|
Chapter 2
Description of Proposed Action and Alternatives
____________________________________________________________________________________________________________
This environmental assessment addresses
actions of the Lower Yosemite Fall Project that were approved in the Yosemite
Valley Plan, including those that have changed slightly since the time
the Yosemite Valley Plan Record of Decision was signed (NPS 2000c).
A few of the actions approved by the Yosemite Valley Plan were
changed because new information became available as the site design was
refined for the Lower Yosemite Fall Project.
Alternatives Development
The Yosemite Valley Plan
evaluated a full range of alternatives, and its Record of Decision approved
actions to proceed. However, as implementation of the Lower Yosemite Fall
Project began, it was recognized that additional NEPA compliance was
necessary. Consequently, actions evaluated in this environmental
assessment are limited to those meeting any of the four criteria listed in
Chapter 1 (page 1-5).
Overview of the Alternatives
This section presents three alternatives
for the Lower Yosemite Fall Project. Under Alternative 1 (No Action), the
Lower Yosemite Fall area would remain unchanged, except for normal
maintenance and repair such as rebuilding Bridge #6, which recently
collapsed. Alternative 2 (Preferred) would implement approved Yosemite
Valley Plan actions for the Lower Yosemite Fall area and clarifies and
adjusts certain actions. The need for these adjustments became evident as
detailed site-specific planning for the area was undertaken. Alternative 3
(As Evaluated in the Yosemite Valley Plan) presents the actions for
the Lower Yosemite Fall area as they were approved in the Yosemite
Valley Plan Record of Decision.
Alternative 1 (No Action)
Under Alternative 1, the existing
conditions in the Lower Yosemite Fall area would be maintained as
described in Chapter 3, Affected Environment. Figure 2-1 is the site plan
for this alternative. Alternative 1 provides a baseline from which to
compare Alternatives 2 and 3, evaluate the magnitude of proposed changes,
and measure the environmental effects of those changes. This no action
concept follows the guidance of the Council on Environmental Quality,
which describes the No Action Alternative as representing no change from
the existing management direction or level of management intensity. Listed
below are the baseline conditions of the actions that comprise the Lower
Yosemite Fall Project.
- Restroom Location.
The
restroom would remain in its current location and condition. Routine
maintenance activities would continue, including the replacement of
2,890 feet of sewer line to the existing restroom. The necessary
environmental compliance for the sewer line replacement project has been
completed, and the project was approved on April 24, 2001.
- Parking Area. The existing
parking area would remain in its current location and condition.
- Shuttle Bus Stop. The
shuttle bus stop would remain at its current location in the Lower
Yosemite Fall area.
- Tour Bus Unloading, Loading, and Parking.
Tour buses would continue to unload and load passengers within the
parking area. Tour bus parking would not be relocated from the Lower
Yosemite Fall area, replacement parking spaces would not be needed for
tour buses that currently park in this area, nor would an interim bus
passenger loading and unloading location be necessary. Tour buses would
continue to park in the parking area.
- Trail Alignment, Including Relocation of the Eastern
Trail Near Bridge #1.
Trails providing
access to the base of Lower Yosemite Fall would remain in their current
alignments.
- Rehabilitation of Trails.
All
trails in the Lower Yosemite Fall area would remain in their current
condition (including routine maintenance). The trails to the base of
Lower Yosemite Fall would not meet federal accessibility standards.
Limited interpretive exhibits would remain in their current condition.
Stock (e.g., horse) users would share trails with hikers through the
Lower Yosemite Fall area.
Figure 2-1
Alternative 1 Site Plan (No Action)
Rehabilitation, Relocation, and Installation of
Bridges. All bridges would remain in their
current locations and condition with the exception of Bridge #6. This
bridge, which recently collapsed, would be rebuilt. Bridge abutments would
remain in their current locations within the creek bed. The bridge across
Yosemite Creek at the base of Lower Yosemite Fall and the viewing platform
area would remain in their current condition.
View Corridor Maintenance. Two
historic view corridors through the Lower Yosemite Fall area would not be
programmatically maintained through selective trimming of trees and tree
removal. Vegetation would be more likely to continue to grow in these view
corridors, thus potentially obscuring historic views.
Removal of Human-Built Rock-Rubble Pile. The
existing rock-rubble pile would remain.
Alternative 2 (Preferred)
Alternative 2 would implement actions
approved in the Yosemite Valley Plan for the Lower Yosemite Fall
area, including modifications. The site plan for Alternative 2 is provided
in figure 2-2. The actions, as well as those approved in the Yosemite
Valley Plan, are described below.
- Restroom Relocation.
The
restroom north of the existing parking area would be removed, and a new
restroom would be constructed near what is currently the southeastern
edge of the parking lot. The location proposed for the restroom is about
540 feet west of the site identified for the restroom in the Yosemite
Valley Plan (see figure 2-3). The change of location would
minimize impacts to an ethnographic resource, keep the restroom out of
Yosemite Falls view corridors, and be adjacent to the proposed
seating/picnic area. The new restroom would be adequately sized for the
expected volume of visitors to the area and would be designed to be
accessible to persons with mobility impairments. It would contain 12
toilet and four urinal fixtures, including two family-accessible rooms,
and two wheelchair-accessible stalls (one men’s, one women’s).
- Parking Area Removal and Establishment of a Small
Seating and Picnic Area.
The existing
parking area (see figure 2-1) would be removed. Trails would be built to
approach the western trail to the base of Lower Yosemite Fall, and there
would be a small picnic area and seating area with informal seating on
benches, logs, or stones. The picnic area would be located on what is
currently the southern portion of the parking area and would include up
to 12 picnic tables. A trail would provide access to the picnic tables.
The remainder of the area would be revegetated with locally native
plants.
Figure 2-2 Alternative 2 Site Plan
(Preferred)
The following actions would remain
unchanged from those approved in the Yosemite Valley Plan:
- New Shuttle Bus Stop.
A new
shuttle bus stop would be located on the north side of Northside Drive
east of the Yosemite Creek Bridge.
- Interim Tour Bus Unloading, Loading, and Parking.
To
address removal of the tour bus loading/unloading and parking area from
the Lower Yosemite Fall area, replacement loading/unloading and parking
spaces would need to be provided for tour buses. Long-term tour bus
loading and unloading would occur at the future new transit center in
Yosemite Village. For an interim time period, bus passenger loading and
unloading zone would be provided along Northside Drive near Cook’s
Meadow, using the existing turnout west of Village Drive. Until day tour
bus parking can be provided elsewhere, as called for in the Yosemite
Valley Plan, day tour buses would for the interim park in an
existing lane of Northside Drive, extending west of Camp 4. Day tour
buses would park in the north (right) lane of the road until passengers
are ready for pickup. When passengers are ready to load, buses would
return to Northside Drive near Cook’s Meadow for passenger pickup.
Interim parking for the few overnight tour buses would be provided in
existing parking areas associated with nearby lodging facilities in
Yosemite Valley.
- Trail Alignment, Including Relocation of the Eastern
Trail Near Bridge #1.
A realigned
trail with elevated boardwalks would be placed between Bridges #1 and #2
and northwest of Bridge #1. This would minimize impacts to the millrace
feature within Hutchings sawmill site because the boardwalks would be
placed above the site. All bridge abutments would be moved out of the
creek channel to adjacent upland areas. One pier would be placed in the
creek at Bridge #3 to support the longer span, and two piers would be in
the creek at Bridge #6 to support the longer span. Two piers in the
creek at the Yosemite Falls Bridge would be replaced at the same
location. Trail alignments between Bridge #6 and the Hutchings view
corridor would be designed to minimize impacts to ethnographic
resources.
- Rehabilitation of Trails.
