opportunities in the Lower Yosemite Fall area.
- Tour Bus Unloading, Loading, and Parking.
Tour
bus operations would continue to use the existing parking area, and
recreational opportunities in the Lower Yosemite Fall area would continue
to be adversely impacted by the intrusion of noise and visual
distractions.
- Trail Alignment.
Retaining
the current trail alignments would inhibit recreational opportunities in
the Lower Yosemite Fall area for those with mobility impairments.
- Rehabilitation of Trails.
Retaining
the trails in their current condition would inhibit recreational
opportunities in the Lower Yosemite Fall area for those with mobility
impairments.
- Rehabilitation, Relocation, and Installation of
Bridges.
Retaining the bridges in their
current condition would not inhibit recreational opportunities in the
Lower Yosemite Fall area.
- View Corridor Maintenance.
Continuing
to not maintain the identified view corridors would not inhibit
recreational opportunities in the Lower Yosemite Fall area.
- Removal of Human-Built Rock-Rubble Pile.
Retaining
the rock-rubble pile in its current condition would not inhibit
recreational opportunities in the Lower Yosemite Fall area.
Overall, there would be a long-term,
negligible impact to recreation under Alternative 1 because there would be
little noticeable change in recreational opportunities.
Cumulative Impacts – Regional Setting
Recreation is considered an
Outstandingly Remarkable Value by the Merced River Plan. This value is
protected by the maintenance of a diversity of recreational opportunities
in the Yosemite Valley. There are a variety of recreational opportunities
available throughout the Yosemite Valley, including Lower Yosemite Fall.
Alternative 1 would not inhibit these opportunities.
Impairment
Recreation impacts resulting from
Alternative 1 would not be of sufficient magnitude to constitute
impairment.
Alternative 2
Analysis – Local Setting
- Restroom Relocation. Long-term,
negligible, adverse impact. Relocating the restroom would not inhibit
recreational opportunities in the Lower Yosemite Fall area.
- Parking Area Removal and Establishment of
Seating/Picnic Area.
Long-term, moderate,
beneficial impact. Under Alternative 2, buses would be removed from
the local setting and the parking area would be removed. The addition of
picnic tables in a portion of this area, as called for in Alternative 2,
would enhance the diversity of recreational opportunities in the Lower
Yosemite Fall area.
- New Shuttle Bus Stop.
Long-term,
negligible, adverse impact. Relocating the shuttle bus stop would not
inhibit recreational opportunities in the Lower Yosemite Fall area.
- Interim Tour Bus Unloading, Loading, and Parking.
Short-term,
negligible, adverse impact. Relocating the tour bus operations from
the Lower Yosemite Fall area would not inhibit recreational opportunities
in the Lower Yosemite Fall area.
- Trail Alignment.
Long-term,
negligible, beneficial impact. Realignment of the trails would
expand recreational opportunities in the Lower Yosemite Fall area for
those with mobility impairments.
- Rehabilitation of Trails.
Long-term,
minor, beneficial impact. Rehabilitation of the trails would
expand recreational opportunities in the Lower Yosemite Fall area for
those with mobility impairments.
- Rehabilitation, Relocation, and Installation of
Bridges.
Long-term, minor, beneficial
impact. Rehabilitation of the bridges would expand recreational
opportunities in the Lower Yosemite Fall area for those with mobility
impairments.
- View Corridor Maintenance.
Long-term,
moderate, beneficial impact. View corridor maintenance through routine
vegetation clearance would cause a noticeable change in sightseeing
opportunities in the Lower Yosemite Fall area.
- Removal of Human-Built Rock-Rubble Pile.
Long-term,
negligible, adverse impact. The presence or absence of the rock-rubble
pile would not inhibit recreational opportunities in the Lower Yosemite
Fall area.
Overall, there would be a long-term,
moderate, beneficial impact to recreation under Alternative 2 due to the
establishment of a picnic/seating area and maintenance of view corridors.
