Lower Yosemite Fall Project
Environmental Assessment
________________________________________________________________________
Yosemite National Park
Lead Agency: National Park Service
ABSTRACT
This Lower Yosemite Fall Project Environmental
Assessment is intended to guide the future of the Lower Yosemite Fall
Project. This environmental assessment addresses actions of the Lower
Yosemite Fall Project that were approved in the Final Yosemite Valley
Plan/Supplemental Environmental Impact Statement (Yosemite Valley
Plan), including those that have changed slightly since the time the Yosemite
Valley Plan Record of Decision was signed in December 2000. A few of
the actions approved by the Yosemite Valley Plan were changed
because new information became available as the site design was refined
for the Lower Yosemite Fall Project.
Three alternatives for the Lower Yosemite Fall Project
are presented in this environmental assessment. Alternative 1 (No Action)
represents conditions and management practices as they currently exist, or
have existed in the recent past, at the Lower Yosemite Fall area. For
example, Bridge #6, currently collapsed, would be rebuilt, and the trails
leading to Bridge #6 would be rehabilitated. Alternative 1 provides the
basis of comparison for the action alternatives (Alternatives 2 and 3).
These two action alternatives are based on the purpose and need for the
project and conform with the goals of Yosemite National Park’s General
Management Plan, the goals and management elements of the Merced
Wild and Scenic River Comprehensive Management Plan, and the goals of
the Yosemite Valley Plan.
Alternative 2 (Preferred) would implement the following
actions approved in the Yosemite Valley Plan for the Lower Yosemite
Fall area, including those with slight changes.
- Restroom Relocation.
The restroom north of the existing parking
area would be removed, and a new restroom would be constructed near what
is currently the southeastern edge of the parking area.
- Parking Area Removal and Establishment of a Small Seating and Picnic
Area.
The existing parking area would be removed. Trails would be
built to access the western trail to the base of Lower Yosemite Fall,
and there would be a small picnic area and informal seating area with
benches, logs, or stones for seating. The remainder of the area would be
revegetated with locally native plants.
- New Shuttle Bus Stop.
A new shuttle bus stop would be located on
the north side of Northside Drive east of the Yosemite Creek Bridge.
- Interim Tour Bus Unloading, Loading, and Parking.
To address
relocation of the tour bus parking area from the Lower Yosemite Fall
area, replacement parking spaces would be provided on an interim basis
for tour buses that currently park in this area. In addition, an interim
bus passenger loading and unloading zone would be provided along
Northside Drive.
- Trail Alignment, Including Relocation of the Eastern Trail Near
Bridge #1.
A realigned trail with elevated boardwalks would be
placed between Bridges #1 and #2 and northwest of Bridge #1. This action
would minimize impacts to the millrace feature within the Hutchings
sawmill site because the boardwalks would be placed above the feature.
- Rehabilitation of Trails.
Pedestrian access to the base of Lower
Yosemite Fall would be on either a rehabilitated western trail (the
existing main access) or a better-defined and hardened eastern trail.
Access to the base of Lower Yosemite Fall for visitors with mobility
impairments would be via the redesigned and hardened eastern trail.
Stock (e.g., horse) use on the trails would be managed as described in
the Yosemite Valley Plan (Vol. IA, page 2-65).
- Rehabilitation, Relocation, and Installation of Bridges.
Five of
the existing historic bridges along the eastern trail would be
rehabilitated to allow wheelchair access throughout the area. A sixth
bridge, the historic bridge across Yosemite Creek at the base of Lower
Yosemite Fall, would be rehabilitated and the viewing platform enlarged.
A seventh bridge would be constructed to complete a loop trail system.
One bridge (#4) would be removed.
- View Corridor Maintenance.
Two historic view corridors through
the Lower Yosemite Fall area (Western Trail view corridor and Hutchings
view corridor) would be maintained by selective trimming of brush and
branches and by selective cutting and removal of trees and vegetation
within these view corridors.
- Removal of Human-Built Rock-Rubble Pile.
Removal of the
human-built rock-rubble pile downstream from the historic Yosemite Falls
Bridge would be preceded by studies, while protecting public health and
safety, thereby ensuring that the action would meet resource objectives.
Alternative 3 would involve the same actions described
for Alternative 2, without change from the Yosemite Valley Plan and
as approved in the Yosemite Valley Plan Record of Decision. The
Alternative 3 actions that differ from Alternative 2 are described below.
- Restroom Relocation.
The restroom north of the existing parking
area would be removed and a new restroom would be constructed east of
Yosemite Creek and north of Northside Drive, adjacent to the future
Lower Yosemite Fall shuttle bus stop.
- Parking Area Removal and Establishment of an Informal Seating Area.
The
existing parking area would be removed, and a portion of the area would
be replaced with an informal seating area. The remainder of the area
would be revegetated with locally native plants.
- Removal of Human-Built Rock-Rubble Pile.
The human-built
rock-rubble pile would be removed without further study, based on the
information presented in the Yosemite Valley Plan.
- Trail Alignment, Including Relocation of the Eastern Trail Near
Bridge #1.
Trail alignment actions would be the same as for
Alternative 2 with the following differences: the trail between Bridges
#1 and #2 would be rehabilitated without a boardwalk, and the trail
northwest of Bridge #1 would be relocated to provide wheelchair
accessibility to the area. The trail northwest of Bridge #1 would be
placed on the millrace feature within the Hutchings sawmill site without
a boardwalk.
If you have questions or comments regarding this
document, you may contact:
Superintendent, Yosemite National Park
ATTN.: Lower Yosemite Fall Project
P.O. Box 577
Yosemite, California 95389
or call: (209) 372-0261
or fax: (209) 379-1294
or visit the planning web site: www.nps.gov/yose/planning