Pedestrian
access to the base of Lower Yosemite Fall would be on either a
rehabilitated western trail (the existing main access) or a
better-defined and hardened eastern trail. These trails would connect to
form a loop through the Lower Yosemite Fall area. Access to the base of
Lower Yosemite Fall for visitors with mobility impairments would be via
the redesigned and hardened eastern trail. Interpretive exhibits and
seating would be added to both the western and eastern trails. An
informal gathering/viewing area would be provided at the beginning of
the western trail, and an informal viewing area would be located east of
the shuttle bus stop. Stock (e.g., horse) use on trails would be managed
as described in the Yosemite Valley Plan (see Vol. IA, page
2-65).
- Rehabilitation, Relocation, and Installation of
Bridges.
Five of the existing historic
bridges along the eastern trail would be rehabilitated to allow
wheelchair access throughout the area. Bridge #1 would be relocated
to provide a better approach to a wheelchair-accessible boardwalk that
would pass over the millrace feature within the historic Hutchings
sawmill site. Construction and maintenance-related access to the
Bridge #1 area would be via the existing maintenance thoroughfare
through the nearby historic housing area. Materials staging would occur
within existing impacted areas adjacent to the historic housing area.
Both staging and access would be preceded by site-specific
reconnaissance for cultural resources and natural resources so that
there would be no potential impact to these resources. Bridge #2 would
be rehabilitated as a boardwalk to allow creek hydrology to be restored.
Bridge #3 would be rehabilitated to maintain access to the Muir plaque
and Clark bench. Bridge #4 would be removed. Bridges #5 and #6 (closest
to the shuttle bus stop) would be rehabilitated to help separate
bicyclists from pedestrians, reduce congestion, improve circulation, and
improve views. A seventh bridge (Bridge #7) would be constructed to
replace a bridge formerly located east of Bridge #3 and complete a
loop trail system. Yosemite Falls Bridge, the historic bridge across
Yosemite Creek at the base of Lower Yosemite Fall, would be
rehabilitated and the viewing platform enlarged.
The abutments for rehabilitated
bridges would be moved out of the creek channels and located farther up
on the banks. One new pier would be placed in the channel at
Bridge #3, and two new piers would be placed in the channel at
Bridge #6. Though a small portion of the channel would be blocked by new
bridge piers, a larger portion of the channel would be enlarged and its
hydrology would be restored as a result of removal of bridge abutments
from the channel. The two piers at the Yosemite Falls Bridge would
remain in the same location.
- View Corridor Maintenance.
The
Yosemite Valley Plan indicates the importance of maintaining
historic views of Yosemite Falls related to the cultural landscape of
Yosemite Valley, including the Lower Yosemite Fall area. Two historic
view corridors through the Lower Yosemite Fall area (Western Trail and
Hutchings) would be maintained by selective trimming of brush and
branches and by selective cutting and removal of trees and vegetation
within these view corridors. Removal of trees and vegetation to maintain
the view corridors would be preceded by site-specific reconnaissance for
cultural resources and natural resources, such as wetland vegetation,
bat roost sites, and bird nest sites, so that there is no potential
impact to those resources.
- Removal of Human-Built Rock-Rubble Pile.
Removal
of the rock-rubble pile downstream from the historic Yosemite Falls
Bridge would be preceded by studies, thereby ensuring that this action
would meet resource objectives.
Alternative 3 (As Evaluated in the Yosemite Valley Plan)
Alternative 3 would involve the same
actions described for Alternative 2, except for the location of the new
restroom, the seating use of a portion of the existing parking area, an
adjustment to the trail alignment near Bridge #1, a boardwalk at Bridge
#2, and the disposition of the rock-rubble pile. Figure 2-3 is the site
plan for Alternative 3. The Alternative 3 actions, all of which are
unchanged from the Yosemite Valley Plan, are described below.
- Restroom Relocation.
The
restroom north of the existing parking area would be removed and a new
restroom would be constructed east of Yosemite Creek and north of
Northside Drive, adjacent to the future Lower Yosemite Fall shuttle bus
stop.
- Parking Area Removal and Establishment of an Informal
Seating Area.
The existing parking area
would be removed, and a portion of the area would be replaced with an
informal seating area. However, a picnic area would not be installed in
the area as it would under Alternative 2. The remainder of the area
would be restored with locally native vegetation.
- New Shuttle Bus Stop.
A new
shuttle bus stop would be located on the north side of Northside Drive
east of the Yosemite Creek Bridge.
- Interim Tour Bus Unloading, Loading, and Parking.
To
address removal of the tour bus loading/unloading and parking area from
the Lower Yosemite Fall area, replacement loading/unloading and parking
spaces would need to be provided for tour buses. Long-term tour bus
loading/unloading would occur at the future new transit center in
Yosemite Village. For an interim time period, a bus passenger loading
and unloading zone would be provided along Northside Drive, near Cook’s
Meadow, using the existing turnout west of Village Drive. Until day tour
bus parking can be provided elsewhere, as called for in the Yosemite
Valley Plan, for the interim day tour buses would park in an
existing lane of Northside Drive, extending west of Camp 4. Day tour
buses would park in the north (right) lane of the road until passengers
are ready for pickup. When passengers are ready to load, buses would
return to Northside Drive near Cook’s Meadow for passenger pickup.
Interim parking for the few overnight tour buses would be provided in
existing parking areas associated with nearby lodging facilities in
Yosemite Valley.
Figure 2-3 Alternative 3 Site Plan (As
Evaluated in the Yosemite Valley Plan)
- Trail Alignment, Including Relocation of the Eastern
Trail Near Bridge #1.
The trail between
Bridges #1 and #2 would be rehabilitated and the trail northwest of Bridge
#1 would be relocated to provide wheelchair accessibility to the area. The
trail northwest of Bridge #1 would be placed on the millrace feature
within the Hutchings sawmill site.
- Rehabilitation of Trails.
Pedestrian
access to the base of Lower Yosemite Fall would be on either a
rehabilitated western trail (the existing main access) or a better-defined
and hardened eastern trail. The western and eastern trails would form a
loop through the area. Access to the base of Lower Yosemite Fall for
visitors with mobility impairments would be via the redesigned and
hardened eastern trail. Interpretive exhibits and seating would be added
to both the western and eastern trails. An informal gathering/viewing area
would be provided at the beginning of the western trail, and an informal
viewing area would be located east of the shuttle bus stop. Stock (e.g.,
horse) use on trails would be managed as described in the Yosemite
Valley Plan (see Vol. IA, page 2-65).
- Rehabilitation, Relocation, and Installation of
Bridges.
Five of the existing historic bridges
along the eastern trail would be rehabilitated to allow wheelchair
accessibility throughout the area. Bridge #1 would be relocated and an
accessible trail would pass through the millrace feature within the
historic Hutchings sawmill site. Bridge #2 would be rehabilitated. Bridge
#3 would be rehabilitated to maintain access to the Muir plaque and Clark
bench. Bridge #4 would be removed. Bridges #5 and #6 (closest to the
shuttle bus stop) would be rehabilitated to help meet a variety of visitor
experience needs and help separate bicyclists from pedestrians. A seventh
bridge (Bridge #7) would be constructed to replace a bridge formerly
located east of Bridge #3 to complete a loop trail system. Yosemite
Falls Bridge, the bridge across Yosemite Creek at the base of Lower
Yosemite Fall, would be rehabilitated and the viewing platform enlarged.
The abutments for the rehabilitated
bridges would be moved out of the creek channels and located farther up
on the banks. One new pier would be placed in the channel at
Bridge #3, and two new piers would be placed in the channel at
Bridge #6. Though a small portion of the channel would be blocked by new
bridge piers, a larger portion of the channel would be enlarged and the
hydrology would be restored as a result of removal of bridge abutments
from the channel. The two piers at the Yosemite Falls Bridge would
remain in the same location.