Cumulative Impacts – Regional Setting
Recreation is considered an
Outstandingly Remarkable Value by the Merced River Plan. This value is
protected by the maintenance of a diversity of recreational opportunities
in the Yosemite Valley. A variety of recreational opportunities are
available throughout the Yosemite Valley, including Lower Yosemite Fall.
The addition of picnic tables, as called for in Alternative 2, would
enhance the diversity of recreational opportunities in the Yosemite
Valley.
Impairment
Recreation impacts resulting from
Alternative 2 would not be of sufficient magnitude to constitute
impairment.
Alternative 3
Analysis – Local Setting
- Restroom Relocation. Long-term,
negligible, adverse impact. Relocating the restroom would not inhibit
recreational opportunities in the Lower Yosemite Fall area.
- Parking Area Removal and Establishment of an Informal
Seating Area.
Long-term, moderate,
beneficial impact. Under Alternative 3, buses would be removed from
the local setting and the parking area would be removed. The addition of
an informal seating area in a portion of this area, as called for in
Alternative 3, would enhance the diversity of recreational opportunities
in the Yosemite Valley.
- New Shuttle Bus Stop.
Long-term,
negligible, adverse impact. Relocating the shuttle bus stop would not
inhibit recreational opportunities in the Lower Yosemite Fall area.
- Interim Tour Bus Unloading, Loading, and Parking.
Long-term,
negligible, adverse impact. Relocating the tour bus operations from
the Lower Yosemite Fall area would not inhibit recreational opportunities
in the Lower Yosemite Fall area.
- Trail Alignment.
Long-term,
minor, beneficial impact. Realignment of the trails would
expand recreational opportunities in the Lower Yosemite Fall area for
those with mobility impairments.
- Rehabilitation of Trails.
Long-term,
minor, beneficial impact. Rehabilitation of the trails would
expand recreational opportunities in the Lower Yosemite Fall area for
those with mobility impairments.
- Rehabilitation, Relocation, and Installation of
Bridges.
Long-term, minor, beneficial
impact. Rehabilitation of the bridges would expand recreational
opportunities in the Lower Yosemite Fall area for those with mobility
impairments.
- View Corridor Maintenance.
Long-term,
minor, beneficial impact. View corridor maintenance through sporadic
vegetation clearance would cause little noticeable change in recreational
opportunities in the Lower Yosemite Fall area.
- Removal of Human-Built Rock-Rubble Pile.
Long-term,
negligible, adverse impact. The presence or absence of the rock-rubble
pile would not inhibit recreational opportunities in the Lower Yosemite
Fall area.
Overall, there would be a long-term,
moderate, beneficial impact to recreation under Alternative 3 due to
the establishment of a seating area.
Cumulative Impacts – Regional Setting
Recreation is considered an
Outstandingly Remarkable Value by the Merced River Plan. This value is
protected by the maintenance of a diversity of recreational opportunities
in the Yosemite Valley. A variety of recreational opportunities are
available throughout the Yosemite Valley, including Lower Yosemite Fall.
The addition of an informal seating area, as called for in Alternative 3,
would enhance the diversity of recreational opportunities in the Yosemite
Valley.
Impairment
Recreation impacts resulting from
Alternative 3 would not be of sufficient magnitude to constitute
impairment.
Transportation
Alternative 1
Analysis – Local Setting
- Restroom Location. Retaining
the restroom in its current location would continue to have no influence
on traffic circulation patterns.
- Parking Area.
Long-term,
minor, adverse impact. Retaining the parking area in its current
location would continue to encourage visitors to drive through the area to
attempt to park. This currently causes a change in the number of vehicle
trips of less than 25% and contributes to congestion at the Lower Yosemite
Fall area-Yosemite Lodge intersection and the recirculating traffic
influence on traffic circulation patterns.
- Shuttle Bus Stop.