- View Corridor Maintenance.
The
Yosemite Valley Plan indicates the importance of maintaining
Yosemite Falls historic views related to the cultural landscape of
Yosemite Valley, including the Lower Yosemite Fall area. Two historic
view corridors through the Lower Yosemite Fall area would be maintained
by selective trimming of brush and branches and by selective cutting and
removal of trees and vegetation within these view corridors.
- Removal of Human-Built Rock-Rubble Pile.
The
rock-rubble pile would be removed without further study, based on the
information presented in the Yosemite Valley Plan.
Environmentally Preferable Alternative
The Council on Environmental Quality
regulations implementing NEPA and the National Park Service NEPA
guidelines require that "the alternative or alternatives which were
considered to be environmentally preferable" be identified (Council
on Environmental Quality [CEQ] Regulations, Section 1505.2).
Environmentally preferable is defined as "the alternative that will
promote the national environmental policy as expressed in NEPA’s Section
101. Ordinarily, this means the alternative that causes the least damage
to the biological and physical environment; it also means the alternative
that best protects, preserves, and enhances historic, cultural, and
natural resources" (CEQ 1981).
Section 101 of NEPA states that
it is the continuing responsibility
of the Federal Government to … (1) fulfill the responsibilities of
each generation as trustee of the environment for succeeding
generations; (2) assure for all Americans safe, healthful, productive,
and aesthetically and culturally pleasing surroundings; (3) attain the
widest range of beneficial uses of the environment without
degradation, risk to health or safety, or other undesirable and
unintended consequences; (4) preserve important historic, cultural,
and natural aspects of our national heritage, and maintain, wherever
possible, an environment which supports diversity, and variety of
individual choice; (5) achieve a balance between population and
resource use which will permit high standards of living and a wide
sharing of life’s amenities; and (6) enhance the quality of
renewable resources and approach the maximum attainable recycling of
depletable resources.
Alternative 2 is the environmentally
preferable alternative for the Lower Yosemite Fall Project, based on its
furtherance of the following national environmental policy goals.
Section 101 Requirement 1. "Fulfill
the responsibilities of each generation as trustee of the environment
for succeeding generations."
Conformance: Alternative
2 would best fulfill the responsibilities of each generation as
trustees of the environment for succeeding generations by ensuring the
protection of view corridors and restroom relocation away from
culturally sensitive areas. Alternative 1, no action, would not
protect the environment over time. Under Alternative 3, the view
corridor would not be as protected and the new restroom location would
interfere with a sensitive cultural area. Both Alternative 2 and
Alternative 3 propose virtually identical trail alignments, which
would be better defined than the existing trails, thereby reducing
visitor trampling in sensitive areas.
Section 101 Requirement 2. "Assure
for all Americans safe, healthful, productive, and aesthetically and
culturally pleasing surroundings."
Conformance: Under
Alternative 2, restroom relocation to an area that is not disruptive
to sensitive cultural areas, as well as protection of the view
corridor, would ensure that all Americans safe, healthful, productive,
and aesthetically and culturally pleasing surroundings.
Section 101 Requirement 3. "Attain
the widest range of beneficial uses of the environment without
degradation, risk to health or safety, or other undesirable and
unintended consequences."
Conformance: Restroom
relocation and protection of the view corridor under Alternative 2
would attain the widest range of beneficial uses of the environment,
risks to health or safety, or undesirable and unintended consequences,
namely retention of the inadequate restroom in its current location
and condition represented by Alternative 1.
Section 101 Requirement 4. "Preserve
important historic, cultural, and natural aspects of our national
heritage, and maintain, wherever possible, an environment which
supports diversity, and variety of individual choice."
Conformance: Alternative
2 would relocate the restroom to an area that is less disruptive to
sensitive cultural resources compared to Alternatives 1 and 3.
Alternative 2 would also better preserve the natural aspects by
protecting the view corridor.
Section 101 Requirement 5. "Achieve
a balance between population and resource use which will permit high
standards of living and a wide sharing of life’s amenities."
Conformance: Under
Alternatives 2 and 3, relocation of the restroom and location of a
picnic area or seating area, respectively, would achieve a balance
between population and resource use, which will permit high standards
of living and a wide sharing of life’s amenities. Alternative 1 does
not promote these standards.
Section 101 Requirement 6. "Enhance
the quality of renewable resources and approach the maximum attainable
recycling of depletable resources."
Conformance: Alternatives
2 and 3 would both achieve this requirement.
In conclusion, upon full consideration
of the elements of Section 101 of NEPA, Alternative 2 represents the
environmentally preferable alternative for the Lower Yosemite Fall area.
Actions Considered but Dismissed
For any project or activity within
Yosemite Valley, a diverse range of actions could be considered. For the
Lower Yosemite Fall area, a full range of alternatives was considered in
the Yosemite Valley Plan. It is not the objective of this
environmental assessment to revisit the range of alternatives in the Yosemite
Valley Plan for the Lower Yosemite Fall area. Alternative actions have
been eliminated from detailed study for any one or a combination of the
following reasons:
- Does not implement the decisions of the Yosemite
Valley Plan for the Lower Yosemite Fall area.
- Does not satisfy guidance criteria, meet project
goals, or resolve park planning needs in Yosemite Valley.
- Less environmentally damaging options are available.
- Unacceptable environmental, cultural, or scenic
impacts would be caused.
- Is not technically or economically feasible.
Those alternative actions considered but
eliminated from detailed study are described below.
Construct a New Restroom on the South Side of Northside
Drive Across from Lower Yosemite Fall Area
A few public comments received during
the scoping period for this environmental assessment suggested that the
National Park Service consider demolishing the existing Lower Yosemite
Fall area restroom and construct a new restroom on the south side of
Northside Drive across from the Lower Yosemite Fall area. This alternative
action was considered but dismissed for the following reasons:
- Does not satisfy guidance criteria, meet project
goals, or resolve park planning needs in Yosemite Valley – The
restroom would not be centrally located and would not be within
proximity to the shuttle bus stop and eastern trail.
- Unacceptable environmental, cultural, or scenic
impacts would be caused – The restroom would interfere with the view
of Yosemite Falls, especially for pedestrians approaching from
Yosemite Lodge.
- Does not satisfy guidance criteria, meet project
goals, or resolve park planning needs in Yosemite Valley – The
restroom would not be located within proximity to the seating or
picnic area.
- Does not satisfy guidance criteria, meet project
goals, or resolve park planning needs in Yosemite Valley – The
restroom would be within proximity to the existing Yosemite Lodge
lobby restroom and would therefore not efficiently serve visitors to
the Lower Yosemite Fall area.
Keep the Existing Restroom and Construct a New Restroom
at the Southeast Corner of the Parking Area
The National Park Service considered
maintaining the existing restroom and constructing an additional restroom
at the southeast corner of the existing parking area. This alternative
action was considered but dismissed for the following reasons:
- Does not satisfy guidance criteria, meet project
goals, or resolve park planning needs in Yosemite Valley – Two
buildings would not minimize or reduce the amount of built environment
in the Lower Yosemite Fall area.
- Does not satisfy guidance criteria, meet project
goals, or resolve park planning needs in Yosemite Valley – The
existing restroom is inadequate. It is undersized for the number of
users, unsightly, in need of major rehabilitation, and does not meet
standards for accessibility under the Americans with Disabilities Act.
- Unacceptable environmental, cultural, or scenic
impacts would be caused – The existing restroom would interfere with
the view of Yosemite Falls.
Modify the Existing Parking Area to Accommodate a
Shuttle Bus Stop
During the public scoping process for
this environmental assessment, it was suggested that the existing parking
area be retained and modified to accommodate the shuttle bus stop. This
alternative action was considered but dismissed for the following reasons:
- Does not implement the decisions of the Yosemite
Valley Plan for the Lower Yosemite Fall area – The approved Yosemite
Valley Plan called for removing the existing parking area.