Continuing
the shuttle bus stop in its current location does not influence traffic
circulation patterns.
- Tour Bus Unloading, Loading, and Parking.
Long-term,
negligible, adverse impact. Continuing the tour bus operation in its
current location would continue to cause tour groups to walk back and
forth to Yosemite Lodge, thus contributing to traffic congestion at the
Lower Yosemite Fall area-Yosemite Lodge intersection.
- Trail Alignment.
Continuing
the trail alignments in their current location would not influence traffic
circulation patterns.
- Rehabilitation of Trails.
Retaining
the trails in their current condition would continue to have no influence
on traffic circulation patterns.
- Rehabilitation, Relocation, and Installation of
Bridges.
Retaining the pedestrian bridges in
their current location and condition would not influence traffic
circulation patterns.
- View Corridor Maintenance.
There
would be no actions to maintain view corridors; there would be no
transportation implications to this lack of maintenance.
- Removal of Human-Built Rock-Rubble Pile.
The
rock-rubble pile would remain in its current condition; there are no
transportation implications to this action.
Overall, there would be long-term,
minor, adverse impacts to transportation under Alternative 1 because the
parking area would be retained, and local circulation patterns on
Northside Drive would not change.
Cumulative Impacts – Regional Setting
The cumulative transportation impacts
would be unchanged from the analysis presented in the Yosemite Valley
Plan. That information is summarized below. Alternative 1, in
combination with other projects in Yosemite Valley, would have no further
cumulative impacts to transportation in the Valley beyond those analyzed
in the Yosemite Valley Plan.
Under the Yosemite Valley Plan,
the average travel time to access Yosemite Valley would increase by 20 to
21 minutes over present conditions, representing a moderate adverse impact
to visitors. Many visitor trips to and within the Valley would be shifted
to transit from private vehicles. There would be a major decrease in
traffic volumes and a major improvement in traffic flow within the Valley
compared to present conditions. Traffic volumes on roads would be reduced
by 50%, resulting in a major, long-term beneficial impact. Bus trips
entering the Valley at the Yosemite Chapel would increase by 285 per day.
All bus trips into the Valley would travel as far as Yosemite Village, and
the shuttle service in the Valley would be greatly expanded, with the
resulting bus miles traveled increasing to 4,949 miles per day. Traffic
congestion would be reduced at the intersections of Sentinel Road with
Northside Drive and Southside Drive. There would be major, long-term
beneficial impacts from improved traffic flow, particularly on El Portal
Road between its intersection with Big Oak Flat Road and Pohono Bridge,
and on Northside Drive, between Yosemite Lodge and Yosemite Village.
Impairment
Transportation impacts resulting from
Alternative 1 would not be of sufficient magnitude to constitute
impairment.
Alternative 2
Analysis – Local Setting
- Restroom Relocation. Long-term,
negligible, adverse impacts. The new restroom location would not alter
traffic circulation patterns in the Lower Yosemite Fall area.
- Parking Area Removal and Establishment of
Seating/Picnic Area.
Long-term, minor,
beneficial impacts. Removal of parking at the Lower Yosemite Fall area
would remove the incentive for visitors to drive to this prominent feature
in Yosemite Valley; this would reduce vehicle trips and congestion.
- New Shuttle Bus Stop.
Long-term,
negligible, beneficial impact. The new shuttle bus stop
location is close to the existing shuttle bus stop, which would shorten
the shuttle bus circulation pattern.
- Interim Tour Bus Unloading, Loading, and Parking.
Short-term,
minor, adverse, impacts. Removing tour buses from the Lower Yosemite
Fall area would have a negligible impact on transportation. Providing
interim bus loading and unloading on Northside Drive would have a
short-term, minor, adverse impact due to the mixed use along the roadside.
Providing interim bus parking along Northside Drive west of Yosemite Lodge
would cause short-term, minor, adverse impacts due to the need to maintain
one lane of outbound traffic slightly further west of Yosemite Lodge.
- Trail Alignment.
Long-term,
negligible, adverse impacts. The new trail alignments would not alter
traffic circulation patterns in the Lower Yosemite Fall area.
- Rehabilitation of Trails.
Long-term,
negligible, adverse impacts. Rehabilitation of the trails would not
alter traffic circulation patterns in the Lower Yosemite Fall area.
- Rehabilitation, Relocation, and Installation of
Bridges.
Long-term, negligible, adverse
impacts. Rehabilitation of the pedestrian bridges would not alter
traffic circulation patterns in the Lower Yosemite Fall area.
- View Corridor Maintenance.
Long-term,
negligible, adverse impacts. Maintenance of the view corridors would
not alter traffic circulation patterns in the Lower Yosemite Fall area.
- Removal of Human-Built Rock-Rubble Pile.
Long-term,
negligible, adverse impacts. Removal of the rock-rubble pile would not
alter traffic circulation patterns in the Lower Yosemite Fall area.
Overall, there would be long-term,
minor, beneficial impacts to transportation under Alternative 2 due
to the removal of the parking area (as well as cars and buses).
Cumulative Impacts – Regional Setting
The cumulative transportation impacts
would be unchanged under Alternative 2 from the analysis presented in the Yosemite
Valley Plan and are summarized previously for Alternative 1.
Impairment
Transportation impacts resulting from
Alternative 2 would not be of sufficient magnitude to constitute
impairment.
Alternative 3
Analysis – Local Setting
- Restroom Relocation. Long-term,
negligible, adverse impacts. The new restroom location would not alter
traffic circulation patterns in the Lower Yosemite Fall area.
- Parking Area Removal and Establishment of Informal
Seating Area.
Long-term, minor, beneficial
impacts. Removal of the parking area would eliminate the cars and
buses coming into the Lower Yosemite Fall area.
- New Shuttle Bus Stop.
Long-term,
negligible, beneficial impact. The new shuttle bus stop
location is close to the existing shuttle bus stop, which would shorten
the shuttle bus circulation pattern.
- Interim Tour Bus Unloading, Loading, and Parking.
Short-term,
minor, adverse impacts. Removing tour buses from the Lower Yosemite
Fall area would have a negligible impact on transportation. Providing
interim bus loading and unloading on Northside Drive would have a
short-term, minor, adverse impact due to the mixed use along the roadside.
Providing interim bus parking along Northside Drive west of Yosemite Lodge
would cause short-term, minor, adverse impacts due to the need to maintain
one lane of outbound traffic slightly further west of Yosemite Lodge.
- Trail Alignment.
Long-term,
negligible, adverse impacts. The new trail alignments would not alter
traffic circulation patterns in the Lower Yosemite Fall area.
- Rehabilitation of Trails.
Long-term,
negligible, adverse impacts. Rehabilitation of the trails would not
alter traffic circulation patterns in the Lower Yosemite Fall area.
- Rehabilitation, Relocation, and Installation of
Bridges.
Long-term, negligible, adverse
impacts. Rehabilitation of the pedestrian bridges would not alter
traffic circulation patterns in the Lower Yosemite Fall area.
- View Corridor Maintenance.
Long-term,
negligible, adverse impacts. Maintenance of the view corridors would
not alter traffic circulation patterns in the Lower Yosemite Fall area.
- Removal of Human-Built Rock-Rubble Pile.
Long-term,
negligible, adverse impacts. Removal of the rock-rubble pile would not
alter traffic circulation patterns in the Lower Yosemite Fall area.
Overall, there would be long-term,
minor, beneficial impacts to transportation under Alternative 3 due
to the removal of the parking area (along with cars and buses).
Cumulative Impacts – Regional Setting
The cumulative transportation impacts
would be unchanged under Alternative 3 from the analysis presented in the Yosemite
Valley Plan. That information is summarized previously for Alternative
1.