- Does not implement the decisions of the Yosemite
Valley Plan for the Lower Yosemite Fall area – As approved in
the Yosemite Valley Plan, the current alignment of Northside
Drive will be converted to a multi-use paved trail in the future and
therefore not support vehicle access to the parking area.
Construct the Restroom in the Southwest Corner of the
Parking Area or in the Traffic Island in the Middle of the Parking Area
During the public scoping process for
this environmental assessment, it was suggested that the relocated
restroom be constructed in the southwest corner or middle of the parking
area. This alternative action was considered by the National Park Service
but dismissed for the following reasons:
- Does not satisfy guidance criteria, meet project
goals, or resolve park planning needs in Yosemite Valley – The
restroom would be several hundred feet from the shuttle bus stop and
eastern trail and would not support the goal of distributing visitors
throughout the Lower Yosemite Fall area. Visitors would be drawn to
the western trail.
- Unacceptable environmental, cultural, or scenic
impacts would be caused – It would be difficult to locate the
restroom without putting it in the western trail view corridor.
During the public scoping process for
this environmental assessment, it was suggested that the new restroom be
built in the center of the existing parking area and trees be planted
around the new building. This alternative was considered and dismissed by
the National Park Service for the following reasons:
- Does not satisfy guidance criteria, meet project
goals, or resolve park planning needs in Yosemite Valley – The
restroom would be several hundred feet from the shuttle bus stop and
the eastern trail and would not support the goal of distributing
visitors throughout the Lower Yosemite Fall area.
- Unacceptable environmental, cultural, or scenic
impacts would be caused – The restroom would interfere with the view
of Yosemite Falls, especially for pedestrians approaching from
Yosemite Lodge.
Mitigation Measures Common to All Action Alternatives
The National Park Service places a
strong emphasis on avoidance, minimization, and mitigation of impacts.
This section summarizes mitigation measures suggested for each resource
area that would largely offset potential impacts to these resource topics.
No mitigation measures are proposed for Alternative 1.
Best Management Practices During Project Construction
To ensure that implementation of either
of the action alternatives largely offsets impacts to natural and cultural
resources and the quality of the visitor experience, the following Best
Management Practices would be implemented, as appropriate, prior to,
during, and/or after specific construction. (For the purposes of this
discussion, construction includes major repair and/or rehabilitation,
demolition, deconstruction, reconstruction, restoration, etc.) Specific
tasks would include, but not be limited to, the following:
- Implement a compliance-monitoring program in order to
stay within the parameters of National Environmental Policy Act and
National Historic Preservation Act compliance documents, U.S. Army
Corps of Engineers Section 404 permits, etc. The compliance-monitoring
program would oversee these mitigation measures and would include
reporting protocols.
- Implement a natural resource protection program.
Standard measures could include construction scheduling, biological
monitoring, erosion and sediment control, use of fencing or other
means to protect sensitive resources adjacent to construction, removal
of all food-related items or rubbish to bear-proof containers, topsoil
salvage, and revegetation. The program could include specific
construction monitoring by resource specialists as well as treatment
and reporting procedures.
- Implement a cultural resource protection program.
Standard measures could include consideration of adaptive reuse,
relocation, and salvage of historic building materials; archeological
monitoring during ground-disturbing activities (in keeping with the
1999 Programmatic Agreement); use of fencing or other means to protect
sensitive resources adjacent to construction; and preparation of a
discovery plan to handle unanticipated exposure of buried human
remains or previously unknown cultural resources. The program could
include specific construction monitoring by resource specialists and
culturally associated Indian people, as well as treatment and
reporting procedures.
- Implement a traffic control plan, as warranted.
Standard measures could include strategies to maintain safe and
efficient traffic flow during the construction period.
- Implement a dust abatement program. Standard dust
abatement measures could include the following elements: water or
otherwise stabilize soils, cover haul trucks, employ speed limits on
unpaved roads, minimize the clearing of vegetation, and revegetate
post-construction.
- Implement standard noise abatement measures during
construction. Standard noise abatement measures could include the
following elements: a schedule that minimizes impacts to adjacent
noise-sensitive uses, use of the best-available noise control
techniques wherever feasible, use of hydraulically or electrically
powered impact tools when feasible, and location of stationary noise
sources as far from sensitive uses as possible.
- Implement a noxious weed abatement program. Standard
measures could include the following elements: ensure
construction-related equipment arrives on site free of mud or
seed-bearing material, certify all seeds and straw material as
weed-free, identify areas of noxious weeds before construction, treat
noxious weeds or noxious weed topsoil prior to construction (e.g.,
topsoil segregation, storage, or sterilization), and revegetate with
appropriate native species.
- Implement a spill prevention and pollution control
program for hazardous materials. Standard measures could include
hazardous materials storage and handling procedures; spill
containment, cleanup, and reporting procedures; and limitation of
refueling and other hazardous activities to upland/nonsensitive sites.
- Implement measures to reduce adverse effects of
construction on visitor safety and experience.
- Implement a notification program. Standard measures
could include notification of sensitive receptors, utilities, and
emergency response units prior to construction activities.
- Implement an interpretation and education program.
Continue directional signs and education programs to promote
understanding among park visitors.
- Use silt fences, sedimentation basins, etc., in
construction areas to reduce erosion, surface scouring, and discharge
to water bodies.
- Develop revegetation plans for the disturbed area and
require the use of native species. Revegetation plans would specify
seed/plant source, seed/plant mixes, soil preparation, etc. Salvaged
vegetation would be used to the extent possible.
- Delineate wetlands and apply protection measures
during construction. Wetlands would be delineated by qualified
National Park Service staff or certified wetland specialists and
clearly marked prior to construction work. Construction activities
would be performed in a cautious manner to prevent damage caused by
equipment, erosion, siltation, etc.
- Develop architectural character guidelines for new
construction in or near historic districts. All new development would
be designed to be compatible with historic resources in terms of
scale, massing, materials, architectural elements, and orientation
with designated historic sites, structures, or districts.
Construction Mitigation Measures
Construction of the Lower Yosemite Fall
Project would begin in the spring of 2002 and continue through the fall of
2004. Construction activities would occur year round, weather permitting.
Construction sites would be fenced off and/or flagged to maintain visitor
safety during both work and non-work hours.
Equipment that would likely be used for
project activities would include but not be limited to the following:
crane, front end loader, jackhammer, pneumatic hammer, dump truck
(10-cubic-yard capacity), paving machine, trencher, scraper, backhoe,
bobcat, and forklift.
Although most of the material within the
Lower Yosemite Fall area would be reused elsewhere on site, asphalt and
demolition debris would be moved off site. Many materials necessary for
the construction of a new restroom and for bridge and trail construction
would be brought in from outside the park. Trucks are expected to travel
to and from the construction site, bringing in or removing
building/asphalt material. The number of truck trips anticipated for
construction is not considered a significant change from existing
conditions for the limited time construction would be underway. For
activities occurring adjacent to Yosemite Lodge, construction timing would
be limited to minimize impacts to lodge visitors. For heavy construction
involving loud noises, construction activity may start no earlier than
9 a.m.
An adequate portion of the existing
parking area would be made available to the contractor for construction
staging. The National Park Service would ensure that interim parking is
available for Lower Yosemite Fall area visitors during project
construction.
When construction is under way, the tour
buses that currently park at the lot and unload passengers would be
displaced. The National Park Service would offset this temporary loss and
inconvenience through the following strategies:
- Interim tour bus loading and unloading in an area
east of the new shuttle bus stop.
- Interim parking of the tour buses along Northside
Drive, west of Camp 4 and Yosemite Lodge.