Impairment
Transportation impacts resulting from
Alternative 3 would not be of sufficient magnitude to constitute
impairment.
Energy Consumption
Alternative 1
Analysis – Local Setting
- Restroom Location. No
construction would occur; therefore, corresponding use of fossil fuels
would not increase.
- Parking Area.
The parking
area would continue at its current location, and no additional buses or
cars would be attracted to the site.
- Shuttle Bus Stop.
The shuttle
bus stop would continue at its current location, thereby consuming no
additional energy.
- Tour Bus Unloading, Loading, and Parking.
Tour
bus operations would continue to use the existing parking area.
- Trail Alignment.
No
construction would occur; therefore, use of fossil fuels would continue at
its present rate.
- Rehabilitation of Trails.
No
construction would occur; therefore, corresponding use of fossil fuels
would continue at its present rate.
- Rehabilitation, Relocation, and Installation of
Bridges.
No construction would occur;
therefore, corresponding use of fossil fuels would continue at its present
rate.
- View Corridor Maintenance.
No
vegetation removal would occur; energy consumption would continue at its
present rate.
- Removal of Human-Built Rock-Rubble Pile.
No
construction would occur; therefore, corresponding use of fossil fuels
would not increase.
Overall, there would be a negligible
impact to energy consumption under Alternative 1 because consumption would
be affected by 5% or less, annually.
Cumulative Impacts – Regional Setting
Alternative 1, combined with other
projects described in the Yosemite Valley Plan, would have a
local, long-term, moderate, beneficial effect on energy consumption in
Yosemite Valley. That information is summarized below.
Employee housing space-heating
consumption would decrease in the Valley, but would increase at El Portal
and Wawona during the 2000-2015 time frame. Overall, there would be a
minor increase in total housing units under the Yosemite Valley Plan and
an associated long-term, minor, adverse impact on home energy consumption.
The reduction in gasoline consumption in
2015 relative to Alternative 1 reflects the shift by park visitors from
private vehicles to shuttle buses, as well as a fleet turnover to vehicles
with improved fuel economy over time. The increase in shuttle fuel
consumption would be attributable to the deployment of diesel or
alternatively fueled shuttle buses for visitors and employees. The
combined fuel consumption savings under the Yosemite Valley Plan in
the years 2005, 2010, and 2015 would represent a moderate, long-term,
beneficial impact.
Impairment
Energy consumption impacts resulting
from Alternative 1 would not be of sufficient magnitude to constitute
impairment.
Alternative 2
Analysis – Local Setting
- Restroom Relocation. Long-term,
negligible, adverse impact. The new restroom would replace the
existing restroom, and no net increase of consumption of energy would be
anticipated.
- Parking Area Removal and Establishment of
Seating/Picnic Area.
Long-term, negligible,
adverse impact. Under Alternative 2, buses would be relocated from the
local area and the parking area would be removed. This would result in a
slight overall increase in energy consumption, because tour buses need to
be driven for a longer duration than under Alternative 1 to park and pick
up passengers at the interim drop-off/pickup zone.
- New Shuttle Bus Stop.
Long-term,
negligible, adverse impact. The new restroom would replace the
existing restroom, and no net increase of consumption of energy would be
anticipated.
- Interim Tour Bus Unloading, Loading, and Parking.
Short-term,
negligible, adverse impact. Relocating the tour buses from the Lower
Yosemite Fall area to a location along Northside Drive would result in a
slight overall temporary increase in energy consumption because tour buses
would need to be driven for a slightly longer duration than under
Alternative 1 to park and pick-up passengers at the interim loading and
unloading zone.
- Trail Alignment.
Long-term,
negligible, adverse impact. No net increase of consumption of
energy is anticipated from the realignment of pedestrian trails.
- Rehabilitation of Trails.
Long-term,
negligible, adverse impact. No net increase of consumption of
energy is anticipated from the rehabilitation of pedestrian trails.