Construction activities would be phased
so that visitors’ recreational use of the area would not be overly
restricted. Phasing would occur over the course of approximately 2½
years; breaks may be taken during bad weather. Construction would be
phased so that only one trail would be reconstructed at any given time.
The seating/picnic area located at the southern portion of the parking
area would be among the last project elements constructed. During this
last phase of construction, the parking area would be removed in parts so
that it would remain in use as a construction staging area.
Resource-Specific Mitigation Measures
Wetlands
The following measures would largely
offset potential impacts to identified wetlands in the Lower Yosemite Fall
area.
- All facilities would be sited to avoid wetlands or
comply with Executive Order 11990 (Protection of Wetlands), the Clean
Water Act, and Director’s Order 77-1 (Wetland
Protection; see Appendix A for further discussion).
- Increased caution and protective fencing would be
used to protect wetlands from damage caused by construction equipment,
erosion, siltation, and other ground-disturbing activities, notably
those wetlands near Bridges #3, #5, and #6 and the Yosemite Falls
Bridge.
- Design of all bridges in the Lower Yosemite Fall area
would include removal of abutments from the wetlands and providing
longer spans to avoid wetlands below the bridges; these longer spans
would be designed to avoid direct impacts to delineated wetlands.
- Construction materials would be prevented from
escaping work areas, especially near streams or natural drainages, and
impacting downgradient wetlands.
- Every effort would be made to avoid adversely
impacting wetlands during view corridor maintenance activities.
- Removal of trees and vegetation to maintain the view
corridors would be preceded by site-specific reconnaissance for
natural resources, such as wetland vegetation, bat roost sites, and
bird nest sites, to avoid potential impacts to those resources.
Soils
Soil erosion and contamination result in
impacts to air and water quality as well as to habitats for plant and
wildlife species. The following mitigation efforts would focus on
minimizing or largely offsetting these impacts.
- Use approved siltation and sediment control devices
in construction areas to reduce erosion and surface scouring.
- Use approved siltation and sediment control devices
appropriate to the situation in grading areas to capture soil erosion
before discharge to braided stream channels.
- Use water bars in temporary access roads to control
and reduce surface scouring.
- Use dust abatement measures (water applications) to
reduce airborne soil erosion, including setting speed limits for
construction vehicles in unpaved areas and hauling cover soil and
debris away in trucks.
Measures would be taken to largely
offset the potential for public exposure to noxious materials or
contaminants that may be present during construction near the Lower
Yosemite Fall area. Potential exposure would be controlled by providing
established and maintained walkways and bridges across the site, covering
walking paths with clean soil and asphalt, and providing barrier fencing
along trails.
Hydrology and Water Quality
The following mitigation measures would
be applied to largely offset potential impacts to water resources.
- Take measures to control erosion, sedimentation, and
compaction, and thereby reduce water pollution.
- Remove hazardous waste materials generated during
implementation of the project from the project site immediately.
- Place construction debris in refuse containers at
least daily.
- Dispose of refuse at least weekly. No refuse would be
burned or buried inside the park.
- To the extent possible, schedule the use of
mechanical equipment during periods of low precipitation and low
groundwater levels to reduce the risk of accidental hydrocarbon leaks
or spills. When mechanical equipment is necessary outside of low
precipitation periods, use National Park Service–approved methods to
protect soil and water from contaminants.
- Dispose of volatile wastes and oils in approved
containers for removal from construction sites to avoid contamination
of soils, drainages, and watercourses.
- Inspect equipment for hydraulic and oil leaks prior
to use on construction sites, and implement inspection schedules to
prevent contamination of soil and water.
- Keep absorbent pads, booms, and other materials on
site during projects that use heavy equipment to contain oil,
hydraulic fluid, solvents, and hazardous material spills.
- Integrate stormwater pollution controls, in
accordance with National Pollution Discharge Elimination requirements
that concentrate runoff shall be integrated into design, construction,
and operation of the new restroom, and paved trails.
Floodplains
Actions occurring within the Merced
River floodplain would be subject to the provisions of the National Park
Service Floodplain Management Guideline 1993 (Special Directive
93-4; Director’s Order NPS 77; see Appendix A for further discussion)
and Executive Order 11988 (Protection of Floodplains). The following
mitigation measures would be applied to largely offset potential impacts
to facilities within the floodplain:
- An emergency preparedness plan would be developed for
any facilities within the floodplain. The National Park Service would
continue to maintain and update a flood evacuation plan. The plan
details responsibilities of individual park employees for advanced
preparedness measures; removing or securing park property, records,
and utility systems; monitoring communication; and conducting salvage
operations.
- The site design or modifications would minimize harm
to floodplain values and risks to life and property. The design of all
new structures would incorporate methods for minimizing flood damage
as contained in the National Flood Insurance Program Floodplain
Management Criteria for Flood-Prone Areas (CFR 44:60.3) and in
accordance with any local, county, or state requirements for
flood-prone areas.
- The design for the impermeable areas would ensure
natural resources are not damaged by pavement runoff from normal
rainfall events.
Vegetation (Including Special-Status Species)
Mitigation actions would occur prior to,
during, and/or after construction to largely offset immediate and
long-term impacts to vegetation. Mitigation would include the following:
- Develop revegetation and ecological restoration plans
for disturbed areas, using native species from the same gene pool.
Revegetation plans would specify soil preparation, native seed/plant
mixes, seed/plant sources, and mulching for all areas disturbed by
construction activities.
- Develop and implement a monitoring plan to ensure
successful revegetation, maintain plantings, and replace unsuccessful
plant materials.
- Salvage vegetation to the extent possible for use in
revegetating disturbed areas.
- Enforce construction specifications regarding soil
salvage and reuse, trenching, plant protection, and finished grading.
- Site buildings, bridges, and trails to minimize
impacts to vegetation. Avoid large trees and hardwood and riparian
species, where possible.
- Select base course and fill materials for
compatibility with native granitic soils to minimize risk of
introducing non-native plant seeds. Monitor areas where fill is
imported from outside the park, and eradicate non-native plants. Apply
standard techniques to prevent non-native plant encroachment.
- Develop monitoring and mitigation plans for managing
non-native plants within and immediately surrounding construction and
developed areas.
- Confine all construction operations to specified
project work limits. Install temporary barriers to protect natural
surroundings (including trees, plants, and root zones) from damage.
Repair or replace damaged trees and plants, and avoid fastening ropes,
cables, or fences to trees.
- Install fencing to minimize use of highly sensitive
sites such as creek edges and wetlands, and install signs as needed to
direct use to more appropriate areas. Placement of fencing and signs
would be developed in consultation with National Park Service cultural
resource staff.
- Use native or seed-free mulch to minimize surface
erosion and introduction of non- native plants.
- In site design, define trails and boundaries of
development to confine human use and reduce radiating impacts.
Wildlife
Mitigation actions would occur prior to,
during, and after construction to minimize immediate and long-term impacts
to wildlife. Many of the measures listed above for vegetation would also
benefit wildlife by helping to preserve habitat. Actions to largely offset
impacts specific to wildlife would include the following:
- Prior to construction, evaluate habitat for species
likely to occur and take steps to minimize impact on those species
determined to be especially vulnerable.
- Limit the effects of light and noise on adjacent
habitat through controls on construction equipment, and through site
design of facilities, to limit long-term effects of resulting
development. Limit noise from transit vehicles through application of
best available low noise technologies and use of operating strategies.
- Install fencing and signs to direct visitors away
from sensitive habitats.
- Provide adequate education and enforcement to limit
visitor activities that are destructive to wildlife and habitats.
- When possible, schedule any disruptive construction
activities to occur when effects on wildlife would be minimal (for
example, after birds nesting season and when bats are neither
hibernating nor have young).
- Preserve, where possible, natural features with
obvious high value to wildlife, such as tree snags.
- Maintain routes of escape from excavated pits and
trenches for animals that might fall in. Cover post holes and other
narrow pits with boards. During construction, maintain vigilance for
animals caught in excavations and take appropriate actions to free
them.
- Provide safeguards to limit the chance of pollution
spills, both during construction and during subsequent use of
completed facilities. This is especially important where activities
are near aquatic or wetland habitats.
- Prior to tree-thinning activities in view corridors,
National Park Service biologists would screen the area for bat roosts,
nesting birds, snags, and other features that are important wildlife
habitat.
Human/Wildlife Conflicts
- Require construction personnel to adhere to park
regulations concerning food storage and refuse management.
- Provide bear-proof containers in the seating/picnic
area.
- Provide adequate cleaning of areas and garbage pickup
to limit wildlife access to human food.
Special-Status Wildlife Species
The U.S. Fish and Wildlife Service is
responsible for administering conservation and recovery measures to
protect federally listed species, as directed in the Endangered Species
Act of 1973. The U.S. Fish and Wildlife Service has prescribed
conservation measures specific to the Yosemite Valley Plan (see
Vol. II, Appendix L) as part of its Biological Opinion. The Biological
Opinion contains Terms and Conditions that are non-discretionary. In
addition, the National Park Service has developed mitigation measures for
all special-status species. These mitigation measures can be found in the
Biological Assessment completed for the Yosemite Valley Plan (see
Vol. II, Appendices A and K). In addition, the following measure would be
applied to largely offset potential impacts to special-status wildlife
species.
- Survey view corridors (before selective thinning
takes place) to identify any likely bat roosting trees and snags.
Retain identified roosting trees and snags to serve as habitat for
special-status bats.
Air Quality
The National Park Service would seek to
perpetuate the best possible air quality by aggressively promoting and
pursuing measures to preserve, protect, and enhance air resources.
Moreover, actions are subject to the provisions of the Clean Air Act and
the forthcoming State of California’s State Implementation Plan. The
following mitigation measures would be applied to largely offset potential
air quality impacts in the Lower Yosemite Fall area.
- Dispose of refuse at least weekly. No refuse would be
burned inside the park.
- Employ dust abatement measures.
Noise
To largely offset the effects of project
construction noise, the following measures would be applied.
- Implement standard noise abatement measures during
park operations. Standard noise abatement measures could include the
following elements: a schedule that minimizes impacts to adjacent
noise-sensitive uses, use of best available noise control techniques
wherever feasible, use of hydraulically or electrically powered impact
tools when feasible, and location of stationary noise sources as far
from sensitive uses as possible.
- Site and design facilities to minimize objectionable
noise.
Archeological, Ethnographic, and Cultural Landscape
Resources
The National Park Service has developed
a Programmatic Agreement in consultation with the California State
Historic Preservation Officer, the Advisory Council on Historic
Preservation, culturally associated American Indian tribes, and the
public. This agreement stipulates a process for the treatment of historic
properties, including identification, evaluation, and, if necessary,
mitigation of adverse effects. Standard mitigation measures may be used in
situations where an undertaking would adversely affect a historic
property. These include documentation, interpretation, materials salvage,
and National Register re-evaluation.
Construction monitoring would be
performed in keeping with the Archeological Synthesis and Research
Design, Yosemite National Park, California (Hull and Moratto 1999),
and as specified in the 1999 Programmatic Agreement (NPS 1999a). The
project would strive to avoid intact deposits through careful project
design. If intact deposits cannot be avoided, all data recovery to
retrieve important information would be conducted in accordance with the
Yosemite Programmatic Agreement. Where previously unknown American Indian
burials and archeological sites are discovered during construction,
provisions outlined in the Native American Graves Protection and
Repatriation Act and its implementing regulations would also be followed.
Through existing agreements and ongoing
consultation with culturally associated American Indian tribes, access to
and use of special resources in Yosemite Valley would continue. To reduce
potential impacts to ethnographic sites, designs would be developed to
prevent visitors from wandering off designated trails. Additional measures
to largely offset potential impacts to cultural resources are listed
below.
- The park would continue to consult with tribes
throughout the site-specific design process and project implementation
to avoid or mitigate damage to ethnographic resources (e.g., trails
would be better defined and barriers would be created to minimize
trampling of ethnographic resources).
- Impacts to ethnographic resources would be mitigated
through actions developed in consultation with culturally associated
American Indian tribes.
- A parkwide gathering plan would be developed in
consultation with American Indian people, as specified in the
Programmatic Agreement. The plan could include strategies for
identifying and continuing to help provide access to gathering areas,
continuing to provide access to traditional use or spiritual areas,
and screening new development from traditional use areas.
- Impacts would be mitigated by continuing to provide
access to traditional and spiritual locations, and where appropriate
screening new development from traditional use areas.
- Removal of trees and vegetation to maintain the view
corridors would be preceded by site-specific reconnaissance for
cultural resources to avoid potential impacts to those resources.
- Interim bus parking would not be adjacent to the
Indian Cultural Center when it is constructed.
- In order to discourage visitor trampling of
identified ethnographic resources, barriers and signs would be placed
along the trails from Bridge #6 to the shuttle bus stop and from
Bridge #6 to the informal viewing area in the Hutchings view corridor.
- New bridges would be designed in keeping with design
criteria guidelines taken from the bridges they would replace so that
they would fit within and be sensitive to the cultural landscape.
Scenic Resources
Mitigation measures for scenic resources
are designed to minimize visual intrusions. Many of the mitigation
measures identified in the Vegetation section, above, would assist to
largely offset potential scenic impacts. These include:
- Minimize development footprints.
- Choose building materials that are visually
compatible or do not compete with the landscape.
- Provide vegetative screening, where applicable.
The following specific mitigation
measures would be implemented to largely offset potential impacts to
scenic resources related to view corridors shown on figure 2-2:
- Consult with the National Park Service vegetation
ecologist during the planning and implementation phases of
revegetation activity. Base revegetation prescriptions on resource
objectives for the site and a site-specific analysis of the plant
community, soils, and cultural resources. Consult with the landscape
architect or historical architect for protection of cultural
landscapes.
- Use selective trimming and cutting techniques when
establishing and maintaining vistas. Some vegetation cover would be
left on the ground while a viewing area is opened up through standing
trees. Develop the appearance of a natural setting by leaving trees of
different size classes. Trim standing trees so that low limbs do not
block scenic view corridors and in a manner that no cutting pattern is
evident.
- Dispose of wood in accordance with strategies defined
in the Yosemite Valley Plan. Whenever possible, the preferred
method is decomposition on site to allow cut vegetation to cycle
through the ecosystem. Fire hazard fuels must be considered in certain
plant communities where fire has not been allowed.
- Provide interpretive materials and programs to
communicate the park’s scenic management policies and procedures for
establishing, restoring and maintaining scenic vista points or areas
and, more importantly, for interpreting the scene at hand and its
historical or natural significance.
- Wherever possible, revegetation efforts in natural
zones would use seeds, cuttings, or transplants representing species
and gene pools native to the ecological area of the park in which the
revegetation project is occurring.
- Avoid impacts to cultural resources during management
of the vistas. If avoidance is not feasible or prudent, the National
Park Service would undertake separate compliance with NEPA and the
National Historic Preservation Act.
- When approval is granted for removal of trees to
maintain view corridors, Best Management Practices required to protect
park values may include, but not be limited to, monitoring of
operations on or near the site by an archeologist, complete site
avoidance, the establishment of an equipment exclusion zone,
directional falling of adjacent trees away from the site area, use of
rubber-tired equipment only, or restrictions on piling and burning of
slash on site. These protection measures are generally used in
combination with one another (Foster 1995).