- Rehabilitation, Relocation, and Installation of
Bridges.
Long-term, negligible, adverse
impact. No net increase of consumption of energy is anticipated
from the rehabilitation of pedestrian trails.
- View Corridor Maintenance.
Long-term,
negligible, adverse impact. View corridor maintenance through periodic
vegetation clearance would not result in a net increase in energy
consumption.
- Removal of Human-Built Rock-Rubble Pile.
Long-term,
negligible, adverse impact. The presence or absence of the rock-rubble
pile would not result in a net increase in energy consumption.
Overall, there would be a long-term,
negligible, adverse impact to energy consumption under Alternative 2
because the parking area and buses would be removed, but replaced
elsewhere in the park.
Cumulative Impacts – Regional Setting
Although cumulative growth in the region
would tend to adversely affect energy consumption, implementation of
ongoing state and federal energy consumption programs will ameliorate this
effect to a degree. Considered with the adverse impacts associated with
regional energy consumption, Alternative 2 and projects in Yosemite Valley
would have a long-term, negligible, beneficial, cumulative impact on
energy consumption.
Impairment
Energy consumption impacts resulting
from Alternative 2 would not be of sufficient magnitude to constitute
impairment.
Alternative 3
Analysis – Local Setting
- Restroom Relocation. Long-term,
negligible, adverse impact. The new restroom would replace the
existing restroom, and no net increase of consumption of energy would be
anticipated.
- Parking Area Removal and Establishment of Informal
Seating Area.
Long-term, negligible,
adverse impact. Under Alternative 3, buses would be relocated from the
local area and the parking area would be removed. This would result in a
slight overall increase in energy consumption, because tour buses would
need to be driven for a longer duration than under Alternative 1 to park
and pick up passengers at the interim drop-off/pickup zone.
- New Shuttle Bus Stop.
Long-term,
negligible, adverse impact. The new restroom would replace the
existing restroom, and no net increase of consumption of energy would be
anticipated.
- Interim Tour Bus Unloading, Loading, and Parking.
Short-term,
negligible, adverse impact. Relocating tour buses from the Lower
Yosemite Fall area to a location along Northside Drive would result in a
slight overall temporary increase in energy consumption because tour buses
need to be driven for a slightly longer duration than under Alternative 1
to park and pick up passengers at the interim drop-off/pickup zone.
- Trail Alignment.
Long-term,
negligible, adverse impact. No net increase of consumption of
energy would be anticipated from the realignment of pedestrian trails.
- Rehabilitation of Trails.
Long-term,
negligible, adverse impact. No net increase of consumption of
energy would be anticipated from the rehabilitation of pedestrian trails.
- Rehabilitation, Relocation, and Installation of
Bridges.
Long-term, negligible, adverse
impact. No net increase of consumption of energy would be
anticipated from the rehabilitation of bridges.
- View Corridor Maintenance.
Long-term,
negligible, adverse impact. View corridor maintenance through periodic
vegetation clearance would not result in a net increase in energy
consumption.
- Removal of Human-Built Rock-Rubble Pile.
Long-term,
negligible, adverse impact. The presence or absence of the rock-rubble
pile would not result in a net increase in energy consumption.
Overall, there would be a long-term,
negligible, adverse impact to energy consumption under Alternative 3
due to the parking area and buses being removed but replaced elsewhere in
the park.
Cumulative Impacts – Regional Setting
Although cumulative growth in the region
would tend to adversely affect energy consumption, implementation of
ongoing state and federal energy consumption programs will ameliorate this
effect to a degree. Considered with the adverse impacts associated with
regional energy consumption, Alternative 3 and projects in Yosemite Valley
would have a local, long-term, negligible, beneficial, cumulative impact
on air quality in the Lower Yosemite Fall area.
Impairment
Energy consumption impacts resulting
from Alternative 3 would not be of sufficient magnitude to constitute
impairment.
|