Visitor Experience
The following mitigation strategies
would be implemented to largely offset potential impacts to visitor
experience at the Lower Yosemite Fall area.
- Develop an exhibit plan for the Lower Yosemite Fall
Project to redirect exhibits from roadside to trailside
interpretation.
- Increase ranger programs for the Lower Yosemite Fall
Project to provide more interpretive opportunities.
- Continue to develop standards and indicators to
improve resource protection and visitor experience.
- Limit the interim day tour bus parking adjacent to
Camp 4 to the time of day that would impact campers the least.
Park Operations and Facilities
The following mitigation measures would
be implemented to largely offset potential impacts to park utilities.
- Utility locations would be verified through field
survey (potholing) and use of the Underground Service Alert services
prior to the start of construction.
- The National Park Service would observe California
Department of Health Services standards that require (1) a 10-foot
horizontal separation between parallel sewer and water mains;
(2) 1-foot vertical separation between perpendicular water and
sewer line crossings (in the event that separation requirements cannot
be maintained, California Department of Health Services would obtain
variance through provisions of water main encasement, or other means
deemed suitable by California Department of Health Services); and (3)
encasement of water mains in protective sleeves where a new sewer
force main (pipeline) crosses under or over an existing sewer main.
- The National Park Service would observe guidelines
specified in the National Plumbing Code, International Plumbing Code,
or Building Officials and Code Administration (BOCA) National Plumbing
Code regarding utilities installation and or abandonment of pipelines.
Utility services that are unexpectedly
interrupted because of construction activities would be reconnected
promptly. In addition, all phases of construction that may result in a
disruption of utility service would require advance notification to all
residents, concession activities, and other National Park Service visitor
activities.
Transportation
The following transportation mitigation
measures would be implemented to largely offset potential impacts to park
resources and operations and facilities.
- Integrate stormwater pollution control measures into
parking area design and construction.
- Implement a traffic management program, as warranted.
Standard measures could include strategies to maintain safe and
efficient traffic flow during the construction period.
- Install appropriate traffic signs, and stripe both
the interim day tour bus loading/unloading area and parking spaces.
- Restrict buses from idling at all times (whether
loading or unloading).
- Staff both the interim bus loading/unloading area and
the interim bus parking area to ensure that bus operations do not
delay traffic. Staff would ensure that (1) the interim bus loading
area is always available for loading and unloading passengers, (2)
several buses do not pick up passengers simultaneously or when space
is not available, and (3) buses do not idle while parked or while
waiting for passengers to load and unload.
Energy Consumption
In April 1999, the United States
Department of the Interior entered into a formal Memorandum of
Understanding with the United States Department of Energy to promote the
use of energy-efficient and renewable energy technologies and practices in
national parks. While the Memorandum of Understanding does not mandate
specific energy-efficient and renewable energy technologies, it does
provide a framework to promote their implementation and use. The
Memorandum of Understanding would guide the selection of energy efficient
technologies for the Lower Yosemite Fall Project and would largely offset
potential impacts to energy consumption.
Summary of Environmental Consequences
Table 2-1 summarizes and compares the
potential environmental consequences associated with each alternative.
Potential environmental consequences are analyzed in more detail in
Chapter 4.
Table 2-1
Summary of Environmental Consequences
|
Alternative 1
(No Action) |
Alternative 2
(Preferred) |
Alternative 3
(As Evaluated in the Yosemite Valley Plan) |
|
NATURAL RESOURCES |
|
WETLANDS |
|
Overall, there would be a long-term, minor,
adverse impact on wetlands due to human use and trampling in areas
where trails are not well defined and due to bridge abutments
located within creek channels that could alter hydrologic flows that
support wetlands. |
Overall, there would be a long-term, minor,
beneficial impact on wetlands due to the removal of bridge abutments
from creek channels. |
Overall, there would be a long-term, minor,
beneficial impact on wetlands due to the removal of bridge abutments
from creek channels. |
|
GEOLOGY, GEOLOGIC HAZARDS, AND SOILS |
|
Overall, under Alternative 1 there would be a
long-term, negligible, adverse impact on soils from off-trail use
that could increase erosion. There would be a long-term, negligible,
adverse impact on geology or geologic hazards due to retention of
the restroom and the parking area within the rockfall shadow zone. |
Overall, there would be a long-term, minor,
beneficial impact on soils due to better defined trails that would
reduce heavy use in off-trail areas under Alternative 2. There would
be a long-term, minor, adverse impact on geology or geologic hazards
due to placement of the picnic area and seating area partially
within the rockfall shadow zone. |
Overall, there would be a long-term, minor,
beneficial impact on soils due to more well-defined trails that
would reduce heavy use in off-trail areas under Alternative 3. There
would be a long-term, minor, adverse impact on geology or geologic
hazards due to placement of the seating area partially within the
rockfall shadow zone. |
|
HYDROLOGY AND WATER QUALITY |
|
Overall, there would be a long-term, minor,
adverse impact on hydrology and water quality under Alternative 1
due to surface runoff from the parking lot, which could introduce
pollutants into nearby creeks. |
Overall, there would be a long-term, moderate,
beneficial impact on hydrology and water quality under Alternative 2
due to the removal of the parking lot and removal of the bridge
abutments from creek channels to accommodate hydrologic flows. |
Overall, there would be a long-term, moderate,
beneficial impact on hydrology under Alternative 3 due to the
removal of the parking lot and removal of bridge abutments from
creek channels to accommodate hydrologic flows. |
|
FLOODPLAINS |
|
Overall, there would be long-term, minor, adverse
floodplain impacts on health and safety under Alternative 1,
relating to trail alignment and bridge rehabilitation. |
Overall, there would be long-term, minor, adverse
impacts to the floodplain under Alternative 2 due to
construction of the new restroom and picnic area and seating area in
the 100-year floodplain. |
Overall, there would be long-term, minor, adverse
impacts to the floodplain under Alternative 3 due to the
construction of the new restroom and seating area within the
100-year floodplain. |
|
VEGETATION |
|
Overall, long-term, minor, adverse impacts to
vegetation would continue under Alternative 1 from trampling and
heavy foot traffic near the restroom and other off-trail areas (as a
result of poorly defined trails and deteriorated bridges) and from
heavy exposure to vehicle emissions. |
Overall, there would be a long-term, moderate,
beneficial impact on vegetation under Alternative 2 due to the
removal of the parking area, revegetation of most of the parking
area, relocation of the restroom, and alignment and rehabilitation
of trails. |
Overall, there would be a long-term, moderate,
beneficial impact on vegetation under Alternative 3 due to the
removal of the parking lot and revegetation of most of the parking
area and rehabilitation and realignment of trails. |
|
WILDLIFE |
|
Overall, there would be long-term, negligible,
adverse impacts to wildlife under Alternative 1, because the
existing facilities are impacting wildlife habitat continuity. |
Overall, there would be a long-term, negligible,
adverse impact on wildlife species or habitat due to tree removal
associated with trail alignment and rehabilitation, bridge
rehabilitation and construction, and view corridor maintenance. |
Overall, there would be a long-term, negligible,
adverse impact on wildlife species or habitat under Alternative 3
due to tree removal associated with trail alignment and
rehabilitation, bridge rehabilitation and construction, and view
corridor maintenance. |
|
SPECIAL-STATUS SPECIES |
|
Overall, there would be long-term, negligible,
adverse impacts to special-status species under Alternative 1. Any
negative effects to federally listed species or their habitat would
be imperceptible. |
Overall, there would be long-term, minor,
beneficial impacts to the Wawona riffle beetle from improved river
flow dynamics. |
Overall, there would be long-term, minor,
beneficial impacts to the Wawona riffle beetle from improved river
flow dynamics. |
|
AIR QUALITY |
|
Overall, there would be a long-term, negligible,
adverse impact to air quality under Alternative 1 due to the
concentration of vehicle emissions in the existing parking area. |
Overall, there would be a long-term, minor,
adverse impact on air quality under Alternative 2 because
vehicle emissions would remain unchanged but shift from the Lower
Yosemite Fall area to other areas in Yosemite Valley. |
Overall, there would be a long-term, minor,
adverse impact on air quality because vehicle emissions would remain
unchanged but shift from the Lower Yosemite Fall area to other areas
in the Yosemite Valley. |
|
NOISE |
|
Overall, there would be a long-term, minor,
adverse impact on noise levels under Alternative 1 as a result of
vehicle accessing and parking in the parking area. |
Overall, there would be long-term, minor, adverse
impacts on noise levels in the Lower Yosemite Fall area under
Alternative 2 due to the removal of the parking area and associated
cars and buses, but some of these impacts would be shifted to other
areas in Yosemite Valley. |
Overall, there would be a long-term, minor adverse
impact on noise levels in the Lower Yosemite Fall area under
Alternative 3 resulting from the removal of the parking area and
associated cars and buses, but some of these impacts would be
shifted to other areas in Yosemite Valley. |
|
CULTURAL RESOURCES |
|
ARCHEOLOGICAL RESOURCES |
|
Overall, there would be long-term, minor, adverse
impacts to archeological resources under Alternative 1 from the
existing restroom location, parking area, and trail alignments. |
Local, long-term, minor, adverse impacts to
archeological sites CA-Mrp-240/303/H, YC12, YC5, Rock Ring, and
CA-Mrp-749 from grading and removal of cultural deposits. Negligible
impacts to CA-Mrp-58 due to avoidance of vegetation removal during
view corridor maintenance. |
Local, long-term, minor, adverse impacts to
archeological sites CA-Mrp-240/303/H, YC12, YC5, Rock Ring, and
CA-Mrp-749 from grading and removal of cultural deposits. Negligible
impacts to CA-Mrp-58 due to avoidance of vegetation removal during
view corridor maintenance. |
|
ETHNOGRAPHIC RESOURCES |
|
Overall, there would be long-term, minor, adverse
impacts to ethnographic resources under Alternative 1 due to
location of existing restroom, parking area, and shuttle bus stop. |
Local, long-term, minor, beneficial impact to Koom-I-ne
village site ethnographic resource from removal of existing
restroom. Local, long-term, moderate, adverse impacts due to
establishment of trail through helli, California black oak,
bedrock milling feature site, and bracken fern sites. |
Local, long-term, moderate, adverse impact to
traditional mushroom gathering area (helli) and grove of
California black oaks used by contemporary American Indians; impact
due to construction of new restroom. Local, long-term, moderate,
beneficial impact to Koom-I-ne village site ethnographic
resource from removal of existing restroom. Local, long-term,
moderate, adverse impacts due to establishment of trail through helli,
California black oak, bedrock milling feature site, and bracken fern
sites. |
|
CULTURAL LANDSCAPE RESOURCES |
|
Overall, there would be a long-term, moderate,
adverse impact to cultural landscape resources under
Alternative 1, due to lack of maintenance of view corridors. |
Local, long-term, minor, beneficial impact to
Valleywide cultural landscape from removal of current restroom.
Local, long-term, minor, beneficial impact to cultural landscape
from construction of new restroom outside of key ethnographic
resource area. Local, long-term, moderate, adverse impacts to
Hutchings Orchard site, the millrace feature at the Hutchings
sawmill site, Lost Arrow Trail, Auto Road, view corridors, and
Valley Loop Trail. |
Local, long-term, minor, beneficial impact to
Valleywide cultural landscape from removal of current restroom.
Local, long-term, moderate, adverse impact to cultural landscape
from construction of new restroom within key ethnographic resource
area. Local, long-term, moderate, adverse impacts to Hutchings
Orchard site, the millrace feature at the Hutchings sawmill site,
Lost Arrow Trail, Auto Road, and Valley Loop Trail. Local,
long-term, minor, adverse impact to view corridors. |
|
SOCIAL RESOURCES |
|
SCENIC RESOURCES |
|
Local, long-term, moderate, adverse impact on
Lower Yosemite Fall view corridors due to intrusion of existing
restroom and of not maintaining the view corridors |
Local, long-term, moderate, beneficial impact to
Lower Yosemite Fall view corridors (Hutchings and Western Trail view
corridors) from removal of existing restroom and vegetation
management (selective tree trimming). |
Local, long-term, minor, beneficial impact due to
sporadic maintenance of Lower Yosemite Fall view corridors
(Hutchings and Western Trail view corridors). Local, long-term
beneficial impacts due to removal of existing restroom. |
|
VISITOR EXPERIENCE |
|
Overall, there would be long-term, moderate,
adverse impacts to visitor experience due to the lack of restroom
relocation, trail alignment, rehabilitation of trails,
rehabilitation of bridges, and view corridor maintenance under
Alternative 1. |
Local, long-term, moderate, beneficial impact from
increased access to new restroom and removal of cars and buses from
the area. Local, short-term, negligible, adverse impact to visitor
use and experience from noise due to construction and demolition.
Local, long-term, moderate, beneficial impacts from rehabilitated
bridges and trails, increased interpretive exhibits, new picnic
area, and less crowding. |
Local, long-term, moderate, beneficial impact due
from increased access to new restroom and removal of cars and buses
from the area. Local, short-term, negligible, adverse impact to
visitor use and experience from noise due to construction and
demolition. Local, long-term, moderate, beneficial impacts from
rehabilitated bridges and trails, and increased interpretive
exhibits, new seating area, and less crowding. |
|
PARK OPERATIONS AND FACILITIES |
|
Local, long-term, minor, adverse impacts due to
frequent maintenance of existing restroom. |
Local, long-term, minor, beneficial impact from
direct service and emergency vehicle access to the new restroom.
Local, short-term, moderate, adverse impact due to construction of
restroom and rehabilitation of trails and bridges. Local, long-term,
moderate, beneficial impacts due to less maintenance needed for new
facilities. |
Local, long-term, minor, beneficial impact from
direct service and emergency vehicle access to the new restroom.
Local, short-term, moderate, adverse impact due to construction of
restroom and rehabilitation of trails and bridges. Local, long-term,
moderate, beneficial impacts due to less maintenance needed for new
facilities. |
|
RECREATION |
|
Overall, there would be a long-term, negligible
impact to recreation under Alternative 1 because there would be
little noticeable change in recreational opportunities. |
Overall, there would be a long-term, moderate,
beneficial impact to recreation under Alternative 2 due to the
establishment of a picnic/seating area and maintenance of view
corridors. |
Overall, there would be a long-term, moderate,
beneficial impact to recreation under Alternative 3 due to the
establishment of a seating area. |
|
TRANSPORTATION |
|
Local, long-term, minor, adverse impact because
parking area would be retained, and local circulation patterns on
Northside Drive would not change. |
Local, long-term, minor, beneficial impact due to
removal of parking area, and cars and buses. |
Local, long-term, minor, beneficial impact due to
removal of parking area, and cars and buses. |
|
ENERGY CONSUMPTION |
|
Overall, there would be a negligible impact to
energy consumption under Alternative 1, since consumption would be
affected by 5% or less annually. |
Overall, there would be a long-term, negligible,
adverse impact to energy consumption under Alternative 2
because the parking area and buses would be removed from the Lower
Yosemite Fall area but replaced elsewhere in the park. |
Overall, there would be a long-term, negligible,
adverse impact to energy consumption under Alternative 3
because the parking area and buses would be removed from the Lower
Yosemite Fall area but replaced elsewhere in the park. |
|